Showing posts with label Performance Evaluations. Show all posts
Showing posts with label Performance Evaluations. Show all posts

Wednesday, October 8, 2014

Training on Construction Bidding and Contracting

I am teaching three courses for NIGP at various locations across the country.  If you're interested in having me teach any of these classes for your NIGP chapter or public agency, please contact Faye Jackson at NIGP directly at FJackson@nigp.org.  If you're within Washington state, contact me directly. Here's a description of the courses.

Maryland State Capitol
in Annapolis
When Bad Things Happen to Bids: Strategies for Ensuring Successful Public Construction Projects:   I was in Annapolis, Maryland on September 12, 2014 teaching this course.  Here's an outline of this one day course: 

Why Aren’t Bidders More Careful?
  • Why Do Bidders Make Mistakes?
  • Missing Bid Prices
  • Conflict Between Numbers and Words
  • Bid Calculation Errors
  • Claims of Error
Is Your Bidder Playing Games?
  • Bid is Too Low
  • Incentive Payments
  • Unbalanced Bids
  • Conditioned or Qualified Bids
Will the Real Low Bidder Please Stand Up?
  • Additive and Alternate Bids
  • Tie Bids
  • Responsive Bids
  • Responsible Bidders
  • Local Bid Preferences
  • Bid Protests and Appeals
  • Conflicts of Interest
What Can You Do to Manage Bidding?
  • What Should Be on the Bid Form?
  • Why Should You Limit Submissions with the Bid?
  • On What Days Should You Not Receive Bids?
  • When is a Bid Late?
  • When Should You Take a Bid Guaranty?
Best Practices in Developing Public Construction Bid Documents:  I'll be teaching this course on October 27 in Savannah, Georgia.  Here's an outline of this one day course:

Principles of Preparation

Formats and Structures
  • Organizational Structures
  • Content Based Systems
  • What Are the Pros and Cons of Using Industry Approved Documents?
Components of Bid Documents
  • Advertisement for Bids
  • Instructions to Bidders
  • Bid Form
  • Payment and Performance Bonds
  • Bidding and Contract Reporting Forms
  • Contract
  • General Conditions / Specifications
  • Technical Specifications
  • Prevailing Wages
  • Specialty Reports and Studies
  • Addenda
Project Review of Bid Documents
  • Do the Bid Documents Reflect Your Objectives?
  • What Provisions Should You Tailor to a Project?
  • Who Should Review the Documents Before Advertisement?
Long Term Review of Bid Documents
  • Baseline Review
  • Annual Review
  • Internal and External Consistency
  • Training
Document Management and Control
  • How Can You Protect Your Standard Documents?
  • Where Should the Standard Documents be Electronically Stored?
  • Who Should Make Changes to Your Standard Documents?
  • How Can You Keep Track of Changes?
Procurement Tools for Ensuring Contractor Performance on Public Construction Projects:  I'll be teaching this class on November 3 in Phoenix, Arizona and then again on November 17 in Hagerstown, Maryland.  Here's an outline of this one day course: 

Is the Contractor Qualified?
  • Pre-qualify Bidders
  • Establish Bidder Responsibility Criteria
  • Specification Qualification Requirements
  • Subcontractor Approval Process
How Can You Manage the Bidding Process?
  • Develop Clear Bidding Documents
  • Optional vs. Mandatory Pre-Bid Meetings
  • Craft Clear Addenda
  • Accept Bidder’s Claim of Error
How Can Bonding Companies Help?
  • Bid Bonds and Other Bid Guaranties
  • Performance Bonds
  • Payment Bonds
  • Warranty Bonds
What Financial Tools Are at Your Disposal?
  • Withhold Retainage
  • Determine and Assess Liquidated Damages
  • Assess Actual Damages
  • Obtain Release of Claims Prior to Payments
What Are Effective Construction Management Practices?
  • Avoid Front-Loaded Schedule of Values
  • Inspect Work Performed
  • Review Pay Applications for Work Completed
  • Manage Claims Process
  • Control Change Orders Approved
Can You Evaluate Contractor Performance?
  • Features of Effective Contractor Performance Evaluation Programs
  • Using Results from Contractor Evaluations
When Can You Award Based on Price and Qualifications?
  • Best Value Procurement
  • Design-Build
  • Construction Manager at Risk
  • Job Order Contracting
Mike Purdy's Public Contracting Blog
© 2014 by Michael E. Purdy Associates, LLC
http://PublicContracting.blogspot.com

Tuesday, March 13, 2012

Obtaining Qualified Contractors on Public Works Projects

Most public agencies are required to award public works projects to the low bidder, and may encounter performance problems with the selected contractor. 

There are a number of strategies available to help ensure that the low bidder is qualified, and how to respond if there are performance problems.

Clear Documents:  Spending the time up front to ensure that the scope of work is clear can help ensure that all bidders are able to submit realistic bids, and that the low bidder will be successful on the project.  Clear contract documents are also an important tool to hold the contractor accountable for performing the work - without unnecessary change orders.  It is important for the agency to review the drawings and specifications prepared by outside architects and engineers to ensure they are clear and reflect the agency's objectives.  If the agency is developing its own drawings and specifications, it is important to review these documents for internal consistency, meeting objectives, and fairness in the bidding process.

Mandatory Bidder Responsibility Criteria:  In Washington State, before a public agency may award a public works project, they must verify that the low bidder meets the mandatory bidder responsibility criteria outlined in RCW 39.04.350.  These criteria address basic registration and compliance issues of the bidder.  They are there to ensure that the contractor awarded the project is a legitimate contractor who pays appropriate taxes and has not been debarred from doing business in the state.  

Supplemental Bidder Responsibility Criteria:  In addition to the Mandatory Bidder Responsibility Criteria, public agencies in Washington State may establish additional or Supplemental Bidder Responsibility Criteria that address the qualifications and experience of the low bidder.  The implementation of these criteria is governed by RCW 39.04.350.  There is a document entitled Suggested Guidelines for Bidder Responsibility that has been developed by the state's Capital Projects Advisory Review Board (CPARB) that provides helpful information for agencies interested in utilizing Supplemental Bidder Responsibility Criteria on public works projects.  Other than selected agencies authorized in state law, most agencies in Washington State may not prequalify contractors. 

Dealing With a Bid That is Too Low:  One of advance signs of a pending problem project is receiving a bid that is significantly lower than the estimate - and significantly lower than the bids of other bidders.  If the low bidder does not submit a claim of error to withdraw their bid, it is a good practice for public agencies to meet with the bidder (before award) to discuss the scope of work and ensure that the bidder has a realistic understanding of the project and the agency's expectations.  Convincing a bidder with a bid that is too low to withdraw their bid is an important preventative measure that can save the agency a lot of grief later on.

Liquidated Damages:  In the event the contractor does not perform the work in a timely manner, the public agency may impose liquidated damages on the contractor for each day past the scheduled substantial completion date that the contractor fails to meet substantial completion.  Liquidated damages are not a penalty and represent an assessment of the agency's likely costs for a project that extends beyond the number of days included in the contract.  Some public agencies, even though they include liquidated damages in their contract, do not often assess the damages.  Liquidated damages are an important tool to help motivate the contractor to complete the work in a timely manner.

Performance Bond:  The surety that issued the performance bond for the project can be an important ally for a public agency when there are performance issues with a contractor (poor workmanship or lack of timely performance).  The bonding company, by issuing the performance bond, has agreed to stand behind the contractor and guaranties to the public agency that the contractor will successfully perform the project in accordance with the contract documents.  Agencies who are experiencing performance problems with a contractor should make it a practice to notify the bonding company so they can work with the contractor to resolve the performance issues.  In Washington State, RCW 39.08 requires that a performance bond be obtained on public works projects.

Termination:  Terminating a public works contract may be either for cause or convenience, and is typically a last resort of a public agency not satisfied with a contractor's performance.  It is important that public works contracts have clear language relating to both termination for cause and convenience.

Performance Evaluations:  At the end of each public works project, some public agencies conduct a formal evaluation of the contractor's performance using a standardized form.  The regular use of a performance evaluation system may be an important tool in the future to ensure that poor performing contractors are not used in the future (by tying it into supplemental bidder responsibility criteria).  Click here for my previous blog entry on 10 key elements of a performance evaluation program.

Summary:  These tools and strategies are part of an overall package that can help public agencies in managing public works projects and ensuring that qualified contractors perform well and in accordance with the agency's needs.
Mike Purdy's Public Contracting Blog 
© 2012 by Michael E. Purdy Associates, LLC 
http://PublicContracting.blogspot.com

Wednesday, January 25, 2012

10 Keys to Establishing a Contractor Performance Evaluation Program

It's important for public agencies to provide systematic and consistent feedback to contractors and consultants.  Such feedback, if structured and documented properly, can be used when considering future awards.

10 Keys:  What does an effective performance evaluation program look like?  Here are a ten items for you to consider as you develop or revise a contractor performance evaluation program:
  1. Written Program:  Establish a written and objective evaluation program.
  2. Criteria and Form:  Use standard evaluation criteria and a standard evaluation form.  Evaluation criteria may differ between construction and consultant contracts, or perhaps for different types of construction contracts.
  3. Training:  Provide training to your agency staff on how to use the performance evaluation program.
  4. Using Results:  Define how the results of the performance evaluations will be used in future award decisions.  Will you debar contractors who receive a certain number of poor performance ratings?  Will you use the ratings to determine a bidder is not responsible, or to impact evaluation of a consultant's qualifications?
  5. Publish Program in Solicitation Documents:  Publish the evaluation program, form, and how the evaluations will be used in the bidding and solicitation documents.  Contractors and consultants should be aware ahead of time how you will measure their performance.
  6. Use Consistently:  Use the performance evaluation program consistency on all projects, not just on projects where the contractor's performance is not acceptable.
  7. Include Written Comments:  Include written comments from evaluators to support the ratings.  Ensure the comments are professional.
  8. Give Contractor a Copy of Scores and Comments:  Provide a written copy of the completed performance evaluation form to the contractor (or consultant).
  9. Appeal Process:  Establish a fair process for the contractor to appeal the evaluation.
  10. Keep Records:  Maintain a database of historical ratings to be used in evaluating qualifications and responsibility on future projects.
Example: The Seattle Housing Authority has a Contractor Performance Evaluation Program.  Click here to review their program.  Click here to review a copy of the evaluation form.
Mike Purdy's Public Contracting Blog 
© 2012 by Michael E. Purdy Associates, LLC 
http://PublicContracting.blogspot.com

Wednesday, January 5, 2011

Federal Contractor Performance Database to be Publicly Accessible Online

Earlier this year, a new database was created that tracks contractors' past performance in order to help federal agencies make responsibility determinations when awarding contracts. New legislation signed this past summer means that large portions of this database will be publicly posted on the Internet. 

The Database (FAPIIS):  In April of 2010, the "Federal Awardee Performance and Integrity Information System" (FAPIIS) took effect (having been originated by the Clean Contracting Act of 2008, a part of the Duncan Hunter National Defense Authorization Act). The system is designed to facilitate consideration of past contractor performance when making contract award decisions.
 
Consolidation of Sources:  FAPIIS pulls information from a number of existing sources, including:
  • Past Performance Information Retrieval System (PPIRS)
  • Central Contractor Registry (CCR)
  • Excluded Parties List System (EPLS)
  • Federal Procurement Data System (FPDS)
Data Included in FAPIIS:  FAPIIS contains contractor information (for the past five years) relating to:
  • past performance evaluations
  • civil, criminal, and administrative proceedings
  • suspensions and debarments
  • non-responsibility or recipient not-qualified determinations
  • terminations for default, cause, or material failure to comply
  • defective pricing determinations
  • administrative agreements issued in lieu of suspensions and debarments
Access to FAPIIS:  Since it was designed to be used to help the federal government make responsibility determinations, FAPIIS was originally intended to be restricted to federal employees involved in contract award decisions, select members of congress, and individual contractors (to verify their own information). However, just a few months after FAPIIS went into effect, a minor provision of the Supplemental Appropriations Act of 2010 amended the use of the database to provide that "... the Administrator shall post all such information, excluding past performance reviews, on a publicly available Internet website."
Mixed Response:  As might be expected, there has been a mixed response to publicly releasing FAPIIS online (most notably, the Professional Services Council, a trade association of government contractors, has expressed concerns about the the release). No date has been set for the launch of the public, online version of FAPIIS. 
More Information:  For more information about FAPIIS, check out the following resources:
Mike Purdy's Public Contracting Blog 
© 2011 by Michael E. Purdy Associates, LLC
http://PublicContracting.blogspot.com

Thursday, August 12, 2010

The Dilemma of Low Bids and Contractor Performance

The Question:  Are public agencies required to award public works construction projects to the low bidder, even if the low bidder has a history of poor performance or a pattern of filing unjustified change order requests and claims?

While there are some tools available to public agencies to help manage the low bid process, those tools must be managed carefully, and even then it may be difficult to disqualify the low bidder.

Not all agencies are authorized to use all of the following tools.  Check your local and state laws to determine if you can use these tools.  The following is a very quick summary introduction to some of the issues involved.

Pre-Qualification:  Under this process, a public agency only accepts bids from contractors who have already gone through a qualifications-based short listing process.  It is often authorized for agencies with specialized work, such as for electrical work.  In theory, it limits the bidding pool only to qualified contractors.

Bidder Responsibility Criteria:  This process is similar to Pre-Qualification except that the review of the contractor's qualifications occurs after the bid submittal deadline instead of before it.  Criteria must be relevant, fair, defensible, and not overly restrictive of the bidding pool.  In Washington State, supplemental bidder responsibility criteria may be used and are outlined in RCW 39.04.350.

References:  Reference checks with previous owners is often a part of a bidder responsibility analysis.  Owners desiring to use references as a means to disqualify a bidder should proceed with caution.  There are often personality conflicts that may have occurred on a previous project that may impact the comments of a reference.  Public agencies should provide bidders who may be disqualified based on reference checks with the opportunity to provide feedback on the comments received.

Performance Evaluation Program:  If implemented correctly, this can be one of the most effective tools for not awarding contracts to contractors with a consistently poor record of performance.  A performance evaluation program should be included in the bidding and contract documents, with clear and relevant evaluation criteria, an appeal process, and how poor performance evaluation scores will be used in making future award decisions.

Think Strategically:  If your agency is facing specific issues about unqualified contractors being awarded projects, it is best to think strategically about the particulars of your situation as well as what is authorized by your state and local laws.  If you would like assistance in thinking through these issues, or in developing a contractor performance evaluation program, please contact me.

Wednesday, June 10, 2009

The Role of Performance Evaluations in Selection

Public agencies are often faced with continuing to use the same contractors and vendors despite poor performance on past contracts, either for the agency or for another organization.

The key to controlling the selection process is to establish an objective performance evaluation program. Important elements of such a program include the following:
  1. Define and publish how the program will be used in making selection decisions so all contractors and vendors are aware of it.
  2. Evaluate all contractors and vendors, not just the ones with poor performance.
  3. Support the ratings with objective and professionally written comments.
  4. Provide for an appeal process if a contractor or vendor disagrees with the ratings.
  5. Maintain a database of the ratings.
  6. Train your personnel in the use of the evaluation program.
  7. Monitor the quality and consistency of the evaluations from a management perspective.
Many public agencies have instituted performance evaluation programs. Where some of them fall short is that the personnel charged with evaluating contractors and vendors fail to provide honest evaluations, either because of a sense that it's too much work to document poor performance, or because they don't want to antagonize the contractor or vendor.

The federal government faces similar concerns with their performance evaluation program, according to a recent report from the Government Accountability Office. To read a brief article on this report, visit the
FederalTimes.com.