Sunday, July 30, 2017

Bid Form Signature Block

This is a follow-up to my recent blog posting about the new Washington state law adding compliance with the state's minimum wage laws as a mandatory bidder responsibility criterion.

Bidder's Place of Signing Bid Form:  I noted that that one option for obtaining the documentation of the bidder's compliance is to include a statement on the bid form.  The bidder would then just sign one document.  Such a signature must be accompanied by a statement that the bidder is signing the bid form under the penalty of perjury.  The revision to RCW 39.04.350 requires compliance with RCW 9A.72.085 which, in addition to the perjury statement requires that the signature block must note the place of signing by the bidder.

Sample Signature Block:  I've included below a signature block that I've used in the past that includes both the perjury statement and place of signing.


Consult With Your Attorney:  Review your bid form and check with your attorney to ensure that your bid form is in compliance with state law, especially if you are including the sworn statement for compliance with minimum wage laws on your bid form.

Mike Purdy's Public Contracting Blog
© 2017 by Michael E. Purdy Associates, LLC
http://PublicContracting.blogspot.com

Monday, July 24, 2017

New Mandatory Public Works Bidder Responsibility Criteria Effective July 23, 2017

The Washington Legislature adopted a new law (Senate Bill 5301) that adds an additional criterion to the list of mandatory bidder responsibility criteria that public agencies must verify and document before awarding any public works project, regardless of cost.  

Effective Date:  The new law became effective on July 23, 2017.  This means that public agencies must ensure that the required sworn statement is obtained prior to award of the public works project. 

Minimum Wage Compliance by Bidder:  The new law establishes a new criterion relating to the contractor's compliance with the state's minimum wage laws.  It also dictates that, prior to award, the contractor must sign a statement that they have not violated the law within a three year period.
  • Criterion:  Here's the language from the law: "Within the three-year period immediately preceding the date of the bid solicitation, not have been determined by a final and binding citation and notice of assessment issued by the department of labor and industries or through a civil judgment entered by a court of limited or general jurisdiction to have willfully violated, as defined in RCW 49.48.082, any provision of chapter 49.46, 49.48, or 49.52 RCW."
  • Documentation:  Here's the language from the law on what is required for documentation: "Before award of a public works contract, a bidder shall submit to the contracting agency a signed statement in accordance with RCW 9A.72.085 verifying under penalty of perjury that the bidder is in compliance with the responsible bidder criteria requirement of subsection (1)(g) of this section.  A contracting agency may award a contract in reasonable reliance upon such a sworn statement." The reference to subsection (1)(g) refers to the "criterion" paragraph above.
Methods for Verifying Bidder's Compliance:  There are a number of options, some better than others, for how a public agency can obtain the required sworn statement from the bidder whose bid is under consideration by the public agency for award. I recommend use of the first option listed below.

  Include Sworn Statement on Bid Form:  This option is the easiest administrative method and least risky option.  I recommend use of this option.  Under this option, a public agency would include the following statement as part of the Bid Form:  "The undersigned Bidder hereby certifies that, within the three-year period immediately preceding the bid solicitation date for this Project, the bidder is not a “willful” violator, as defined in RCW 49.48.082, of any provision of chapters 49.46, 49.48, or 49.52 RCW, as determined by a final and binding citation and notice of assessment issued by the Department of Labor and Industries or through a civil judgment entered by a court of limited or general jurisdiction."  In addition, the following language would need to be part of the signature block for the Bid Form: "I certify (or declare) under penalty of perjury under the laws of the State of Washington that the foregoing is true and correct."  This statement is necessary to comply with the provisions of the new law that dictates that the sworn statement must be in compliance with RCW 9A.72.085.

  Request Sworn Statement from Low Bidder:  Under this option, after bid opening, the public agency would request the low bidder submit the sworn statement after bid opening.  The Municipal Research and Services Center (MRSC) has developed a sworn statement for this purpose.  Click here to visit MRSC's website where you can click on the link for "model certification form."  This is an additional step for the public agency that can be eliminated by including the sworn statement on the Bid Form (see option above). While I don't recommend this option because it is an additional step, there is nothing inherently wrong with this option.

  Include Sample Sworn Statement in Bid Documents:  Under this option, a public agency would include MRSC's model certification form as a sample in the bid documents.  The public agency would still be required to obtain the signed form from the low bidder prior to award, which represents an additional step like the option immediately above. It could be confusing for bidders whether they are required to submit the sample with the bid or after bid opening.  I do not recommend this option.

  Require Separate Sworn Statement be Submitted with the Bid:  Using MRSC's model certification form, under this option, the bid documents would require that the signed sworn statement be submitted with the bid.  This is not a good option, as it increases the risk that a bidder (the low bidder) will fail to submit the sworn statement with the bid, thereby rendering the entire bid non-responsive and unable to be considered further.  Using best practices for public works bidding, public agencies should limit the number of documents submitted with the bid to the Bid Form, bid guaranty, subcontractors list if the project is estimated to cost $1 million or more, and any documents required by federal or state grant provisions. I strongly recommend that public agencies not use this option. 

Other Mandatory Bidder Responsibility Criteria:  The new law adds compliance with minimum wage laws to the existing list of mandatory bidder responsibility criteria that public agencies must verify and document prior to award of any public works project.  The other criteria may be found in RCW 39.04.350.  Review your agency's practices to ensure that you have a process to verify and document the mandatory bidder responsibility criteria for all public works projects. 

Other New Public Works Laws:  See my blog from April 17, 2017 for a description of five new public works laws that do the following:
  • Increases the dollar threshold for when a payment/performance bond may be waived
  • Grants subcontractors additional rights to have retainage released early through a retainage bond
  • Adds an additional criterion to the list of mandatory bidder responsibility criteria
  • Authorizes Public Utility Districts to contract for on-call public works projects
  • Authorizes transit agencies (public transportation benefit area authorities) to use Job Order Contracting
Presidential History Blog:  Check out my Presidential History Blog at PresidentialHistory.com and sign up for a free email subscription to it.


 
Mike Purdy's Public Contracting Blog
© 2017 by Michael E. Purdy Associates, LLC
http://PublicContracting.blogspot.com

Wednesday, January 28, 2015

How Not to Implement Bidder Responsibilty Criteria on a Project

Establishing bidder responsibility criteria on public works construction projects can be a good idea.  It helps ensure that the low bidder is, in fact, capable and qualified to successfully perform the work.  Some public agencies, however, go about implementing responsibility in ways that are counterproductive and lack transparency. 

City of Des Moines, Iowa:  In September 2014, the City of Des Moines adopted what they grandiosely call the "City of Des Moines Taxpayer Quality Assurance Policy."  It only applies for building or facility projects estimated to cost more than $1 million.  In essence, it is intended to be a bidder responsibility law, but it is flawed in a number of ways:
  • More Prequalification than Responsibility:  The law requires that all contractors interested in bidding on a project must complete and submit "no later than two weeks prior to the deadline for accepting bids" a "General Contractor Quality Assurance Questionnaire" and respond to 26 questions.  Establishing bidder responsibility is generally determined after bids have been opened to assess whether the low bidder is responsible.  The City of Des Moines' questionnaire begins to look more like a prequalification process.
  • All bidders must complete questionnaire:  Unlike bidder responsibility practices, the City is requiring all bidders to complete and submit the questionnaire.  Because of the length and complexity of some of the questions, this may cause some bidders to decide not to bid on city work, thus reducing competition and increasing prices, or to bid on the project but increase their prices to recoup their costs in completing the questionnaire and to deal with the hassle of bidding with the City.
  • Responsiveness vs. Responsibility:  The City's practice of requiring the questionnaire prior to bidding makes submission of the form a matter of responsiveness initially before an analysis is even made of whether the bidder is responsible. In other words, if a bidder fails to submit the questionnaire by the deadline, presumably their bid is non-responsive. Documentation of bidder responsibility should never be made part of the bid process, but requested of the low bidder after bid opening.
  • Questionnaire is subjective:  The questions asked by the City are not actual bidder responsibility criteria, but collects information about which the City does not disclose what the basis will be of their evaluation of the questionnaire.  In other words, to properly implement bidder responsibility, there must be actual criteria and standards, so that anyone looking at the documentation submitted should be able to come to the same conclusion about whether the bidder met the criteria or not.  
Misguided effort:  The City of Des Moines' attempt to ensure responsible bidders is ultimately misguided.  It creates a subjective process that will discourage competition and increase costs. The policy also attempts to fix a non-existent problem.  According to the City's engineers, "in general, the City of Des Moines has not experienced major issues in its public bid construction program." Click here to read an excellent and more detailed analysis of the City's law from the law firm of Fabyanske Westra Hart & Thomson. 

Use bidder responsibility criteria:  The preferred method for implementing bidder responsibility is to publish actual criteria in the bid documents, and to then request documentation from the low bidder a certain number of days after bid opening demonstrating that they meet the criteria.  Criteria should be crafted in such a manner to not unduly restrict competition, but to establish a baseline threshold of the ability of the bidder to successfully perform the work.  Click here to read "Suggested Guidelines for Bidder Responsibility" published by the State of Washington's Capital Projects Advisory Review Board.


Presidential History:
  • Presidential History Blog:   While I will discontinue writing this Public Contracting Blog on March 5, 2015, you can sign up for a free email subscription to my Presidential History Blog at www.PresidentialHistory.com.  On a case-by-case basis, I will only be accepting limited consulting and training opportunities after March 5, 2015.
Mike Purdy's Public Contracting Blog
© 2015 by Michael E. Purdy Associates, LLC
http://PublicContracting.blogspot.com

Tuesday, January 20, 2015

Training: Public Works Bidding and Contracting

2 Day Class on "Public Works Bidding and Contracting"

Mike Purdy
When:  February 26-27, 2015 (8:00 am to 5:00 pm) 

Where:  Kennewick, Washington 

Instructor:  Mike Purdy 

Training Outline:  This two day "Public Works Bidding and Contracting" class will cover the following subjects:

  • Types of Public Works Contracts
  • What is a Public Work, Ordinary Maintenance, and Maintenance?
  • On-Call Public Works Contracts and the State Auditor's Office
  • Small Works Rosters
  • Developing Bid Documents
  • Bid Receipt and Opening
  • Bonds and Insurance
  • Bid Responsiveness
  • Bidder Responsibility
  • Bidding and Award
  • Prevailing Wages
  • Change Orders
  • Retainage and Contract Close-out
Cost:
  • $140 - WA NIGP Chapter members
  • $180 - Non-WA NIGP Chapter members
Sponsored by:  Washington State Chapter of NIGP

Information and Registration:  Click here. Don't delay as decision whether there are enough registrants to hold the class must be made in the next week or so.
Mike Purdy's Public Contracting Blog
© 2015 by Michael E. Purdy Associates, LLC
http://PublicContracting.blogspot.com

Wednesday, November 19, 2014

What Requirements Still Apply for Emergency Public Works Contracts?

When a public agency has declared an emergency and waived competitive bidding requirements for a public works construction project, what is being waived is the contractor bidding and selection process.  In other words, under an emergency contract seeking bids is not required.  

Not enough time to conduct a bid process:  The nature of emergencies dictates that there is not sufficient time to conduct a bid process without raising the risk that individuals may be injured, property damaged, or that the essential functions of government may not be fulfilled.  The definition of an emergency public work varies by state. In Washington state, it is defined in RCW 39.04.280. 

What is required for emergencies:  The following is a list of some of the requirements that still apply for emergency public works projects.  Generally, only the selection process is waived through the emergency declaration.  While this list is based on Washington state law, portions of it may also apply for other states, depending on their specific requirements:
  • Declaration of emergency:  A formal declaration of an emergency must be made.  See RCW 39.04.280.
  • Bidder Responsibility:   The mandatory bidder responsibility criteria of RCW 39.04.350 still apply for emergency contracts.
  • Contract:  There should still be a public works contract documenting the various requirements and the dollar amount of the project, even if it is for a time and materials, not-to-exceed amount.
  • Prevailing wages:  Prevailing wages must still be paid consistent with the requirements of RCW 39.12.
  • Intent:  A Statement of Intent to Pay Prevailing Wages must be approved by the Department of Labor and Industries and filed with the public agency prior to making any payments to the contractor.  A separate Intent must be completed for the contractor and each subcontractor, regardless of tier.
  • Affidavit:  An Affidavit of Wages Paid must be approved by the Department of Labor and Industries and filed with the public agency prior to making payment of retainage to the contractor.  A separate Affidavit must be completed for the contractor and each subcontractor, regardless of tier.
  • Bonds:  A payment and performance bond must be submitted to the agency for the work, in accordance with RCW 39.08.
  • Insurance:  The amounts and types of insurance required on a public works project are governed by each agency and not by Washington state law. 
  • Retainage:  Retainage should be withheld from each progress payment.  See RCW 60.28.  The only exceptions to not withholding retainage is if a retainage bond is submitted by the contractor or if the contractor was selected through the Limited Public Works process under the Small Works Roster (for public works projects less than $35,000), in which case there would have been no need to waive the competitive bidding process.
Timing of emergencies:  While the above items are still required under Washington state law for an emergency public work, agencies must ensure that health, safety, and property are protected and that an agency's essential functions continue to serve the public.  Sometimes, due to the emergency nature of the project, it is important to get a contractor on the job site immediately, perhaps in the middle of the night, to address the emergency.  In such a case, often some of the paperwork requirements are addressed after the fact. 

Emergency procedures:  Washington state law does not have exemptions for public works requirements on emergency projects, other than for the actual bidding and selection process.  It is important that each public agency have clear emergency public works procedures that will dictate:
  • Compliance:  The timing of compliance with the requirements of state law.
  • Authorization:  Who within the agency is authorized to declare an emergency and waive competitive bidding.  This person or persons should be available at any time, which is why it is often problematic to dictate that only an elected board or council may waive competitive bidding.
Mike Purdy's Public Contracting Blog
© 2014 by Michael E. Purdy Associates, LLC
http://PublicContracting.blogspot.com

Wednesday, October 8, 2014

Training on Construction Bidding and Contracting

I am teaching three courses for NIGP at various locations across the country.  If you're interested in having me teach any of these classes for your NIGP chapter or public agency, please contact Faye Jackson at NIGP directly at FJackson@nigp.org.  If you're within Washington state, contact me directly. Here's a description of the courses.

Maryland State Capitol
in Annapolis
When Bad Things Happen to Bids: Strategies for Ensuring Successful Public Construction Projects:   I was in Annapolis, Maryland on September 12, 2014 teaching this course.  Here's an outline of this one day course: 

Why Aren’t Bidders More Careful?
  • Why Do Bidders Make Mistakes?
  • Missing Bid Prices
  • Conflict Between Numbers and Words
  • Bid Calculation Errors
  • Claims of Error
Is Your Bidder Playing Games?
  • Bid is Too Low
  • Incentive Payments
  • Unbalanced Bids
  • Conditioned or Qualified Bids
Will the Real Low Bidder Please Stand Up?
  • Additive and Alternate Bids
  • Tie Bids
  • Responsive Bids
  • Responsible Bidders
  • Local Bid Preferences
  • Bid Protests and Appeals
  • Conflicts of Interest
What Can You Do to Manage Bidding?
  • What Should Be on the Bid Form?
  • Why Should You Limit Submissions with the Bid?
  • On What Days Should You Not Receive Bids?
  • When is a Bid Late?
  • When Should You Take a Bid Guaranty?
Best Practices in Developing Public Construction Bid Documents:  I'll be teaching this course on October 27 in Savannah, Georgia.  Here's an outline of this one day course:

Principles of Preparation

Formats and Structures
  • Organizational Structures
  • Content Based Systems
  • What Are the Pros and Cons of Using Industry Approved Documents?
Components of Bid Documents
  • Advertisement for Bids
  • Instructions to Bidders
  • Bid Form
  • Payment and Performance Bonds
  • Bidding and Contract Reporting Forms
  • Contract
  • General Conditions / Specifications
  • Technical Specifications
  • Prevailing Wages
  • Specialty Reports and Studies
  • Addenda
Project Review of Bid Documents
  • Do the Bid Documents Reflect Your Objectives?
  • What Provisions Should You Tailor to a Project?
  • Who Should Review the Documents Before Advertisement?
Long Term Review of Bid Documents
  • Baseline Review
  • Annual Review
  • Internal and External Consistency
  • Training
Document Management and Control
  • How Can You Protect Your Standard Documents?
  • Where Should the Standard Documents be Electronically Stored?
  • Who Should Make Changes to Your Standard Documents?
  • How Can You Keep Track of Changes?
Procurement Tools for Ensuring Contractor Performance on Public Construction Projects:  I'll be teaching this class on November 3 in Phoenix, Arizona and then again on November 17 in Hagerstown, Maryland.  Here's an outline of this one day course: 

Is the Contractor Qualified?
  • Pre-qualify Bidders
  • Establish Bidder Responsibility Criteria
  • Specification Qualification Requirements
  • Subcontractor Approval Process
How Can You Manage the Bidding Process?
  • Develop Clear Bidding Documents
  • Optional vs. Mandatory Pre-Bid Meetings
  • Craft Clear Addenda
  • Accept Bidder’s Claim of Error
How Can Bonding Companies Help?
  • Bid Bonds and Other Bid Guaranties
  • Performance Bonds
  • Payment Bonds
  • Warranty Bonds
What Financial Tools Are at Your Disposal?
  • Withhold Retainage
  • Determine and Assess Liquidated Damages
  • Assess Actual Damages
  • Obtain Release of Claims Prior to Payments
What Are Effective Construction Management Practices?
  • Avoid Front-Loaded Schedule of Values
  • Inspect Work Performed
  • Review Pay Applications for Work Completed
  • Manage Claims Process
  • Control Change Orders Approved
Can You Evaluate Contractor Performance?
  • Features of Effective Contractor Performance Evaluation Programs
  • Using Results from Contractor Evaluations
When Can You Award Based on Price and Qualifications?
  • Best Value Procurement
  • Design-Build
  • Construction Manager at Risk
  • Job Order Contracting
Mike Purdy's Public Contracting Blog
© 2014 by Michael E. Purdy Associates, LLC
http://PublicContracting.blogspot.com

Thursday, May 8, 2014

Training: Competitive Public Construction Bidding

Competitive Public Construction Bidding

When:  May 13, 2014 (1:00 p.m. to 5:00 p.m.) 

Where:

  • Seattle, Washington (City University, 521 Wall Street) or
  • Live Webcast
Agenda: 
  • Strategic Decision Making for Selecting the Most Appropriate Public Works Project Delivery Method (Linneth Riley-Hall, Sound Transit)

  • Using Contractor Responsibility Criteria for Public Works Contract Bidding (W. Gregory Guedel, Foster Pepper PLLC)

  • Tools for Ensuring Contractor Performance on Public Works Projects (Mike Purdy, Michael E. Purdy Associates, LLC)

  • The Top 10 Things to Know About Public Works Contracting (Aleanna Kondelis, City of Seattle)
Sponsored by: The Seminar Group 

Cost:
 
  • $325 - Single registration
  • $275 - Government employee
  • As one of the faculty for this training, The Seminar Group will provide my blog readers with a $50 per person discount off of the regular tuition rate.  Call The Seminar Group to register and mention Mike Purdy and the discount code "FAC50."
  • Other rates available - see website
Information and registration:  Click here.
Mike Purdy's Public Contracting Blog
© 2014 by Michael E. Purdy Associates, LLC
http://PublicContracting.blogspot.com

Wednesday, March 12, 2014

Is An Unreasonably Low Bid Non-Responsive?

Is an unreasonably low bid on a public works construction project non-responsive, or is the bidder not responsible, or neither?  

Bid tabulation:  Let's say that low bid came in at $25,000, with the second low bid at $160,000, and the third low bid at $180,000.  The engineer's estimate for the project was $200,000.

Responsiveness:  If the low bidder responded in accordance with all of the requirements of the bid documents, their bid would be responsive.  In other words, did they submit their bid on time, sign the bid form, include the required bid guaranty, etc.? 

Responsibility:  While responsiveness always relates to the bid, responsibility relates to the bidder and whether they are capable and qualified to perform the work.  Different states have different requirements for establishing responsibility.  In Washington, a public agency may include bidder responsibility criteria in the bid documents to evaluate after bid opening whether the low bidder met those relevant criteria and is capable of performing the work.  If no responsibility criteria were included, a very low bid would not be enough to find the bidder not a responsible bidder.  If bidder responsibility criteria were included in the bid documents, as long as the bidder met them, a public agency could not determine that a very low bid price made them not responsible. 

Meet with the bidder:  When faced with an unreasonably low bid, a public agency should meet with the bidder to review their understanding of the scope of work and how they estimated the project.  In the example bid tabulation above, it appears that the bidder didn't include all of the work in its bid.  In meeting with the bidder, the public agency would try to convince the bidder to withdraw their bid, rather than risk almost certain financial losses and a problem project.
Mike Purdy's Public Contracting Blog
© 2014 by Michael E. Purdy Associates, LLC
http://PublicContracting.blogspot.com

Tuesday, March 4, 2014

Are Reincarnated Construction Companies Responsible Bidders?

As a public agency, you've had less than satisfactory experiences with a particular contractor that has not performed well and that has left a trail of lawsuits and claims on previous projects.  Perhaps you've included bidder responsibility criteria in your bid documents to help ensure that the contractor will not meet the objective criteria and is not awarded future projects. 

Reincarnated contractor:  But what if the contractor closes down the construction company and the same owner simply re-opens a new construction company?  It's highly likely that you will continue to experience the same problems with the reincarnated company.  Is there anything you can do about this? 

Bidder responsibility criteria:  The Washington State Capital Projects Advisory Review Board (CPARB) has published Suggested Guidelines for Bidder Responsibility that outlines tools for public agencies to use in developing what is known as Supplemental Bidder Responsibility Criteria.  Here are a couple of the generic criteria included in the Guidelines:
  • Claims Against Retainage and Bonds:   The Bidder shall not have a record of excessive claims filed against the retainage or payment bonds for public works projects during the previous three years, that demonstrate a lack of effective management by the Bidder of making timely and appropriate payments to its subcontractors, suppliers, and workers, unless there are extenuating circumstances and such circumstances are deemed acceptable to the Owner.
  • Lawsuits:     The Bidder shall not have lawsuits with judgments entered against the Bidder within five years of the bid submittal date that demonstrate a pattern of failing to meet the terms of contracts, unless there are extenuating circumstances and such circumstances are deemed acceptable to the Owner. 
Responsibility criteria addressing ownership:  The challenge with the responsibility criteria above is that it does not address a company with a poor record that has simply opened up a new company with the same ownership.  Here are some suggested edits to the criteria that may help to address this situation:
  • Claims Against Retainage and Bonds:   The Bidder shall not have a record of excessive claims filed against the retainage or payment bonds for public works projects during the previous three years, that demonstrate a lack of effective management by the Bidder of making timely and appropriate payments to its subcontractors, suppliers, and workers, unless there are extenuating circumstances and such circumstances are deemed acceptable to the Owner.  For the purpose of this criterion, "Bidder" shall include the registered construction company submitting the bid, as well as the owner(s) of the company and any other construction companies the owner(s) may currently or previously have owned.
  • Lawsuits:     The Bidder shall not have lawsuits with judgments entered against the Bidder within five years of the bid submittal date that demonstrate a pattern of failing to meet the terms of contracts, unless there are extenuating circumstances and such circumstances are deemed acceptable to the Owner.  For the purpose of this criterion, "Bidder" shall include the registered construction company submitting the bid, as well as the owner(s) of the company and any other construction companies the owner(s) may currently or previously have owned.
Talk with your attorney:  Think strategically about what Supplemental Bidder Responsibility Criteria you include in your bid documents, and talk with your attorney as you develop language to deal with ownership of previous construction companies as part of the criteria.

Mike Purdy's Public Contracting Blog
© 2014 by Michael E. Purdy Associates, LLC
http://PublicContracting.blogspot.com

Tuesday, December 3, 2013

Why You Shouldn't Ask About a Bidder's Qualifications...with the Bid

Most public agencies awarding a public works construction project are required to award to the bidder with the lowest responsive bid.  This is the traditional model of low bid also known as "Design-Bid-Build." 

Is the bidder responsible?  But the low bidder may not necessarily be a responsible bidder.  See my previous blog on the subject.  To assess whether a bidder is a responsible bidder, the bidder should meet specific, relevant, and objective criteria established in the bid documents.

4 reasons to not ask for qualifications with the bid:  There are four main reasons why public agencies should not request documentation of a bidder's qualifications, or how they meet responsibility criteria, with the bid.  Instead, this information should be requested from the low bidder after bids have been opened.

  • Non-responsive bids:  By asking for bidder qualifications with the bid, there is a risk that a bidder (perhaps the low bidder) may fail to provide some or all of the information required.  If the information must be submitted as part of the bidding process, the lack of submitting this information would render the bid non-responsive.  Non-responsive bids may result in protests, delays, and higher project costs.
  • Burden to bidders:  Asking for bidder qualification documentation with the bid requires all bidders to submit this documentation, which often takes time for bidders to pull together.  The best practice is to request this information only from the low bidder (or if there are schedule concerns from maybe one or two other bidders), which means it would be submitted after the bid submittal deadline.
  • Focusing on bid price:  If you ask for bidder qualification information to be submitted with the bid, this takes away valuable time from bidders to focus on preparing the most competitive bid price.  The process of developing a bid is often a last minute process.  Bidders wait until minutes before the deadline to obtain subcontractor and supplier bids who are delaying the submission of their prices in order to avoid having bidders "shop" their bid prices for a better deal with another subcontractor. 
  • Limited number of bidders:  As bidders evaluate what projects to bid on, they will often make the decision to bid on projects that have fewer bidding requirements.  Bidders have limited time and staffing to prepare bids and requiring too much information to be submitted with the bid may reduce the number of bidders who submit bids (which may result in higher prices).
State laws vary:  Individual states have different laws and requirements about bidder responsibility.  In Washington state, public agencies may develop and use Supplemental Bidder Responsibility Criteria in assessing whether the low bidder is responsible.  RCW 39.04.350 describes the process and the Suggested Guidelines for Bidder Responsibility of the Capital Projects Advisory Review Board (CPARB) provides helpful suggestions and tools regarding bidder responsibility.

Summary:  It is important to obtain qualified contractors on public works construction projects, and this can  be accomplished through evaluating the responsibility or qualifications of the low bidder.  By keeping the bidding process as uncomplicated as possible, public agencies reduce the risk of non-responsive bids, avoid burdening all bidders with requirements, allow bidders to focus on developing competitive prices, and limit the risk of reduced numbers of bidders who opt to bid on less complicated projects.

Mike Purdy's Public Contracting Blog
© 2013 by Michael E. Purdy Associates, LLC
http://PublicContracting.blogspot.com

Tuesday, November 19, 2013

Do Your Contracts Address Subcontractor Responsibility Criteria and Verification?

Whether you are a public agency, contractor, or subcontractor doing public works construction in the State of Washington, you should review your contracts to ensure they address the subcontractor responsibility requirements of RCW 39.06.020.  Here's what that law states:
A public works contractor must verify responsibility criteria for each first tier subcontractor, and a subcontractor of any tier that hires other subcontractors must verify responsibility criteria for each of its subcontractors. Verification shall include that each subcontractor, at the time of subcontract execution, meets the responsibility criteria listed in RCW 39.04.350(1) and possesses an electrical contractor license, if required by chapter 19.28 RCW, or an elevator contractor license, if required by chapter 70.87 RCW. This verification requirement, as well as the responsibility criteria, must be included in every public works contract and subcontract of every tier. (emphasis added)
Action steps:  
  • Public agencies:  Do your contracts address subcontractor responsibility criteria and the verification process?
  • Contractors and subcontractors:  Do your contracts address subcontractor responsibility criteria and the verification process?
  • CPARB language:  The Capital Projects Advisory Review Board (CPARB) has adopted Suggested Guidelines for Bidder Responsibility that includes suggested language on this issue for public works contracts for agencies and contractors.  Click here for CPARB's website where you can view the Guidelines.
Mike Purdy's Public Contracting Blog
© 2013 by Michael E. Purdy Associates, LLC
http://PublicContracting.blogspot.com

Wednesday, November 13, 2013

Why Bidders Are Never Non-Responsive

Why are bidders never non-responsive?  It's somewhat of a trick question, but it illustrates an important point. 

Responsiveness vs. Responsibility:  Responsiveness in public bidding always relates to a bid, while responsibility relates to a bidder.  To be responsive, a bid must be in compliance with the requirements of the bid documents.  To be responsible, a bidder must be capable and qualified to perform the work.  In other words, a bidder is never responsive or non-responsive.  It's their bid that is either responsive or non-responsive. 

Responsiveness questions:  Here are some of the common questions that should be asked about whether a bid is responsive and in compliance with all of the requirements of the bid documents, or whether a bid is non-responsive:
  • Bid submission location:  Was the bid submitted at the correct location identified in the bid documents?
  • Timeliness of bid submission:  Was the bid submitted prior to the deadline established in the bid documents?
  • Signed bid form:  Was the bid form signed?
  • Bid guaranty:  Was a bid guaranty or bid deposit (bid bond, cashier's check, certified check, cash) in the appropriate amount submitted with the bid?
  • Bid prices:  Does the bid include a bid price for all items identified on the bid form?
  • Bid form blanks:  Were all blanks on the bid form filled out completely?
  • Addenda:  Were all addenda acknowledged on the bid form?
  • Bid exclusions:  Did the bid include any exclusions or conditions different from the requirements of the bid documents?
Material vs. Immaterial Irregularities:  Should all bids with irregularities automatically be rejected as non-responsive?  Not necessarily.  There's a difference in the type of bid irregularities.  Some are material and others are immaterial.  In other words, a material irregularity in a bid is one that is significant and gives a competitive advantage or benefit to one bidder not enjoyed by other bidders.  Material irregularities in a bid should result in the bid being rejected as non-responsive and not considered further.  On the other hand, an immaterial irregularity in a bid does not give one bidder a competitive advantage or benefit not enjoyed by other bidders.  A bid with an immaterial irregularity may be accepted as responsive, or at the discretion of the public agency, may be rejected as non-responsive.

Is the bidder responsible?  While responsiveness relates to whether the bid complied with the requirements of the bid documents, responsibility assesses whether the bidder is capable and qualified to perform the work.  

Different laws on responsibility:  Laws differ regarding the amount of discretion a public agency may have in determining that the bidder with a low responsive bid is or is not a responsible bidder.  There is a spectrum of authority for public agencies in establishing bidder responsibility:
  • Significant discretion:  Some public agencies have broad discretion and judgment in making the determination of responsibility
  • Limited discretion:  Some public agencies permit a bidder responsibility analysis within certain bounds.  For example, in the State of Washington, all bidders on public construction projects must meet a half-dozen mandatory bidder responsibility criteria before being awarded a project.  In addition, agencies in Washington are permitted to establish additional relevant bidder responsibility criteria on a project-by-project basis to be used in making a responsibility analysis.  RCW 39.04.350 governs bidder responsibility in the State of Washington. 

  • Almost no discretion:  Some public agencies must almost always award to the bidder with the low responsive bid, regardless of capability or past performance concerns. 
Check your language:  I often see language in bid documents that notes the intent of a public agency to award the project to the "lowest responsive and responsible bidder."  This type of language blurs the important distinction between responsiveness and responsibility.  Instead, bid document language should reflect that the agency will award to the "responsible bidder with the lowest responsive bid," or something similar. 

Case by case:  Evaluating whether a bid is responsive and whether a bidder is responsible are determined on a case by case basis, dependent on the specific facts and the language of the bid documents.  It's important to involve the public agency's attorney in making these determinations, and in assessing how defensible a particular position is to a protest or lawsuit.  

The question:  "Why are bidders never non-responsive?"  Bidders are never non-responsive, even though their bid may be non-responsive.  A bidder, however, may be determined to not be a responsible bidder, making them ineligible to be awarded a project. 
Mike Purdy's Public Contracting Blog
© 2013 by Michael E. Purdy Associates, LLC
http://PublicContracting.blogspot.com

Sunday, October 13, 2013

Training: Bid Responsiveness and Bidder Responsibility

Bid Responsiveness and Bidder Responsibility:  Responsiveness and Responsibility.  They sound very similar but are very different concepts.  This training will provide key background information and examples on how public agencies should evaluate whether bids are responsive or non-responsive, and how to help ensure that the low bidder is a responsible bidder. 

Where and When:  Four training sessions in Washington state, all from 10:00 a.m. to 2:30 p.m.
  • Renton (October 31, 2013)
  • Yakima (November 5, 2013)
  • Camas (November 13, 2013)
  • Everett (November 21, 2013)
Cost:  Free 

Instructors:
  • Mike Purdy
  • John Carpita, MRSC
Sponsored by:
  • APWA Washington Chapter, Contract Administration Subcommittee
  • MRSC (Municipal Research and Services Center)
Information and registration:  Click here.

Mike Purdy's Public Contracting Blog
© 2013 by Michael E. Purdy Associates, LLC
http://PublicContracting.blogspot.com

Wednesday, September 11, 2013

Demystifying Public Works Bidding and Contracting

On September 5, 2013, I was in Ephrata, Washington providing an all day training session for the Grant County Public Utility District staff on Demystifying Public Works Bidding and Contracting.

Here's an outline of the training I provided:

Types of Public Works Contracts
  • By agency staff
  • Advertised Public Works
  • Small Works Roster (Limited public works)
  • On-Call Public Works
  • Alternative Public Works (GC/CM, Design-Build, Job Order Contracting)
Bid and Agency Limits on Performing Public Works

What is a Public Work? 
  • What is Ordinary Maintenance?
  • Is Maintenance a Public Work?
Why Aren't Bidders More Careful?
  • Why Do Bidders Make Mistakes?
  • Missing Bid Prices
  • Conflict Between Numbers and Words
  • Bid Calculation Errors
  • Claims of Error
Is Your Bidder Playing Games?
  • Bid is Too Low
  • Unbalanced Bids
  • Conditioned or Qualified Bids
Will the Real Low Bidder Please Stand Up?
  • Additive and Alternate Bids
  • Tie Bids
  • Responsive Bids
  • Responsible Bidders
  • Local Bid Preference
  • Bid Protests and Appeals
When You Don't Want a Check
  • Purpose of Bid Guarantees
  • Types of Bid Guaranties
  • The Risks of Checks
  • Are Bid Guarantees Required on Small Works Roster Projects?
  • Amount of Bid Guarantees
  • Restrictions on Bid Bond Amounts
  • What is a Power of Attorney?
  • How Much Does a Bid Bond Cost?
  • When Should You Return Bid Bonds?
  • Checklist for Bid Bonds
Payment and Performance Bonds
  • Purpose of Payment and Performance Bonds
  • Why Should You Get 2 Separate Bonds?
  • Bonds vs. Insurance
  • Are Bonds Required on All Public Works Projects?
  • When Should the Bonds Be Obtained?
  • What Happens if You Fail to Get the Bonds?
  • Should the Bonds Cover Change Orders?
  • Should the Bonds Cover Sales Tax?
  • Are Bonds Ever Forged?
  • What Happens if the Contractor Defaults?
  • Checklist for Bonds
When Bad Things Happen During Construction
  • Front Loaded Schedule of Values
  • Dealing with a Change Order Artist
  • Prevailing Wages Not Paid
  • Subcontractors and Suppliers Not Paid
  • Work Not Completed on Time
  • Punch List Work Not Completed
  • Warranty Work Ignored by Contractor
Public Works Contract Close-out
  • Who Does Retainage Protect?
  • Completion Dates
  • Filing, Renewing, and Releasing Claims
  • Pre-Claim Notices
  • Foreclosure and Payment
  • Release of Retainage
  • What Happens if There's Not Enough Retainage
  • Check Your Bidding and Contract Documents
Questions:  If you'd like to talk about me providing this training for your agency or association, please contact me.
Mike Purdy's Public Contracting Blog 
© 2013 by Michael E. Purdy Associates, LLC 
http://PublicContracting.blogspot.com

Tuesday, August 20, 2013

Obtaining Qualified Contractors on Public Construction Projects

Traditionally, public agencies have awarded public construction projects to the low bidder.  In theory, this ensures that the public pays the lowest possible cost for such work.  However, the low bid doesn't always result in the lowest price at the end of the project, nor does it ensure that the low bidder is capable of performing quality work.

Agencies seek more flexibility in award:  In response to concerns about low bidders not performing well and arguing for change orders that will increase the contract cost, public agencies have increasingly been developing alternative methods for awarding public construction projects.  These alternative methods come with their own set of challenges and may actually cost more money, depending on how the selection process is implemented.

Design-Bid-Build:  The following three approaches, based on contractors bidding a fully designed scope of work, are sometimes used by public agencies for ensuring that the contractor selected is qualified to perform the work:

Prequalification:  Under this scenario, contractors must be prequalified and meet certain criteria before being permitted to bid on a project.  Some public agencies are not authorized to prequalify contractors.  For those that are authorized to prequalify contractors, it is important that the criteria used to evaluate qualifications be clear, objective, and not overly restrictive of the bidding pool of contractors.

Bidder Responsibility:   In many cases, bidder responsibility criteria are the same as the prequalification criteria.  The only difference is that all contractors may bid a project rather than just prequalified contractors.  The low bidder must then demonstrate they meet the bidder responsibility criteria.  Prequalification analysis occurs prior to bidding, while bidder responsibility evaluation occurs after bidding, but prior to award.  Like prequalification, bidder responsibility inserts an element of subjectivity into the award process.

Best Value:  A best value selection process moves away from price as the only basis for identifying the successful contractor and instead begins to looks more like a Request for Proposals process, where various evaluation criteria are identified, including price.  Not all public agencies are authorized to conduct a best value selection process, and the process is often criticized for its subjectivity with the result that the public agency may contract with the firm who does not have the lowest bid.

Alternative Project Delivery Methods:  The following two alternative project delivery methods are gaining in popularity with public agencies.  Unlike the models used under a Design-Bid-Build approach, the design is not complete when the contractor is selected under the following two alternative methods:

Construction Manager at Risk:  This process is known by many different names (CM at Risk, CMAR, GC/CM (General Contractor/Construction Manager), and CM/GC (Construction Manager/General Contractor)).  Not all public agencies are authorized to use this process which involves selection of a contractor early in the design process, through a Request for Proposals process, partially based on qualifications and partially based on limited pricing (fee and general conditions work).  The selected contractor then works with the designer in providing various preconstruction services (cost estimating, scheduling, constructability reviews, value engineering, etc.) before the construction cost is negotiated between the parties when the design is sufficiently completed. 

Design-Build:  Under this project delivery method, the public agency uses a Request for Proposals process to select one firm to both design and build the project, eliminating or reducing conflicts between the designer and contractor.  The price is either part of the selection process (which brings with it many of the problems of the traditional low bid award), or the price is negotiated between the partieis when the design is sufficiently complete.  

Indefinite Delivery/Indefinite Quantity:  Also known as IDIQ, this method of public construction is basically an on-call process, in which undefined work is bid ahead of time and one contractor is selected, sometimes based on price alone and sometimes based on price and qualifications.  There are two major forms that IDIQ public construction contracts take:

Job Order Contracting:  Under Job Order Contracting, a contractor is selected partially based on qualifications and partially based on their markup percentage for serving as the general contractor for undefined work that will be assigned as the needs arise.  Establishing the cost of a specific project is typically based on an agreed upon unit price book.  Nevertheless, the contractor and agency must still negotiate the specific cost of work to ensure that units and quantities used in the estimate are appropriate.  Job Order Contracting is sometimes criticized for being more expensive than the traditional low bid process, but it is a more efficient process for ensuring that work is performed in a timely manner.

On-Call Contracting:  On-call construction contracting differs from Job Order Contracting in the selection process in that specific units of work are bid as part of the selection process (rather than relying upon a unit price book).  While the contractor in Job Order Contracting may be required to subcontract out major portions of the work, under on-call contracting, the contractor often performs all or most of the work themselves.  On-Call contracting is an effective tool for minimizing multiple invitations to bid for what are typically smaller dollar amount projects.  

General comments:
  • How much are bidder qualifications worth?  In most of the methods described above, there is some level of subjectivity involved in the selection process as a public agency evaluates and scores bidders based on qualifications and experience.  The result is that the low bidder may not end up being the selected bidder, or the price may be negotiated.  
  • Maintaining fairness and transparency:  In selecting contractors based on factors other than the low price, it is important that the process established be fair and transparent, and that the qualifications and proposals of contractors be rated as objectively as possible.  The low bid process was originally established to avoid public agencies showing favoritism to certain contractors.  Public agencies are now recognizing that the low bidder isn't always the best option for the public.  But in expanding the scope of selection methodologies, there is the risk of shifting back into an environment of favoritism to certain contractors.  These alternative tools must be managed carefully and thoughtfully.
  • Not all agencies authorized to use all methods:  Not all public agencies are authorized to use some of the selection methods outlined here.  State laws differ.  In addition, if there are federal funds involved with a project, public agencies need to work closely with the federal department granting the money to ensure that the selection process complies with federal regulations.
Mike Purdy's Public Contracting Blog 
© 2013 by Michael E. Purdy Associates, LLC 
http://PublicContracting.blogspot.com

Wednesday, August 14, 2013

How Much Are Bidder Qualifications Worth?

The San Antonio Housing Authority (SAHA) recently paid $94,000 more for a construction project because they took the second lowest price, instead of the lowest price.  The second lowest price had better overall qualifications.

Best Value Selection:  SAHA defended their action stating that their evaluation process was not based on the awarding to the low bid, but they assigned points to the bidders based on other factors, including the following, that would ensure they obtained the best value contractor:
    • Oversight and Planning
    • Scheduling
    • Safety and Warranty
    • Price
    • Strength of Section 3 participation
    • Contractor's Women and Minority Business Enterprise plan
Different from Bidder Responsibility:  Rather than just evaluating the qualifications of the low bidder based on bidder responsibility criteria, SAHA assigns points to each of these criteria and then awards to the contractor with the highest number of points, even though their price might not be the lowest price.  

Protest:  SAHA's practice recently led to complaints being filed by a contractor whose bid was $94,000 lower than the bidder awarded the project.  According to SAHA, the protesting bidder's scores on the non-price related factors were not as high as the contractor's who was awarded the project.

What is permitted?  Not all agencies are authorized to conduct a best value selection process using a Request for Proposals for construction projects.

More information:  Click here for more details about the SAHA controversy.
Mike Purdy's Public Contracting Blog 
© 2013 by Michael E. Purdy Associates, LLC 
http://PublicContracting.blogspot.com

Tuesday, August 6, 2013

The Risks of Requiring Use of Specific Subcontractors

Not all subcontractors are created equal.  There are good ones and ones that a public agency may prefer not be used on their projects, based on past performance issues.

The Question:  May a public agency require use of a specific subcontractor, or prohibit use of certain subcontractors?

Risks:  Here are three risks associated with asking or requiring a contractor to substitute a subcontractor they have planned to use with a different subcontractor:
  • Cost:  Since the contractor's bid was based on the use of specific subcontractors, requiring the contractor to use a different subcontractor may result in added costs to the contractor that the contractor will want to pass onto the public agency.  In essence, the substitution request or requirement of the public agency represents a changed condition from the bid documents in which the contractor was free to select their own subcontractors.  
  • Liability:  If a public agency dictates the use of a specific subcontractor and there are any problems associated with the subcontractor's performance, the contractor will assert that the public agency is responsible for any added costs, since the contractor was forced to use a subcontractor not of their own choosing.
  • Third party action:  The substituted subcontractor may take action against both the contractor and the public agency, alleging that they were improperly removed from the project.  Depending on the outcome of such an action, that could end up in court, the public agency may be required to pay damages to the substituted subcontractor.
Strategies:  One of the best strategies for ensuring that qualified subcontractors are used on the project is to establish bidder responsibility criteria related to subcontractors that the contractor would need to demonstrate were met prior to being deemed a responsible contractor and being awarded the contract.  In Washington state, RCW 39.04.350 permits public agencies to establish supplemental bidder responsibility criteria that may relate to the qualifications and experience of the contractor, subcontractors, and key personnel.