Tuesday, July 15, 2014

Issues to Consider in Electronic Bidding Solutions

More and more public agencies are exploring or actually receiving bids electronically, and there are a host of software solutions to manage receipt of bids electronically.  The following is a checklist of some of the issues to consider when evaluating electronic bidding solutions: 

Legal authority:  Do your state or local laws permit electronic bidding?  Some laws permit it for goods, services, and construction, while others prohibit it altogether or restrict it to certain procurements. 

Bid guaranty:  If you require a bid guaranty (bid bond, cashier's check, certified check) as part of the bid submittal, how does the electronic bidding solution address bid guaranties?  Is this solution consistent with your state and/or local laws? 

Signature:  How do bidders "sign" the bid and agree with all of the provisions of the bid documents? 

Conditioned bids:  Make sure the software system does not allow bidders to qualify or condition their bid. 

Bid form:  How easy is it for a public agency to set up a bid form on the software, especially for complex bid forms with schedules, unit prices, additives, alternates, allowances, and sales tax (if applicable)? 

Integrity:  What security tools does the system software provider use to prevent manipulation of bid prices by a hacker, bidder, or the public agency? 

Disclosure:  What security features does the software have to ensure that bid amounts are secure and not subject to disclosure prior to the bid submission deadline? 

Tested by time:  How long has the system been in use, and what is its track record on security issues?  Check references of other agencies who have used the system before deciding to sign up for it. 

Transparency:  How are bids "opened"?  Does this occur in a public setting?  How does the system promote transparency of the bid process? 

Cost:  Who pays for the use of the system?  The bidder (all bidders or just the low bidder) or the public agency?  Regardless of who pays directly, ultimately the public agency will pay for the service, even if it means that the bidder simply includes the cost of using the system in their bid price. 

Small contractors:  Are small contractors technologically savvy enough to use the system?  Will electronic bidding reduce the number of bidders and have a corresponding increase in bid prices? 

Non-local contractors:  Will more non-local contractors submit bids?  How does this impact a local agency's policy to encourage or provide bid preferences to local firms?  

Small public agencies:  Do small public agencies have the technological expertise to use electronic bidding?

Mike Purdy's Public Contracting Blog
© 2014 by Michael E. Purdy Associates, LLC
http://PublicContracting.blogspot.com

Monday, May 5, 2014

In What Order Should Bids Be Opened?

When bids are received by a public agency, should they be opened:
  1. In the order in which they were received?
  2. Alphabetically based on the contractor's name?
  3. In a random order?
Applicable laws and policies:  Unless there are applicable local or state laws or agency policies, bids may be opened in any order, as the order of opening doesn't impact the bidding process or give one bidder an advantage that other bidders don't have.

Administrative convenience:  Some agencies choose to open bids in alphabetical order and may have entered the names of anticipated bidders on a bid tabulation form prior to bid opening.
Mike Purdy's Public Contracting Blog
© 2014 by Michael E. Purdy Associates, LLC
http://PublicContracting.blogspot.com

Monday, May 20, 2013

The Envelope Please: Opening the Right Bid

All bids have been received.  The clock shows that it is past the bid submission deadline.  You gather up the bids and take them to the room where you will open them.  One by one, you open the envelopes, pull out the bids, and read them.

The wrong envelope:  But suddenly you realize that the bid you have just pulled out of an envelope isn't for the project you're opening bids for.  In fact, it isn't even for any of the projects you're opening bids for now, but for a project with a bid submission deadline next week.

Assumptions:  Let's assume the follow circumstances:
  • You stop short of reading the wrong bid
  • You don't notice or look at the bid price
  • You don't reveal the name of the bidder
  • The room is full of contractors and agency employees
What should you do?   Under the circumstances, it is best to be as honest and transparent as possible.
  • Tell the story:  Describe factually to the assembled audience what has just occurred, including the fact that you did not see the bid price. 
  • State your intent:  Tell the audience that the bid will be opened and read after the actual bid submission deadline.
  • Re-seal envelope:  With the audience as witnesses, put the bid back into the envelope and re-seal it immediately with tape.
  • Write it down:  Document in writing what has just occurred, with the document signed by at least agency employees who were present.  If you're able to get one or two contractors to sign it as well, that would be helpful.  In the event of a challenge or protest, this documentation will be helpful in defending your agency's action to consider the bid that was opened early.
Lessons learned:  Here are a couple of lessons learned from this scenario:
  • Require project name on bid envelope:  Have language in your Instructions to Bidders requiring that the bidder write the project and bidder name on the bid envelope.
  • Check that project name is on bid envelope:  Staff receiving the bids should ensure the project and bidder name are on each envelope as they are submitted.
  • Separate bids received by project:  Train staff who receive bids to keep the bids separate by project.
  • Check that bids are for the correct project:  Before bids are released to be read, the person who received them should go through the envelopes one by one to make sure they are for the correct project.
  • Double-check bid envelopes before reading:  Before beginning to open bids, the bid reader should double check the bid envelopes to ensure they are for the correct project.
Truth is stranger than fiction:  These type of situations actually occur, and point out the importance of carefully managing the bid receipt and opening process.  Obviously, the facts of your situation may be different and may call for you to change how you respond.

Mike Purdy's Public Contracting Blog 
© 2013 by Michael E. Purdy Associates, LLC 
http://PublicContracting.blogspot.com

Sunday, January 13, 2013

How to Decide When to Receive and Open Bids

There are a number of considerations that public agencies should take into account when making the decision on what day public works bids should be received.  These factors should all be considered together to determine the best schedule for when to receive bids.

What's required?  Some states and local governments have laws that specify how many days a public works construction project must be advertised for prior to receiving and opening bids.  Research this and know what requirements govern your agency.

Project schedule:  Each project has certain schedule deadlines that need to be met.  Bid openings should be scheduled in order to keep the project schedule on track.

Bid preparation time:  Public agencies should pay attention to the size and complexity of the project in making the decision how long a project should be advertised for.  If too little time is provided for bidders to prepare their bids before the bid submission deadline, they may either not bid, or submit an unreasonably low or high bid due to not having had sufficient time to understand the project.  An unreasonably low bid may cause problems during the project and result in unnecessary change orders. 

Other projects:  Pay attention to other projects from other public agencies that may be advertised and bidding at the same time.  If there are too many bid openings for the same type of work scheduled for one day, bidders may be forced to pick bidding only a limited number of projects.  This may result in fewer bids being received by your agency, and thus less competitive bids. Try to schedule bid openings when there are not a lot of other bid openings by other agencies in the general region.

Best days of the week:  Most public agencies make it a practice to only receive and open bids on Tuesdays, Wednesdays, or Thursdays.  Receiving bids on Mondays or Fridays may reduce the number of bidders since the bidders' staff may be taking vacation time for a long weekend.

Holidays:  It is a wise idea to avoid receiving and opening bids around major holidays.  Like Mondays and Fridays, it may limit the number of bidders, reduce competition, and result in higher prices for the public agency.
Mike Purdy's Public Contracting Blog 
© 2013 by Michael E. Purdy Associates, LLC 
http://PublicContracting.blogspot.com

Sunday, May 20, 2012

Training: Public Works Bidding and Contracting

2 Day Class on Public Works Bidding and Contracting

When:  
Instructor:  Mike Purdy

Class Outline:
  • Types of Contracts
  • Bidding
  • Bid Receipt
  • Bid Guaranty
  • Bid Responsiveness
  • Award
  • Bidder Responsibility
  • Contract Execution
  • Prevailing Wages
  • Construction
  • Change Orders
  • Close-out
  • Alternative Public Works Contracting

Cost: 
  • Free - WCIA Members
  • $175 - Non-WCIA Members
Information and Registration:  Click here.
Mike Purdy's Public Contracting Blog 
© 2012 by Michael E. Purdy Associates, LLC 
http://PublicContracting.blogspot.com

Tuesday, October 25, 2011

Preventing Early Opening of Bids

When bids are submitted to a public agency there is a risk that a bid may simply go through the agency's normal process for opening and routing mail.  This may result in a sealed bid being inadvertently opened prior to the deadline and time established for opening and reading the bids, compromising the integrity and confidentiality of the bidding process.

Practical Tips:  The following are some steps that may help ensure that bids are opened at the appropriate time:
  • Bidding Instructions:  Ensure that the agency's bidding instructions are clear about the information that must be identified on the face of the bid envelope.
  • Staff Training:  Provide training to reception and mail room staff responsible for receiving deliveries and mail to the agency.  Make sure they understand they should not open mail that is indicated as including a bid inside the envelope.  This applies for whether a bid is received through the U.S. Postal Service, FedEx, UPS, another delivery service, or in person.
  • Notice to Reception Staff:  Work with reception and mail room staff and provide them with an updated list and schedule of the deadlines for when bids for certain procurements are due.  Having this list can help alert them to slow down and not open these but to deliver them to the appropriate procurement staff.
  • Managing a Bid Opened Early:  If a bid is accidentally opened early, do not remove the bid from the envelope, but re-seal the envelope immediately.  If the bid has already been removed from the envelope, put it back in the envelope and re-seal the envelope.  If the envelope is missing, put the bid in another envelope and seal it.  Regardless of the circumstances, document on the face of the envelope that the bid was inadvertently opened, along with the date and time you re-sealed it.  Initial or sign the statement.
Mike Purdy's Public Contracting Blog 
© 2011 by Michael E. Purdy Associates, LLC 
http://PublicContracting.blogspot.com

Thursday, May 5, 2011

My Training Schedule This Week

Wednesday, May 4:  On Wednesday, I taught 45 professionals from various public agencies on public works contracting issues in Spokane, Washington.  The topics I addressed included the following:
  • Bidding and Contract Documents
  • Receipt and Opening of Bids
  • Bid Responsiveness and Bidder Responsibility
  • Insurance, Bonds, and Retainage
  • Change Orders
  • Public Works Contract Close-out
The class was co-sponsored by WSDOT and the Municipal Research and Services Center.  I will be teaching the same class on May 26, 2011 in Shoreline, Washington, on September 21, 2011 in Ellensburg, Washington, and again on November 16, 2011 in Olympia, Washington.

For more information about the class and to register, visit WSDOT's website by clicking here.  Click on the link for "Purchasing, Bidding, and Contract Management for Local Agencies."

Thursday, May 5:  On Thursday, I gave two training speeches at the annual conference of the Washington Association of School Business Officials (WASBO), in Spokane, Washington.   My two topics were:
  • We're Being Audited! - Tips for Managing and Surviving Audits
  • What is the Davis-Bacon Act? - Complying with Federal Prevailing Wage Requirements
Each of these sessions was 50 minutes long.  There were about 40 people in the Audit class and 30 in the Prevailing Wage class.  The attendees asked great questions.
Mike Purdy's Public Contracting Blog 
© 2011 by Michael E. Purdy Associates, LLC 
http://PublicContracting.blogspot.com

Tuesday, September 14, 2010

Training on Purchasing, Bidding & Contract Management for Local Agencies

I conducted an all day training session on Tuesday, September 14, 2010 in Vancouver, Washington as part of the 2010 Annual Conference of the Washington Finance Officers Association (WFOA).  

The subject of the training was Purchasing, Bidding and Contract Management for Local Agencies.

The following is an abbreviated outline of the seven hour training program:
  • Types of Contracts and Solicitations
  • Purchased Goods and Services
  • Architectural and Engineering Services
  • Public Works Contracting (Bidding, Award, Contract Execution, Construction, Close-out)
If you would like a copy of the detailed outline of the class, or if you'd like to discuss me providing this training for your agency, please contact me.

Wednesday, August 4, 2010

Webinar: Bulletproof Your Bidding Process: Keys to Minimize Liability

I will be teaching at 1 hour webinar on a variety of public bidding issues.

Subject: Bulletproof Your Bidding Process: Keys to Minimize Liability 

When: August 12, 2010 from 1:00 p.m. to 2:00 p.m. (Eastern Time).

Cost:  $199

Outline of Webinar:  Here are some of the subjects I'll be covering.
  • Bid receipt and opening issues
  • Managing addenda
  • Mandatory pre-bid meetings
  • Common bid irregularities
  • Difference between material and immaterial irregularities
  • Bidder responsibility criteria
  • What bidding error can be corrected
  • Managing requests for bid withdrawal (claims of error)
  • Bid protests
More Information and Registration:  Visit the website of Government Educator, who is sponsoring the webinar.

Questions:  Please contact me if you have any questions about the webinar.

Tuesday, July 20, 2010

Parting Company with a Contractor

There are a variety of actions a public agency may take that have the effect of parting company with a contractor, either before or after a contract has been executed.

Prior to Award:
  • Math Error in Bid:  In the event a bidder makes a mathematical error in its bid, especially for a unit price bid, most bidding documents provide that the owner may and should make corrections, with the unit price taking precedence over the multiplication of the unit price times the estimated quantities, and the owner's summation of the unit price extensions taking precedence over the contractor's summation of the items.  In the event such corrections are made, the bidder who may have been identified as the low bidder at bid opening may no longer be the low bidder.
  • Claim of Error:  After bid opening, a bidder may discover that they have made an error in their bid, especially as they compared their bid price to those of the other bidders.  There are generally two types of claims of errors, those relating to clerical or administrative errors, and those relating to errors of judgment.  In a claim of error, the bidder requests to be relieved of their liability for their bid.  If the owner accepts the claim of error, the bid would no longer be considered.  There is no negotiation of the bid price that is permitted through a claim of error.

  • Non-Responsive Bid:  After bid opening, once the bids have been evaluated by the owner, the owner may determine that the bid is non-responsive, meaning it did not respond to the requirements of the bidding documents.  Common reasons for non-responsive bids include bids submitted after the deadline, unsigned bids, and failure to submit a sufficient bid guaranty with the bid.  Bids with irregularities that are material (those that give an advantage or benefit to the bidder not enjoyed by other bidders) must be rejected by the owner as non-responsive, while those bids with immaterial irregularities may be accepted or rejected at the owner's discretion.
  • Bidder Not Responsible:  A bidder with a low responsive bid may be rejected by an owner for not being a responsible bidder, or not having the capabilities or qualifications to perform the project.  Bidder responsibility standards vary by jurisdiction, but generally there should be responsibility criteria that are included in the bidding documents to put the bidder on notice of how they will be evaluated.  Such bidder responsibility criteria should be relevant and to the extent possible, fairly objective, although there is disagreement often between owners and contractors about this.
After Award, But Prior to Contract Execution:
  • Revocation:  At times, an owner may revoke an award before the contract has been executed.  Reasons why this may occur include the contractor failing to execute the contract or provide the required bonding and insurance, a protest filed by another bidder, or a change in direction or funding for the project.
After Contract Execution:
  • Termination:  There are two primary types of termination:  termination for cause and termination for convenience.  Termination for cause carries with it an additional burden of proof by the owner, and may be disputed more intently by a contractor than termination for convenience. 
Bidding Webinar:  I will be teaching a 60 minute Webinar on bidding issues on August 12, 2010.  For more information and to register, visit the website of Government Educator.

Thursday, July 15, 2010

Do You Know Where Your Bids Are?

Does your public agency have a standard practice of what happens to bids once they've been received, but before they are opened?  

Secure - But Not Too Secure:  Received bids should be stored in a secure location, not accessible to the public.  However, they should not be so secure that your staff forgets about them.  Frequently, I hear of agencies who have opened bids, only to discover later that there were other bids received on time that didn't make it to the bid opening.  

Vacation:  In one case, the contracting manager had secured a bid submitted early in his desk drawer, and went on vacation without telling anyone of the bid.  Only when he returned did the missing bid become an issue.

2 Bids Missing:  In another case recently at the City of Roseville, California, six bids were opened and read.  Within an hour, staff noticed two additional bids that had not been opened.  These were opened, and one of them was the low bidder.  The firm who was announced as the low bidder after the six bids were received filed a  protest arguing they should be awarded the project, or that all bids should be rejected and the project readvertised.  The City of Roseville staff determined that the late reading of the two bids was an immaterial irregularity, and those two bids should be considered.

Do You Know Where Your Bids Are?  Have a standard practice of collecting bids so that this type of situation doesn't arise.  Some agencies are governed by laws that require a public opening and reading of bids, often on the same day as the bid submittal, so if misplaced bids are discovered late, this can cause a problem.  From the perspective of contractors, not reading bids at the time and place announced does not help promote transparency and trust in the bidding process, and can, as in the City of Roseville's case, lead to bid protests.

The Bottom Line:  Have a clear process, with trained staff, of how you receive, store, and open bids.  Please contact me if you would like an assessment of your bid receipt and opening practices, or if you would like a three hour training session on the subject.

Monday, July 12, 2010

Webinar: Bulletproof Your Bidding Process

I will be teaching at 1 hour webinar on a variety of public bidding issues.

Subject: Bulletproof Your Bidding Process: Keys to Minimize Liability 

When: August 12, 2010 from 1:00 p.m. to 2:00 p.m. (Eastern Time).

Cost:  $199

Outline of Webinar:  Here are some of the subjects I'll be covering.
  • Bid receipt and opening issues
  • Managing addenda
  • Mandatory pre-bid meetings
  • Common bid irregularities
  • Difference between material and immaterial irregularities
  • Bidder responsibility criteria
  • What bidding error can be corrected
  • Managing requests for bid withdrawal (claims of error)
  • Bid protests
More Information and Registration:  Visit the website of Government Educator, who is sponsoring the webinar..

Questions:  Please contact me if you have any questions about the webinar.

Monday, June 28, 2010

A Bidding Nightmare

It's 1:58 p.m., just two minutes before bids are due on your sidewalk replacement project - and your front counter staff person has taken a break or gone to pick up supplies in another part of the building.  

A bidder races in the door, frantic that no one is around to receive and stamp in his bid.  The bidder wanders through the hallways and cubicles, seeking someone to receive his bid.  He finally finds someone, who takes the bid back up to the front counter where the bid is date and time stamped in.  But the time stamp reads 2:01 p.m., after the deadline.  The bid is opened along with the other bids and the bid is the lowest bid.  

Is the Bid Responsive?  Is the bid responsive and should it be considered further?  Whether the bid should be accepted depends on the specific facts of the situation.  In this case, the public agency did not manage the process properly.  The bidder presumably was on time.  Should the bidder (and the taxpayers) be punished because the agency didn't have someone available to time stamp in the bid?

Tips on Bid Receipt:  To prevent bid protests and problems, here are a couple of practical tips on managing the receipt of bids:
  • Make sure that someone knowledgeable on bid receipt procedures is at the bid receipt counter continuously at least an hour before the bid submittal deadline.
  • Check the time clock with official time the morning of every day when bids will be received to ensure the time close is consistent with the official time.  See http://www.time.gov/.
  • Do not accept or read bids that have been submitted after the bid submittal deadline.
Training:  I have developed a two hour class on best practices on bid receipt and opening issues that I have taught a couple of times.  Please contact me if you would like me to conduct this training for your agency.

Wednesday, May 12, 2010

Training on Public Works Contract Administration

I taught a six hour course on May 12, 2010 on Public Works Contract Administration sponsored by the Washington State Department of Transportation (WSDOT) and the Municipal Research and Services Center (MRSC).  

About 45 public agency representatives attended the training in Bellevue, Washington.  This was the second day of this training program.  The first day focused on purchasing and professional services.

The topics I covered included the following:
  • Construction Contract Documents
  • Bid Receipt and Opening
  • Insurance, Bonds, and Retainage
  • Responsive Bids
  • Responsible Bidders
  • Change Orders
  • Public Works Contract Close-out: Claims Against Bonds and Retainage
The same class will be held again in the fall as follows:
  • September 22-23, 2010, Camas, Washington
  • October 13-14, 2010, Mount Vernon, Washington
For more information about the class and to register, visit WSDOT's website.  If you would like to discuss me providing training for your agency, please contact me.

Tuesday, October 27, 2009

Las Vegas Agency Rejects All Bids

On October 20,2009, the Clark County (Nevada) Commissioners took the unusual step of rejecting all four bids received on a $55 million membrane/ozonation facilities project due to bid irregularities in all of the bids.

Earlier, the county had declared the bid of McCarthy Builders as non-responsive for being submitted almost a minute and a half past the bid submittal deadline. Click here to read my previous blog entry on October 14, 2009 on the late bid submittal protest. The county received two bid protests on the project that undoubtedly contributed to their decision to reject all bids.

In rejecting all bids and choosing to re-advertise the project, the county noted the various types of irregularities in the bids. The county appears to have required a number of documentation items to be submitted with the bid, a practice that can result in non-responsive bids, as occurred in this instance.


Unless required by funding sources or specific laws, I always advise that public agencies limit what is required to be submitted with the bid. This allows bidders to concentrate on developing a competitive bid price, often a challenge in the last minute receipt of subcontractor bids and the development of a final bid price to the owner. Limiting the submissions with the bid reduces the number and type of issues that may arise that would result in a non-responsive bid.


In making a decision about whether a bid is responsive or not, the public agency should consider whether the irregularity in the bid is material or immaterial. In other words, if the irregularity would have provided a bidder with an advantage not enjoyed by other bidders, the bid must be declared non-responsive. Irregularities that do not provide one bidder with an advantage not enjoyed by others may be either accepted or rejected by the owner.

While it may exist, I didn't find anything in the Clark County record that reflected their evaluation of whether these irregularities were material or immaterial. Without reviewing the bidding documents and facts in this situation, it's hard to make the determination of whether the irregularities are material or immaterial.


The following is a summary of some of the irregularities in the bids noted by Clark County. Unless some of these items are required for submission by law, it seems to me that the county should not be requiring these with the bid submittal.
  • Failure to submit a copy of the bidder's contractor license with the bid. This should be a matter of public record and something that should be validated after bid submittal and prior to award of a contract.

  • Failure to submit with the bid a copy of the contractor license for subcontractors performing at least 5% of the contract amount. Also a matter of public record and something that shouldn't be submitted with the bid.

  • The total bid price was not tabulated correctly. It was higher than the sum of 12 individual bid items. Most agencies have, or should have, language in the bidding documents permitting the owner to correct such mathematical errors, so it's surprising that this was cited as one of the irregularities leading to rejection of all bids.

  • Use of a form outlining the qualifications of the proposed electrical subcontractor was from a different project. Requesting qualification information with the bid requires all bidders to prepare and submit, instead of only requiring this information for the successful bidder prior to award. It also can lead to non-responsive bids. In Washington State, RCW 39.04.350 provides for the establishment of supplemental bidder responsibility criteria. I always advise that agencies request this information to be submitted after the bid submittal deadline.

  • An instrumentation supplier qualification form was not completely filled out.

  • An expired "Certificate of Eligibility" form related to bid preference was submitted. I'm not sure what the context is for this form, but if it's not required by law or the funding source, this is an example of the type of form that should not be required to be submitted with the bid.

  • The form listing subcontractors were not completely and accurately filled out and contained dollar discrepancies. Another subcontractor listing form was not the current version of the form that had been updated by an addendum. In Washington State, there is a specific law requiring the submission with the bid of a list of subcontractors who will be performing electrical, plumbling, and HVAC for projects estimated to cost $1 million or more. See RCW 39.30.060.
In addition to the bid of McCarthy Builders that was rejected for being submitted late, the other four bidders whose bids were rejected were: Whiting-Turner Contracting Co., PCL Civil Constructors, Inc., MMC, Inc., and Western Summit Constructors, Inc.

It's a good idea for public agencies to review their bidding documents to determine whether items are being required for submission with the bid that do not have to be submitted then, but could be submitted after the low bidder is identified. This helps streamline the bidding process for contractors and reduces the likelihood of receiving non-responsive bids.

Thursday, October 22, 2009

Dealing with a Late Bid Submittal

How should public agencies handle a bid that is submitted past the published bid submittal deadline? Here are a couple of principles and things to keep in mind:
  1. Use a Time Stamp Clock: Have an electronic time clock that you use for date and time stamping in the receipt of bids. If the time clock displays and prints a time including seconds, and the bidding documents state that bids will be received until 2:00 p.m., a bid would be considered late if it was stamped in at 2:00:01 p.m. If, however, the time clock does not display and print seconds, a bid received and stamped in at 2:00 p.m. would still be on time. It would be late once the time clock read 2:01 p.m.

  2. Validate Official Time: On the bid submittal day, validate that the time on the time clock is accurate. Use the website maintained jointly by the U.S. Department of Commerce's National Institute of Standards and Technology (NIST) and its military counterpart, the U.S. Naval Observatory (USNO). The website address is: http://www.time.gov/

  3. Post a Sign Designating Official Clock: Have a sign notifying bidders that the time clock is the official time for receipt of bids and not a wall clock or other clock in the office.

  4. Have Clear Language in Bidding Documents: Make sure the language in your bidding documents is clear as to the deadline.

  5. Do Not Accept or Read Late Bids: If a bid is received after the deadline, it should not be accepted by the public agency. The public agency should receive it only to stamp it, make a photocopy of the time stamp and outside of the bid envelope and immediately return the document unopened to the bidder. The bid should not be opened or read. Sometimes, a bidder may, however, refuse to accept the bid back, in which case it is best not to get into an argument about it. The public agency should then take the bid, verbally tell the bidder that the bid is non-responsive and will not be opened or considered, not open it, and immediately return it by certified mail, return receipt requested, to the bidder with a letter explaining that the bid was received past the deadline. I once had an upset bidder literally throw a late bid over the bid counter at my staff who had returned it to the bidder. So, remember to duck!
There are many other important issues and situations to consider when managing the bid receipt and opening process. If you are interested in an audit of your agency's bid receipt and opening practices or would like training on this subject, please contact me to discuss how I might provide assistance to you in this important area.

Wednesday, October 14, 2009

Bidder Protests Rejection of Late Bid

A Nevada contractor has filed a protest arguing that its bid on a $55 million project should be accepted even though the bid was received by the owner almost a minute and a half after the bid submittal deadline.

McCarthy Building Cos., Inc. argued in their protest to Clark County that county employees were not at the bid counter when McCarthy employees wanted to submit the bid. The county employees have stated that they left the counter after the 2:00 p.m. deadline. And, of course, McCarthy argues it had the lowest bid.

The county commissioners will consider the matter on October 20, 2009.

For more information, visit the website of the Las Vegas Sun and scroll down on the page.

I will provide more details as they become available.

Monday, March 9, 2009

Are Your Bid Receipt Procedures Clear?

Do you have clear procedures for what to do if a bidder, after having submitted a bid, requests to withdraw and modify the bid, prior to the bid submittal deadline?
  • What do your Instructions to Bidders say about this subject?
  • Are your staff knowledgeable about what to do if a bidder asks for their bid back?
  • Do they know what to do if the contractor then wants to resubmit the bid prior to the bid submittal deadline?
Here are some suggested procedures to ensure clarity in the bid receipt process.
  • A bidder may request withdrawal of a bid submitted prior to the bid receipt deadline, either for the purpose of making changes to the bid, or for withdrawing the bid, subject to the following conditions:
  • The requester provides sufficient identification (or is known to the staff) that they represent the bidder.
  • A request may be received verbally or in writing.
  • The request is received prior to the bid receipt deadline.
  • Public agency staff should make a photocopy of the face of the bid envelope, ensuring that the bid receipt time shows up on the copy.
  • Public agency staff should have the bidder sign the photocopy with the following: "Received by: [signature, printed name, date, and time]."
  • Public agency staff should keep the photocopy of the face of the bid envelope and submit it to the appropriate contracting official.
  • Public agency staff should remove the bid receipt stamp or cross it out from the face of the bid envelope.
  • Public agency staff should then return the bid to the bidder, notifying the bidder that if they choose to resubmit the bid, it must be received prior to the bid receipt deadline and stamped in again with a new time and date stamp.

Wednesday, October 22, 2008

When Should Bids Be Opened When Subcontractors List is Required?

Under Washington State law, RCW 39.30.060, bidders must submit a subcontractors list as part of the bidding process for any project where the public agency has estimated the cost of the project at $1 million or more. The subcontractors list must include the names of the subcontractors who will perform the HVAC, plumbing, and electrical work, or for the bidder to name themselves if they will perform this work. By choice of the public agency and as described in the bidding documents, the subcontractors list may be submitted either with the bid or up to one hour after the bid submittal deadline.

Let's look at a potential scenario. If the public agency requires bids to be submitted by 2:00 p.m. on a certain day and the subcontractors list by 3:00 p.m. on the same day, the question comes up as to when the bids should be opened and read. The better practice is to receive the bids by 2:00 p.m., receive the subcontractors lists by 3:00 p.m., and then open the bids and subcontractors list at 3:00 p.m.

The problem with opening the bids at 2:00 p.m. is that it invites bidders to bid low on a project, knowing that if they believe their bid is too low they can choose to simply not submit the subcontractors list by 3:00 p.m. thus automatically rendering their bid non-responsive. State law is very clear that failure to submit the subcontractors list by the deadline results in a non-responsive bid.


Thus, to prevent bidders from potentially manipulating the bidding process and obtaining an unfair advantage over other bidders by having the choice of whether to accept the bid or not, it is better to open all bids and the subcontractors list at 3:00 p.m. (or whatever time the public agency sets - this is just the time noted in this example).

Friday, July 27, 2007

Bid Opening


On Thursday, I conducted a bid opening at the University of Washington Tacoma for a $6.3 million new assembly hall building. With five minutes before the bid receipt deadline, we had received no bids. Then two bids came in. With one minute to go, another bid was clocked in. With nine seconds before the deadline, another bidder raced in. The final bidder, who had been madly filling in the final figures in a chair just steps from the bid counter, slapped their sealed bid on the counter with a nail-biting three seconds before the clock struck the 2:00 p.m. deadline. Interestingly, the low bidder was the first one to submit its bid. My effort in Tacoma was part of training the staff there on receiving and conducting bid openings on their own. I've developed a set of written guidelines and procedures, laying out issues to be aware of in managing bid receipt and opening. If you'd like a copy of the guidelines as part of thinking about your own practices, please let me know and I'd be glad to e-mail you a copy.