Tuesday, August 20, 2013

Obtaining Qualified Contractors on Public Construction Projects

Traditionally, public agencies have awarded public construction projects to the low bidder.  In theory, this ensures that the public pays the lowest possible cost for such work.  However, the low bid doesn't always result in the lowest price at the end of the project, nor does it ensure that the low bidder is capable of performing quality work.

Agencies seek more flexibility in award:  In response to concerns about low bidders not performing well and arguing for change orders that will increase the contract cost, public agencies have increasingly been developing alternative methods for awarding public construction projects.  These alternative methods come with their own set of challenges and may actually cost more money, depending on how the selection process is implemented.

Design-Bid-Build:  The following three approaches, based on contractors bidding a fully designed scope of work, are sometimes used by public agencies for ensuring that the contractor selected is qualified to perform the work:

Prequalification:  Under this scenario, contractors must be prequalified and meet certain criteria before being permitted to bid on a project.  Some public agencies are not authorized to prequalify contractors.  For those that are authorized to prequalify contractors, it is important that the criteria used to evaluate qualifications be clear, objective, and not overly restrictive of the bidding pool of contractors.

Bidder Responsibility:   In many cases, bidder responsibility criteria are the same as the prequalification criteria.  The only difference is that all contractors may bid a project rather than just prequalified contractors.  The low bidder must then demonstrate they meet the bidder responsibility criteria.  Prequalification analysis occurs prior to bidding, while bidder responsibility evaluation occurs after bidding, but prior to award.  Like prequalification, bidder responsibility inserts an element of subjectivity into the award process.

Best Value:  A best value selection process moves away from price as the only basis for identifying the successful contractor and instead begins to looks more like a Request for Proposals process, where various evaluation criteria are identified, including price.  Not all public agencies are authorized to conduct a best value selection process, and the process is often criticized for its subjectivity with the result that the public agency may contract with the firm who does not have the lowest bid.

Alternative Project Delivery Methods:  The following two alternative project delivery methods are gaining in popularity with public agencies.  Unlike the models used under a Design-Bid-Build approach, the design is not complete when the contractor is selected under the following two alternative methods:

Construction Manager at Risk:  This process is known by many different names (CM at Risk, CMAR, GC/CM (General Contractor/Construction Manager), and CM/GC (Construction Manager/General Contractor)).  Not all public agencies are authorized to use this process which involves selection of a contractor early in the design process, through a Request for Proposals process, partially based on qualifications and partially based on limited pricing (fee and general conditions work).  The selected contractor then works with the designer in providing various preconstruction services (cost estimating, scheduling, constructability reviews, value engineering, etc.) before the construction cost is negotiated between the parties when the design is sufficiently completed. 

Design-Build:  Under this project delivery method, the public agency uses a Request for Proposals process to select one firm to both design and build the project, eliminating or reducing conflicts between the designer and contractor.  The price is either part of the selection process (which brings with it many of the problems of the traditional low bid award), or the price is negotiated between the partieis when the design is sufficiently complete.  

Indefinite Delivery/Indefinite Quantity:  Also known as IDIQ, this method of public construction is basically an on-call process, in which undefined work is bid ahead of time and one contractor is selected, sometimes based on price alone and sometimes based on price and qualifications.  There are two major forms that IDIQ public construction contracts take:

Job Order Contracting:  Under Job Order Contracting, a contractor is selected partially based on qualifications and partially based on their markup percentage for serving as the general contractor for undefined work that will be assigned as the needs arise.  Establishing the cost of a specific project is typically based on an agreed upon unit price book.  Nevertheless, the contractor and agency must still negotiate the specific cost of work to ensure that units and quantities used in the estimate are appropriate.  Job Order Contracting is sometimes criticized for being more expensive than the traditional low bid process, but it is a more efficient process for ensuring that work is performed in a timely manner.

On-Call Contracting:  On-call construction contracting differs from Job Order Contracting in the selection process in that specific units of work are bid as part of the selection process (rather than relying upon a unit price book).  While the contractor in Job Order Contracting may be required to subcontract out major portions of the work, under on-call contracting, the contractor often performs all or most of the work themselves.  On-Call contracting is an effective tool for minimizing multiple invitations to bid for what are typically smaller dollar amount projects.  

General comments:
  • How much are bidder qualifications worth?  In most of the methods described above, there is some level of subjectivity involved in the selection process as a public agency evaluates and scores bidders based on qualifications and experience.  The result is that the low bidder may not end up being the selected bidder, or the price may be negotiated.  
  • Maintaining fairness and transparency:  In selecting contractors based on factors other than the low price, it is important that the process established be fair and transparent, and that the qualifications and proposals of contractors be rated as objectively as possible.  The low bid process was originally established to avoid public agencies showing favoritism to certain contractors.  Public agencies are now recognizing that the low bidder isn't always the best option for the public.  But in expanding the scope of selection methodologies, there is the risk of shifting back into an environment of favoritism to certain contractors.  These alternative tools must be managed carefully and thoughtfully.
  • Not all agencies authorized to use all methods:  Not all public agencies are authorized to use some of the selection methods outlined here.  State laws differ.  In addition, if there are federal funds involved with a project, public agencies need to work closely with the federal department granting the money to ensure that the selection process complies with federal regulations.
Mike Purdy's Public Contracting Blog 
© 2013 by Michael E. Purdy Associates, LLC 
http://PublicContracting.blogspot.com

Wednesday, August 14, 2013

How Much Are Bidder Qualifications Worth?

The San Antonio Housing Authority (SAHA) recently paid $94,000 more for a construction project because they took the second lowest price, instead of the lowest price.  The second lowest price had better overall qualifications.

Best Value Selection:  SAHA defended their action stating that their evaluation process was not based on the awarding to the low bid, but they assigned points to the bidders based on other factors, including the following, that would ensure they obtained the best value contractor:
    • Oversight and Planning
    • Scheduling
    • Safety and Warranty
    • Price
    • Strength of Section 3 participation
    • Contractor's Women and Minority Business Enterprise plan
Different from Bidder Responsibility:  Rather than just evaluating the qualifications of the low bidder based on bidder responsibility criteria, SAHA assigns points to each of these criteria and then awards to the contractor with the highest number of points, even though their price might not be the lowest price.  

Protest:  SAHA's practice recently led to complaints being filed by a contractor whose bid was $94,000 lower than the bidder awarded the project.  According to SAHA, the protesting bidder's scores on the non-price related factors were not as high as the contractor's who was awarded the project.

What is permitted?  Not all agencies are authorized to conduct a best value selection process using a Request for Proposals for construction projects.

More information:  Click here for more details about the SAHA controversy.
Mike Purdy's Public Contracting Blog 
© 2013 by Michael E. Purdy Associates, LLC 
http://PublicContracting.blogspot.com

Wednesday, May 23, 2012

State Charged with Public Works Procurement Process Reform

Under the terms of legislation approved this year, the Washington State Department of Enterprise Services (DES) will be conducting an ambitious review of the state's current public works procurement processes and will make reform recommendations.  

The state's capital budget bill (ESB 6074 - Section 1022) outlined the charge to DES but allocated only $75,000 to complete the quick turn-around study.

Focus of report:  Because of the limited funding for the study, DES may concentrate some of its focus on state agencies, although the legislation broadly applies to the state's "current public works procurement processes."  The report is required to include historical data on:
  • Use of change orders
  • Use of Job Order Contracting
  • How competitive public works contracts are advertised
  • Contract closeout procedures
In addition, DES told the Capital Projects Advisory Review Board (CPARB) on May 10, 2012 that the study may address a number of other topics, including the following:
  • Best value procurement
  • Use of electronic signatures
  • Standardizing bidding thresholds for all agencies
  • Prequalification of contractors on Design-Bid-Build projects
Labor union concerns:  The impetus for the study came from the state employees labor union (Washington Federation of State Employees) and the impact that some public works processes are having upon their work.  For example, union representatives expressed concern in testimony to the Legislature that some public works change orders are outside the original scope of work of the project and represent work that state employees, and not contractors, should be performing.

Stakeholder input:  In developing its report and recommendations, DES may consult with the Capital Projects Advisory Review Board (CPARB) for advice and assistance, and will also solicit input from various stakeholders. 

Other concurrent studies:  In addition to the study being conducted by DES, two other organizations are conducting reviews of public works contracting, specifically the alternative public works contracting processes authorized by RCW 39.10:
Public works legislation in 2013:  It is anticipated that next year the Legislature will be reviewing significant legislation addressing public works procurement and contracting procedures:
  • CPARB:  CPARB's intent is to recommend legislation to the Legislature in January 2013.  That legislation will take into account recommendations from JLARC as well as CPARB's Reauthorization Subcommittee.  It is anticipated that the legislation will make recommendations for certain changes to the GC/CM, Design-Build, and Job Order Contracting laws, and will authorize continuation of these alternative methods beyond June 2013, which is when the current law expires. 
  • DES:  DES is required to submit its report to the Legislature and Governor by December 15, 2012, and to include draft legislation to implement the recommendations in its report.  This legislation will also presumably be considered by the Legislature in 2013.
Overlap between studies:  All three reviews (DES, CPARB, JLARC) will be examining Job Order Contracting processes and practices.

Mike Purdy's Public Contracting Blog 
© 2012 by Michael E. Purdy Associates, LLC 
http://PublicContracting.blogspot.com

Wednesday, April 25, 2012

Project Delivery Methods for Public Construction Projects

Let's take a look at some of the project delivery methods that are sometimes used for public works construction projects. 

Design-Bid-Build:  Traditionally, most public works construction projects are advertised and then awarded to the lowest responsible bidder with a responsive bid.  This is known as the Design-Bid-Build model, where there is a separate designer, the agency then bids the project, and it is awarded to a contractor to build it.  

Rosters:  Sometimes, there are variations to the bidding process.  The project may be publicly advertised or the plans and specifications may be provided to only a limited number of bidders on a roster.  But it's still Design-Bid-Build since bidders are submitting prices for constructing the project based on complete plans and specifications.

Design-Build:  In the Design-Build model, the public agency selects one firm to both design the project and to build it.  Here are some features of Design-Build: 
  • Ends the blame game:  Eliminates a traditional source of contention with contractors blaming the designer for faulty design when things go wrong, and the designer blaming the contractor for faulty installation.
  • Speed:  Can be a fast process for delivering projects.  
  • Requires sophisticated owner:  It is a more complex process and requires a fairly sophisticated public agency to manage not only the selection process, but the actual design and construction portions of the work.   
  • Not applicable for all projects:  May not be a good project delivery method if the agency and the end users or the public want to have significant input into the design.
  • Selection process:  In some instances, the Design-Builder might be selected based on a combination of qualifications, design, and price, while in others they may be selected only based on qualifications, and then work with the agency during the design process.  At the end of design, the parties would negotiate a contract price.
Construction Manager at Risk: The Construction Manager at Risk method goes by a variety of different names, including GC/CM (General Contractor/Construction Manager), CM/CM (Construction Manager/General Contractor), CM at Risk, and CMAR.  
  • Preconstruction Services:  It is a method in which the agency selects a contractor early in the design process to provide consultant input to the design from a contractor’s viewpoint, and to begin planning the project.
  • Qualifications and Price Based Selection:  The selection is based on qualifications and limited pricing, such as the cost of general conditions work and the contractor’s overhead and profit.
  • Negotiated Price:  When the design documents reach a certain percentage of completion, the agency and contractor negotiate the construction cost.
  •  Subcontractors:  In some jurisdictions, there are requirements that all work be competitively bid or that limits the amount of work the contractor may perform with their own forces, while other agencies don’t have such requirements.
IDIQ (Indefinite Delivery/Indefinite Quantity):  Job Order Contracting is one form of IDIQ and is a means for agencies to obtain the services of a contractor on an on-call or as-needed basis for construction, maintenance, and repair work without advertising each specific project.  Typically, the contractor is selected partially on qualifications and partially based on either unit prices or price markups.  Other forms of IDIQ include advertising for bids from contractors  to perform on-call work in a specific specialty area (such as electrical or carpentry).  Selection is usually based on unit prices.

Public-Private Partnerships: In an era with shrinking public dollars for public improvements, some agencies have successfully tapped into the private sector with creative, “one-off” types of partnerships, in which the private sector contributes financially to the project with the prospect of gaining financially.  Examples might include a toll highway built and operated by the private sector, or low income housing projects that benefits from federal tax credits.

Best Value Procurement:  In Best Value Procurement, a contractor is selected based on a combination of their bid of complete plans and specifications for a construction project, and also based on their qualifications.  Evaluation criteria with maximum points are established for both the bid price as well as specifics about the contractor’s qualifications.  As an example, if the bid amount was only worth 15 points out of a total of 100 points, an agency could end up awarding a project to a firm without the low price because they were rated high on their qualifications.  

No Competition:  Some public agencies have dollar thresholds, below which they are not required to obtain bids for a project, but are free to select any contractor.  

Emergency Project:  Other times, competitive bidding is waived in the event of an emergency situation when there is not sufficient time to advertise and award a project.  Emergencies are usually based on a threat to public safety or health, or a situation which would prevent the agency from performing its essential functions and providing critical services.

Work Performed by Agency Staff:  Some public agencies have dollar thresholds, below which their own internal staff may perform public works projects, and that don't have to be competitively bid to contractors.

Other Project Delivery Methods:  There are a variety of other project delivery methods, some of which are not used as frequently.  These include Multiple Prime Contracts and Integrated Project Delivery.

Regulations and Resources:  In assessing the most appropriate project delivery method to use:
  • Regulations:  Review your state and local laws to see what methods your agency is authorized to use.
  • Staff:  Assess your staff resources and knowledge and whether you have sufficient ability to engage in some of the more complex project delivery methods.
  • Project:  Evaluate what project delivery method will be best for a specific project.
Mike Purdy's Public Contracting Blog 
© 2012 by Michael E. Purdy Associates, LLC 
http://PublicContracting.blogspot.com

Sunday, November 28, 2010

State Refines Draft "Best Value Selection" Legislation

The State of Washington, through a task force of the Capital Projects Advisory Review Board (CPARB) is continuing to revise draft legislation that would permit use of a best value selection process for public works construction projects, on a pilot basis.  If the task force is able to reach agreement on the draft legislation, and if CPARB approves the draft legislation at its December 9, 2010 meeting, the legislation would be introduced for consideration by the Legislature in January 2011.

Best value contracting as is being discussed by the task force means "a public works project that is awarded based on price, qualifications, and value added to the overall project."  Click here to read the draft legislation.

The task force will be meeting on Thursday, December 2, 2010 from 10:30 a.m. to 11:30 a.m. to discuss finalizing the draft legislation.  The meeting is open, but due to the small room, only a dozen people will fit in the room.  Other interested parties may participate via the telephone.
Mike Purdy's Public Contracting Blog 
© 2010 by Michael E. Purdy Associates, LLC
http://PublicContracting.blogspot.com

Sunday, November 14, 2010

The Future of Capital Project Delivery

All Day Conference:  The Future of Capital Project Delivery

When:  Wednesday, November 17, 2010 (8:30 a.m. to 5:00 p.m.)

Where:  Tulalip, Washington (Tulalip Resort Conference Center)


Cost: 
  • $299 for NWCCC members
  • $379 for Non-members
Presentations on the following subjects:
  • Target Value Design
  • BIM Project Execution Planning
  • Integrating Technology into Lean Construction
  • Project Delivery through Best Value Selection
  • Advancing New & Emerging Technologies to Provide Highest Business Value in Capital Project Life-cycle
  • Industrial Engineering Techniques for Improving Field Operations
  • Project Delivery at Boeing
  • Innovation and Integration in Project Delivery at the University of Washington
  • The Future of Capital Project Delivery
Speakers:
  • Eric Smith, University of Washington
  • Churck Lynch, Boeing
  • Dr. Glenn Ballard, UC Berkeley
  • Steve Hutsell, Corps of Engineers
  • John Lynch, Washington State Department of General Administration
  • Kimon Onuma, Originator of BIMStorm
  • Brigitta Foster, Sandia National Labs
  • Ceoff Anderson, Lease Crutcher Lewis
  • Ray Topping, FIATECH
  • Deke Smith, BuildingSMART Alliance NIBS
Information and Registration:  Click here.

Mike Purdy's Public Contracting Blog (© 2010 by Michael E. Purdy Associates) 
http://PublicContracting.blogspot.com

Wednesday, September 8, 2010

CPARB to Meet September 9, 2010

Washington State's Capital Projects Advisory Review Board (CPARB) will meet on September 9, 2010 in Olympia, Washington.

The agenda includes the following items:
  • King County Work Order Contracts:  This is in response to a complaint letter filed with CPARB by Seattle area minority contractors who argue that King County is not authorized to use this method of contracting because it does not comply with the current Job Order Contracting provisions authorized in chapter 39.10 RCW.  Click here for a copy of the letter from the minority contractors.  Many public agencies have work order, or on-call contracts, similar to King County's.
  • Integrated Project Delivery/Best Value Task Force:  CPARB will be reviewing recommendations from the Task Force for introducing legislation to permit a pilot Best Value selection process for public works projects.  The draft legislation defines Best Value as "a public works project that is awarded based on price, qualifications, and value added to the overall project."  Click here to read the draft legislation.
  • Bidder Responsibility/Eligibility Task Force: This Task Force has met a couple of times and hopes to meet again in late October to review proposed revisions to CPARB's Suggested Guidelines for Bidder Responsibility.  The Task Force is discussing how to ensure that Supplemental Bidder Responsibility Criteria are applied and used in a manner that meets the needs of public agencies and is fair for contractors.
  • CPARB Work Plan: Discussion on potential legislation and establishing a task force to begin to address issues surrounding the June 30, 2014 sunset date for the alternative public works laws.

Tuesday, May 11, 2010

CPARB to Meet May 13, 2010

The State of Washington's Capital Projects Advisory Review Board (CPARB) is scheduled to meet on Thursday, May 13, 2010 in Olympia, Washington, from 9:00 a.m. until noon.

The agenda includes the following items:
  • Integrated Project Delivery / Best Value Task Force Report
  • Bidder Responsibility / Subcontractor Eligibility Criteria Task Force
  • 2010 Work Plan 
  • 2010 Legislative Update



Thursday, February 25, 2010

Speech on "Issues and Trends in Public Project Delivery"

I'll be giving a speech on Friday morning at 8:45 a.m. (February 26, 2010) at the Annual Seminar of the Pacific Northwest Chapter of the Construction Management Association of America (CMAA) on "Issues and Trends in Public Project Delivery."

Here's a high level outline of my speech:
  • Why We Have Competitive Bidding
  • 4 Trends in Public Project Delivery
  • Contracting and Delivery Models:
  1. Design-Bid-Build
  2. General Contractor/Construction Manager (GC/CM)
  3. Job Order Contracting
  4. Public-Private Partnerships
  5. Maintenance Contracts
  6. Best Value
  7. Integrated Project Delivery (IPD)
 The Annual Seminar will be held in Bellevue, Washington at the Mount Si Conference Room at 500 108th Ave NE.

Wednesday, February 10, 2010

CPARB Meets on February 11, 2010

I will be heading to Olympia on Thursday morning (February 11, 2010) to listen to the discussion at the Capital Projects Advisory Review Board (CPARB) meeting.  

The agenda includes the following items which I will report on in a subsequent blog entries:
  • Discussion of City of Tacoma's proposed Design-Build project.  In a January 20, 2010 letter to the City of Tacoma, CPARB stated that "there is a concern with how the Design-Build RFQ [for a parking garage] meets the requirements of RCW 39.10 for public works."  Representatives from the City of Tacoma have been invited to attend the meeting and discuss the project with CPARB.
  • Report on use of Job Order Contracting in 2009
  • Report from the Integrated Project Delivery/Best Value Task Force
  • Legislative updates and discussion
  • Identify task forces for 2010 work plan of CPARB.

Monday, August 24, 2009

Task Force on Integrated Project Delivery (IPD) and Best Value

The Washington State Capital Projects Advisory Review Board (CPARB) has formed a task force of design and construction industry representatives to evaluate the potential use of Integrated Project Delivery and Best Value Procurement in the state.

Click here to read the minutes of their July 1, 2009 meeting.

The next meeting will be held on October 8, 2009 from 9:00 a.m. to noon at the Northwest Carpenters Facility, 25120 Pacific Highway South, Kent, Washington.

Thursday, June 25, 2009

State of Washington Investigates Integrated Project Delivery and Best Value Contracting

The State of Washington has established a task force to investigate the possibility of using two alternative methods of contracting for public works construction projects: Integrated Project Delivery (IPD) and Best Value Contracting/Competitive Negotiations.

These will be the topics discussed on July 1, 2009 at a task force meeting of industry-wide representatives under the auspices of the Capital Project Advisory Review Board (CPARB). If it is determined that these are appropriate contracting methods, CPARB could make a recommendation to the Washington State Legislature to approve these as alternative public works contracting procedures.

If approved, they would join three other models of project delivery already authorized by chapter 39.10 RCW: Design-Build, General Contractor/Construction Manager (GC/CM), and Job Order Contracting.


The task force on IPD and Best Value will meet from 1:00 p.m. to 3:00 p.m. on July 1, 2009 at the Northwest Carpenter Facility (25120 Pacific Highway South, Kent, Washington). The agenda includes evaluating what IPD and Best Value are, as well as looking at the current alternative public works delivery methods authorized.

Monday, April 13, 2009

Best Value / Design-Build for County Solid Waste Plants

A reader of this blog recently pointed out to me that counties in the State of Washington may use what amounts to best value procurement combined with design-build-operation for solid waste handling systems, plants, sites, or other facilities.

This process is outlined in
RCW 36.58.090 and is separate from the provisions of chapter 39.10 RCW that outlines alternative public works contracting procedures, including design-build.

There has been discussion in Washington State of expanding the list of authorized alternative public works contracting procedures to include best value. In 2010 or 2011, the State Legislature may take up consideration of a pilot program for this.

Wednesday, April 8, 2009

Best Value Contracting for Public Works

Check out the PowerPoint presentation below on Best Value Contracting in Public Works. I recently heard David Bergquist from the State of California speak on the pilot program recently authorized by the California Legislature on Best Value Procurement for the University of California at San Francisco.

Within Washington State, Best Value procurement for public works is not authorized. Chapter 39.10 RCW provides for only three alternative public works contracting methods to be used instead of the traditional Design-Bid-Build method of procurement. The three methods that are authorized are: General Contractor/Construction Manager (GC/CM), Design-Build, and Job Order Contracting.

There is some interest in Washington State to explore Best Value procurement and possibly propose legislation for beginning with some pilot projects.

Thursday, April 2, 2009

Best Value Pilot Program in California

The State of California has adopted a pilot program authorizing a Best Value procurement process for the selection of contractors on public works projects at the University of California at San Francisco.

Under Best Value procurement, price is not the only factor used in the selection of a contractor. Other evaluation factors include demonstrated management competency, relevant experience, financial condition, labor compliance, and safety record.


I attended a meeting last week at which David Bergquist, from the University of California's Office of General Counsel spoke about this alternative procurement process. His speech was entitled "Public Sector Capital Projects: Is there a better way than Low Bid?" Mr. Bergquist was instrumental in working to get this pilot program adopted by the California Legislature.


To view the California law on Best Value,
click here.

If you would like me to e-mail you a copy of David Bergquist's PowerPoint presentation on Best Value, please
contact me.

Tuesday, March 17, 2009

Is There a Better Way to Obtain Public Sector Capital Projects than by Low Bid?

Evening Lecture: Public Sector Capital Projects: Is there a better way to buy them than low bid?

When: Wednesday March 25, 2009 - (5:00 p.m. to 9:00 p.m.)

Where: Glen Acres Golf Club, 1000 S. 112th St., Seattle, Washington

Sponsored by: Lean Construction Institute, Cascadia Chapter

For more information and to register, click here.

Speaker: Dave Bergquist, University of California

Dave Bergquist will speak on the Best Value legislation recently enacted in California and his experiences with the five year pilot program at the University of California at San Francisco. Following the presentation, there will be a discussion on the implications of Best Value for Washington State.

Wednesday, July 16, 2008

CPARB – 2009 Legislative Priorities

The Capital Projects Advisory Review Board (CPARB) met on July 10, 2008 to discuss legislative priorities for the 2009 Legislative session of subcontractors and public owners. At the August 14, 2008 CPARB meeting, the Board will considered legislative priorities from contractors and labor unions.

Subcontractor Priorities: Subcontractors presented three issues they would like to see endorsed by CPARB and approved by the Legislature:

  1. Require payment of prevailing wages on Public-Private Partnerships.
  2. Include Housing Authorities as a specifically named public entity covered by the alternative public works contracting procedures of chapter 39.10 RCW.
  3. Modify the definition of “prefabricated modular building” in RCW 39.10.300 (the Design-Build statute) to limit the number of such modular buildings that may be used on a project without having to obtain the approval of CPARB’s Project Review Committee.

Owner Priorities: Owners presented four issues they would like to see endorsed by CPARB and approved by the Legislature:

  1. Permit all public agencies in the state to use the provisions of RCW 39.04.015 that currently only allows “state contracting authorities” the ability to negotiate a bid price on a public works project, under limited circumstances.
  2. Increase the thresholds for the Small Works Roster to $500,000 (from $200,000), and increase the Limited Public Works threshold from $35,000 to $100,000 (RCW 39.04.155).
  3. Include Best Value Procurement as a fourth alternative public works contracting process.
  4. Increase the dollar thresholds for cities and counties for the amount of work that may be performed with their own forces without having to contract it out.

There will be additional discussion by CPARB on these issues as part of deciding whether CPARB should recommend legislation to address these concerns.

Saturday, July 12, 2008

Best Value Procurement

The Capital Projects Advisory Review Board (CPARB) has begun discussions about Best Value Procurement. Essentially, this is an off-shoot of the traditional Design-Bid-Build, but could best be characterized as “Design-Select-Build.” The distinction is how the contractor is selected.

In Design-Bid-Build, the contractor is selected based on a low bid. In Best Value, the contractor is selected based on a combination of price and qualifications, experience, and approach.

Naturally, some contractors are concerned about such an approach for two reasons.

  1. It puts some contractors at a disadvantage when compared to larger and more experienced firms.
  2. Contractors are concerned that public agencies may manipulate the selection process to only select their favorite contractors.
How Best Value Procurement gets developed (and if it does) and what evaluation criteria will be used will make a big difference as to whether this alternative delivery method is added to the tool belt for use by public agencies in Washington State.

There are different versions of Best Value Procurement in existence. Arizona State University’s Performance Based Studies Research Group (PBSRG) touts a version of Best Value that, in my opinion, is heavily biased against public agencies in favor of contractors. Read my earlier blog entry about this method, based on my attendance at their training, by clicking here.

Is it Time for New Alternative Public Works Contracting Methods?

In the State of Washington, there are three project delivery methods for public works construction contracts that are officially designated as “alternative public works” contracting procedures (chapter 39.10 RCW).
They are viewed as “alternatives” to the traditional “Design-Bid-Build” of government agencies in the State to procure construction services – where the public agency hires a designer (architect or engineer) to “design” the project by developing detailed design specifications and drawings. Then the public agency advertises and “bids” the project to contractors. The responsible contractor submitting the low responsive bid is awarded the contract and they then “build” the project.

While Design-Bid-Build has been around a long time in the State, it has its inherent problems – always awarding to the low bidder doesn’t always serve the public’s interests. Recognizing this concern, the State Legislature has authorized these three “alternative” project delivery methods for public works construction projects.

But beyond these three alternative project delivery methods, there are other tools that are used in other parts of the country and in the private sector, some of which are getting attention in Washington State. These include the following:
I will write about each of these other methods in subsequent postings to this blog.

Saturday, February 16, 2008

Best Value Procurement

I attended a four day conference on Best Value procurement near Phoenix from February 11th through 14th. While the concept of selecting a contractor based on best value rather than purely low bid has significant public benefits to the taxpayers on public works construction projects, if designed and managed appropriately, I came away from the conference very skeptical about the particular slant on best value that was promoted by the presenters, notwithstanding the strong support that Best Value has generated with many in the construction field.

The conference was part pep rally, part testimonials by owner converts, and part explanation of a fairly rigid contracting process that has a strong bias against owners and strongly tilts towards and favors contractors. In fact, it is contractors and vendors who have funded millions of dollars in research and support of Arizona State University’s Performance Based Studies Research Group (PBSRG), the sponsors of the conference. The conference was also long on self-promotion of PBSRB by Dr. Dean Kashiwagi, its director.

Frequently repeated and unsupported statements were zealously preached to the some 60 organizations (owners, contractors, suppliers) with representatives at the conference. The “client [owner] is the source of all risk” was a major theme as Dr. Kashiwagi urged owners to “give up control [of the contractor] because you actually have no control.” PBSRG’s black and white philosophy argues that the contractor is the expert and knows best how to do the project. Under Best Value procurement, as articulated by Dr. Kashiwagi, neither management or decision making by the owner is necessary or desirable. “Decision making is not a good thing,” Dr. Kashiwagi asserted. Instead, once having picked the right contractor, the contractor should take control of the project, including writing the actual contract. In fact, according to Dr. Kashiwagi, the “contract must protect the contractor, not the owner.” Furthermore, the owner shouldn’t manage risk but delegate technical risk to the contractor.

The conference was heavy on promoting a simplistic, unrealistic, and underlying philosophy that views people mechanistically, asserting that people are always predictable and that for any event there is just one possible outcome because people are always predictable. “All event outcomes can be predicted with ‘all information,’” a questionable assumption even if we lived in a perfect world where all information was available. Thus, if these assertions are true, so goes the argument, contractors will always do the right thing if they’re just given the responsibility to manage risks instead of having the owner attempting to control a project and mitigate risks. All of this, of course, appears to be predicated on the false assumption that all contractors are competent, take pride in their work, and have the owner’s best interest at heart. Nothing in the philosophy supports an owner’s role in managing a project. Instead, the contractor, as the expert, should make the decisions and be accountable, while all efforts should be made to minimize the owner’s “management, inspection, and decision making.”

Furthermore, I found Dr. Kashiwagi’s presentation style to be condescending and derogatory of owners, procurement officers, and those who, in his words are “blind” (possess technical knowledge and experience that they try to use in managing), but are not “visionaries.” He continually repeated that his best value system was “simple” and based totally on logic, even though he made multiple unsupported and non-logical claims for his positions. I often wondered if the system is really so simple why it took a four day conference that included marketing pitches to hire PBSRG as consultants to run the procurement and project for owners. Dr. Kashiwagi repeatedly urged the attendees to make no changes to the system or it wouldn’t work.

According to PBSRG, the success of Best Value is boiled down to whether the contractor is on-time, on-budget, and “making everyone happy.” Conspicuously missing from the equation is the concept of quality. But under PBSRG’s model, the contractor will take care of the quality and the owner won’t have to even inspect the project as much because if the contractor is a high performer, they’ll manage all of this, permitting the owner to minimize decision making and managing the project.

Beyond its heavy and negative bias against owners in favor of protecting contractors, the core of the Best Value procurement system, does offer some potential tools for owners that may be able to be used even in a low bid environment. However, PBSRG’s Best Value procurement is designed to work outside of a low bid environment where non-price factors are used as part of the selection process.

While the generic concept of Best Value makes good sense, as promoted by PBSRG, it does not seem to me to be within an owner’s best interests, notwithstanding the glowing testimonies from various owners who have used it under PBSRG’s guidance.