Monday, April 1, 2013

When Are Change Orders Appropriate?

Change orders are to be expected on public works construction projects.  It's impossible to design a project to address all unknowns that may arise.  But when should additional work be performed as a change order, and when should it be bid as a separate project?

Politics and change orders:  Sometimes, political decisions cause public agencies to issue change orders in order to meet critical deadlines.  The borough of Belmar, New Jersey recently bypassed competitive bidding for more than a half million dollars of electrical and foundation work in repairing the borough's boardwalk that had been damaged by Superstorm Sandy.  Officials are racing to have the boardwalk opened in time for Memorial Day tourists.

NJ change order regulations:  New Jersey state regulations prohibit change orders for "extra work that could reasonably be effectuated by a separately bid contract without unduly disrupting the basic work or imposing adverse cost consequences."  The state code also prohibits change orders if they "materially expand upon the size, nature or scope of the project as it was originally described in the bid specifications."  Experts noted, however, that other parts of the regulations provide flexibility to support Belmar's actions.

Article on Belmar's change order:  Click here for an article describing more of the circumstances surrounding Belmar's change order.

Negotiate and document:  When change orders are necessary, it is important for public agencies to carefully review detailed backup documentation of the contractor's proposed costs, and, where appropriate to negotiate costs.  A record of the negotiations process should be maintained to demonstrate that the amount of the change order is competitive and reasonable.  This type of cost analysis is required for federally funded projects, and is a good practice for all projects. 

Change orders in Washington state:  Unlike New Jersey, Washington state does not have any state laws addressing when it is or isn't appropriate to execute a change order.  However, the Washington State Auditor's Office routinely issues audit findings to public agencies for change orders they deem are outside the original scope of work and could be bid as a separate project.  In January 2012, the Auditor's Office issued a performance audit on the importance of agencies negotiating and documenting change order costs.  Click here to read my blog entry on their audit report.

Mike Purdy's Public Contracting Blog 
© 2013 by Michael E. Purdy Associates, LLC 
http://PublicContracting.blogspot.com

Tuesday, April 10, 2012

Training: Construction Change Order Pricing

Construction Change Order Pricing:  This training will feature a representative of the Washington State Auditor's Office, reviewing the findings from a recently released audit on Construction Change Order Pricing by public agencies.  The training will include a presentation by a contractor, and there will be a panel discussion with the auditor, contractor, and a public agency.

When: 
  • May 3, 2012 (Renton, Washington)
  • May 10, 2012 (Camas, Washington)
  • May 17, 2012 (Everett, Washington)
  • May 22, 2012 (Yakima, Washington)
Times:  10:00 a.m. to 3:00 p.m.

Cost:  Free

 Sponsored by:
 Presenters:
  • Chris Cortines, CPA, Deputy Director of Performance Audits, State Auditor's Office
  • Mike Myette, P.E., President, MM Construction Consulting, LLC
  • Linda Shilley, Contract Administrator, Port of Olympia
More Information and Registration:  Click here.
Mike Purdy's Public Contracting Blog 
© 2012 by Michael E. Purdy Associates, LLC 
http://PublicContracting.blogspot.com

Tuesday, February 28, 2012

Performance Audit Issued on Construction Change Order Pricing


Purpose and Scope:  The auditor chose eight public agencies "to identify leading practices local governments can use to help reduce the cost of change orders" for both construction and architectural/engineering contracts.  Agencies selected for the audit were the cities of Bellingham, Everett, Puyallup, Richland, SeaTac, Shoreline, Spokane, and Thurston County.  Although the report title indicates its scope is "Construction Change Order Pricing," it also looked at some architectural and engineering changes.

Recommendations:  The audit identified the following three recommendations:
  • Establish a basis for reasonable and typical prices and rates for labor, materials, equipment, and markups.
  • Require contractors to submit detailed change order proposals so prices and rates can be evaluated and compared to established prices and rates.
  • Scrutinize change orders so that local governments do not pay more than established prices and rates.  When local governments expect A&E firms to evaluate their construction change order pricing, their contracts should clearly describe this in the scope of work.  Similarly, local governments should have policies and procedures to help staff members ensure change-order pricing matches established pricing and rates.
Issues:  On the surface, the auditor's recommendations appear reasonable.  Bidding and contract documents should establish the basis and formulas for how change orders will be priced, and contractors should submit detailed change order proposals which public agencies should scrutinize.  However, in at least a few areas, some of the audit report's recommendations are not practical or advisable.

Markup Rates:  The audit criticized the agencies for markup rates that exceeded what the auditor found were typical and reasonable, based on their survey of other agencies across the country.  While one of the purposes of a performance audit is to identify such issues, the audit failed to acknowledge that most of the agencies audited were simply using the standard specifications prepared by the Washington State Department of Transportation (WSDOT), either because it was required due to the funding of the project, or was more practical for both agency staff and contractors to have one specification for all public works projects.  To the extent that the audit has issues with markups, it is an issue that should be raised with WSDOT and not with the local agencies.  Establishing markup rates must take into account local conditions and contract expectations.

Prevailing Wages:  The audit report criticized agencies for paying more than the prevailing wage rate for some labor costs on change orders.  The audit noted that state law "does not obligate local governments to pay contractors for higher labor rates on change orders."  While that is certainly a true statement, the auditor's position does not reflect an accurate understanding of prevailing wages or construction costs.  
  • Contractors may pay more than prevailing wages:  Many contractors pay higher than the prevailing wage rates on public works projects in order to retain qualified workers or to comply with changing requirements of collective bargaining agreements. 
  • Contractors should be fairly compensated:  On change order work, contractors should not be expected to work at a financial loss simply because the auditor does not think workers should ever be paid more than prevailing wages.  The state's prevailing wage law is a worker protection act and establishes a minimum amount that workers must be paid. RCW 39.12 was never intended to be used to limit labor costs on change order work.
  • State's General Conditions:  While the audit holds up the State's General Conditions for Washington State Facilities Construction as a model, it does not seem to recognize that the requirements of the General Conditions contradicts the audit assertion that agencies should pay no more than the prevailing wage rates on change order work.  The audit noted that the General Conditions "limits labor rates on change orders to those submitted on the Statement of Intent to Pay Prevailing wages or higher amounts if justified and approved" by the agency.  Under two conditions, agencies pay more than the prevailing wage rates.  First, the prevailing wages listed on the Intent are often higher than the prevailing wage rates, and second, the General Conditions permit payment of a higher amount than reflected on the Intent. 
  • No artificial cap on labor:  Public agencies should pay labor on change orders consistent with what contractors are actually paying their workers, and it should not be artificially capped at prevailing wages.
Pre-established Amounts:  While public works contracts should establish a formula for how labor, materials, equipment and markups for overhead and profit are to be applied to change orders, the audit seems to suggest that unit prices and hourly rates for all change order work should be competitively bid as part of the original bid.  This is not always possible.  Particularly for a building or facility, units cannot be anticipated or bid for all possible changes.  Bidding hourly rates as part of an original bid, even if tied to estimated hours, does not make those hourly rates competitive since contractors have different levels of efficiency in performing the work.

Minimal Savings:  Of the $8.2 million in change orders that were actually audited for the eight agencies, the audit identified potential savings of just 2.1% or $175,074 based on the "leading practices" it cited.  This would suggest that public agencies are doing a good job at negotiating change order amounts, at least under the structure that the audit establishes. 

Summary:  While the audit report appropriately points out that public agencies should have a formula basis for change order work in their contracts, that contractors should submit detailed proposals consistent with the formulas, and that agencies have an obligation to carefully review such proposals, in some of its particulars the audit is misleading.  

Audit Report: Click here to read the 57 page performance audit report on "Construction Change Order Pricing."
Mike Purdy's Public Contracting Blog 
© 2012 by Michael E. Purdy Associates, LLC 
http://PublicContracting.blogspot.com

Sunday, August 21, 2011

Planning For and Surviving I-900 Performance Audits

Planning For and Surviving I-900 Performance Audits
Based on Initiative 900 that was approved by the votes of the State of Washington in 2005, the Washington State Auditor's Office regularly conducts performance audits of public agencies in the state. 

When:  October 28, 2011 (9:00 a.m. to 5:00 p.m.)

Where:  Seattle (Crowne Plaza Hotel, 1113 Sixth Avenue)

Cost:  
  • $525 for Single Registration
  • $425 for Government Employees
  • Other prices for other categories
Agenda and Speakers:
  • Introduction and Overview (Krista K. Mush, Michael D. McKay, James P. Wagner)
  • Adoption & Overview of I-900 (Michael E. McKay, James P. Wagner)
  • View from the State Auditor's Office, Part 1 (Jan M. Jutte)
  • View from the State Auditor's Office, Part 2 (Lou Adams)
  • Accounting Issues and Standards (Paul S. Fricca)
  • Issues for Agencies Being Audited (Krista K. Bush, Michael D. McKay)
  • Managing the Audit Process (Krista K. Bush)
  • Issues for Private Contractors (James P. Wagner)
  • Issues Relating to Release of Audit Report (Lou Adams, Jan M. Jutte, Michael D. McKay, James P. Wagner)
  • Panel Discussion
Information and Registration:  Click here.
Sponsored by:  The Seminar Group

Other Performance Audit Resources:
Mike Purdy's Public Contracting Blog 
© 2011 by Michael E. Purdy Associates, LLC 
http://PublicContracting.blogspot.com

Tuesday, August 9, 2011

Coming Soon: Audit on Construction Change Order Pricing

The Washington State Auditor's Office has completed most of their work on their performance audit of Construction Change Order Pricing for seven cities and one county in the state.  

Audit Being Finalized:  The auditor's office has requested the agencies audited to provide their technical review of the draft audit.  Once the auditor makes any changes in the audit based on feedback and corrections from the agencies, they will send the final draft report to the agencies for them to provide their formal written response to the audit.  The formal responses from the agencies will be published in the final audit.  The auditor hopes to publish the audit later this month.

Agencies Who Were Audited:  The following are the agencies that were audited:
  • City of Bellingham
  • City of Everett
  • City of Puyallup
  • City of Richland
  • City of SeaTac
  • City of Shoreline
  • City of Spokane
  • Thurston County
What Are Best Practices?  It promises to be an interesting audit report when it is finally published that will generate a lot of conversation (and some disagreement with the audit) over what practices should be followed.  It probably won't rise to the blockbuster level of some of the previous construction management performance audits that have come from the state auditor. 
Mike Purdy's Public Contracting Blog 
© 2011 by Michael E. Purdy Associates, LLC 
http://PublicContracting.blogspot.com

Thursday, January 27, 2011

Performance-Based Contracting Audit Planned

The Washington State Auditor's Office is seeking the services of a firm to help them audit the use of performance based contracting among state agencies.

The Auditor's Office defines performance based contracts as having the following characteristics:
  • Identifying expected deliverables
  • Identifying performance measures or outcomes
  • Making payment contingent on successful delivery of these performance measures or outcomes.
In November 2010, Washington Governor Chris Gregoire requested assistance from the Auditor's Office in evaluating performance contract practices by state agencies.

The audit will seek to answer the following questions:
  1. Contract Management:  How are agencies actively managing performance-based contracts?  For example, if a vendor is not performing, what corrective actions are being taken?  Are contractors/vendors being held accountable?  Given limited resources, what options are available to improve management if needed?
  2. Performance Measures:  Do current performance-based contracts include appropriate and effective performance measures for assessing contractor performance?  If not, why not?
  3. Incentives:  Do current performance-based contracts provide incentives for excellent performance and/or consequences for inadequate performance?  If not, why not?
  4. Leading Practices:  What are leading practices around performance-based contracting?  How could we apply these practices to Washington State?
Using the results of the audit, the Auditor's Office plans to write a summary report to the Governor by June 1, 2011.
Mike Purdy's Public Contracting Blog 
© 2011 by Michael E. Purdy Associates, LLC 
http://PublicContracting.blogspot.com

Tuesday, September 28, 2010

What Happens If You Get an Audit Finding?

Audits are a part of everyday life for those managing government contracting and purchasing.  State and local governments, as well as the federal government, have auditors that audit to ensure that public agencies are complying with various laws, regulations, internal agency policies and procedures, and grant provisions.

What are some of the impacts of an audit finding?
  • Negative Publicity:  Depending on the nature of the finding, it may be front page news.  As such, it casts your agency in a negative light from the public's perspective, and becomes a political issue as elected officials and administrators attempt to tighten up your agency's practices to prevent future problems.
  • Personnel Actions:  Again, depending on the nature of the finding, it may result in agency employees being subject to disciplinary action, including personnel warnings, suspension without pay, and even termination.
  • Loss of Grant Funding:  Some applications for grants will require agencies to disclose any audit findings, and such findings may impact a decision for an award of a grant.  Granting agencies want to make sure that those they are awarding grants to are managed properly.
  • Procedural Changes:  Some audit findings are the result of an oversight that indicates a lack of internal controls to ensure that proper procedures are followed.  Other audit findings occur because an agency doesn't have policies and procedures in a particular area.  In either event, an audit finding will result in changes to how an agency operates to ensure tighter controls, and to prevent future findings.
  • Follow-up Scrutiny:  An agency that has received an audit finding may be scrutinized more closely in future years by the auditor to ensure the agency has corrected the problems.  In Washington State, an audit finding may also lead to a Performance Audit of part of the agency's operations.  
Practical Tips:  Know what laws, regulations, internal policies and procedures, and grant provisions apply to the contracting and procurement of goods and services for your agency.  Obtain necessary training of your agency personnel.  Establish clear checks and balances to ensure compliance. 

Thursday, September 9, 2010

Auditor Developing Performance Audit Work Plan

The Washington State Auditor's Office is currently developing their work plan for performance audits of local governments during the years 2011 through 2013.

The Auditor will make their decisions of what agencies and programs to audit based on suggestions from local governments, citizens, public interest groups, and other interested parties, including the Auditor's Office.

According to a solicitation for firms to help them gather input, the Auditor will use the following criteria to prioritize audit topics:
  • Focus on the highest state priorities:  Priority is placed on proposed audits that address the state's most important and costly programs and functions across government.
  • Address areas of high risk:  Some programs and activities require more attention because of the size of their budgets, the inherent risk of their missions, or the need for substantial reform.
  • Provide actionable recommendations:  Evaluate the likelihood that decision-makers will be able to follow through on potential audit recommendations, so that results will actually improve.
  • Return on investment:  In light of local governments' ongoing budget challenges, the selection process prioritizes audits that offer the potential to reduce costs or improve services within current spending.
  • Manageable audit scope:  Priority is given to audit topics that present a scope of work that can be accomplished in a timely manner.
In November 2005, the voters of the State of Washington approved Initiative 900 that requires the State Auditor's Office to conduct performance audits of all public agencies in the state.  Initiative 900 is now included in RCW 43.09.470.

Sunday, March 21, 2010

Performance Audit Plan Announced

Over the next four years, only two performance audits to be conducted by the Washington State Auditor's Office will focus on contracting and procurement issues:
  • Results of Federal Economic Stimulus Funding
  • Opportunities to Improve State Procurement
Absent from the list of 30 identified performance audits in the auditor's work plan for 2010 to 2013 are audits of construction management practices of public agencies that the auditor has focused on it the past.

Most memorably, the auditor issued a scathing report of the construction management and contracting practices of the Port of Seattle in December 2007.


Sunday, January 24, 2010

No Indictments in Port of Seattle Contracting Fraud Investigation


Two years ago, the Washington State Auditor's Office issued a scathing performance audit on the Port of Seattle's contracting and construction management practices.  That audit led to the U.S. Attorney's Office launching a two year probe into whether any Port of Seattle employees broke federal laws and should be indicted.

Last week, the Port announced that the feds have concluded their corruption and fraud investigation and will not be issuing any indictments. 

The December 2007 performance audit led to the resignation of two employees and to seven employees being disciplined. 

The Port has since created a Central Procurement Office headed by Nora Huey to make necessary changes in the Port's contracting practices.

Resources:

Monday, June 22, 2009

Audit Findings: King County Construction Management

The Washington State Auditor's Office released an audit of King County's Construction Management practices with the following five findings:
  1. The lack of adequate performance measures and expectations prevent the King County Executive and Council from providing adequate oversight of construction activity.

  2. King County does not have an adequate construction project management information system.

  3. King County does not have standard construction management procedures.

  4. King County construction management data, files and records are not consistently maintained and are not readily accessible for management oversight and review purposes.

  5. King County does not provide resources that are adequate to enable the Executive Audit Services to comply with County policy requiring construction management audits.
Early this year, the State Auditor's Office terminated what began as a performance audit because the County was unable to provide the records necessary for the auditor to perform their review. The audit report released on June 22, 2009 reports on the information obtained by the auditor before the termination of the performance audit.

The auditor stated that "We believe the recommendations provided...may enable the County to better enforce project completion deadlines, liquidated damages and minimize overall construction costs."

The audit also addresses other County operations unrelated to construction management.

The following are resources about the audit:

  1. Read the complete audit report along with the auditor's recommendations and the County's responses.

  2. Visit King County's website to read the County's summary response to the audit and their disagreements with the auditor.

  3. See what the SeattlePI.com has to say about the audit.

  4. Visit the Puget Sound Business Journal's website to read their report of the audit.

Wednesday, June 10, 2009

Findings on Library System Performance Audit

The Washington State Auditor's Office has issued a performance audit report of the Construction Management practices of the King County Library System.

The summary for the report states the following:

"We found that KCLS is doing a good job overall with its construction projects. We did find opportunities for improvement and to reduce its risk. We found that KCLS has incomplete policies and procedures for managing construction projects. We found issues with contracting practices, and in particular, change orders, that resulted in paying excessive markups on projects. Its current change order rate is 17 percent. By following the recommendations, they could reduce it to around 10 percent, which is more in line with industry best practices. The construction project method they chose for the five design-build projects was a good approach for KCLS, but was not legal according to state law."

Having clear and complete policies and procedures for managing construction projects, along with staff who have been trained in them is critical to proper construction management. The use of Design-Build projects in Washington State is limited to public agencies who have received either agency approval or project approval to use Design-Build, one of three alternative public works contracting procedures authorized by chapter 39.10 RCW. Please contact me if you would like assistance in reviewing, revising, or writing contracting policies and procedures for your agency. Likewise, I can provide assistance in the use of Design-Build, General Contractor/Construction Manager (GC/CM), and Job Order Contracting, the three alternative public works contracting procedures.

Wednesday, April 29, 2009

Is Your Agency Ready for a Performance Audit?

The Washington State Auditor's Office has been conducting Performance Audits of public agencies in the State over the last couple of years.

Some of the audit reports have made headline news, most notably their audit of the Port of Seattle's construction management program that resulted in a contracting reorganization at the Port, disciplinary actions against employees, and new laws adopted by the State Legislature. The Auditor's Office is continuing to audit additional public agencies.


To hear the experiences of the Port of Seattle and Seattle Public Utilities, come to an evening dinner meeting: Preparing for a State Audit.


When: Wednesday, May 20, 2009 (4:45 p.m. to 7:45 p.m.)

Where: Rock Salt On Latitude Restaurant, 1232 Westlake Avenue North, Seattle, WA

Cost: $37 per person

Sponsored by: APWA Washington State Chapter (Management & Public Administration Committee)

Registration Deadline: Wednesday, May 13, 2009

To register, visit APWA's website

Sunday, April 5, 2009

Update on Performance Audits

The Washington State Auditor's Office is continuing its performance audits of public agencies in the State. Here's an update on their activities related to construction management and capital project audits.

Pending Construction Management Audit Reports:
The Auditor's Office is currently drafting performance audit reports in the area of construction management for the following three public agencies: Pending Capital Projects Audit Reports: In addition, they are drafting performance audit reports on capital projects for three public hospital districts: Fieldwork underway: Fieldwork is currently underway for construction management and operations for Public Utilities Districts in Chelan, Douglas, and Grant counties.

Future Audits Planned: Future performance audits on construction management practices include the following agencies:

Sunday, February 22, 2009

PowerPoint of CMAA Speech Available

On Thursday, February 19, 2009, I spoke at the monthly meeting of the Pacific Northwest Chapter of Construction Management Association of America.

My topic was “The Changing Landscape of Public Works Contracting.” I addressed a number of current issues relating to the following:
  • Alternative Public Works Contracting
  • Legislative Updates
  • Bidder Responsibility
  • Performance Audits
If you would like a copy of my PowerPoint presentation, please contact me and I will e-mail it to you.

Thursday, December 18, 2008

Port of Seattle Changes Estimate on Project

Port of Seattle staff changed their internal estimate on a project to build a new cruise ship terminal near the Magnolia Bridge after the bids came in 30% over the Port's estimate. By changing the estimate after bids were submitted, Port staff avoided having to notify the Port Commission of the higher bid. The Port's policy requires that any bid that is more than 10% higher than the estimate must be submitted to the Commission for review.

Read the Seattle Times article from December 18, 2008 for more details.

RCW 39.04.020 is the state law that requires public agencies to develop estimates on public works projects. In summary, it requires the following for any public works project:
  • Develop plans and specifications
  • Develop an estimate of the cost of the work
  • Have the plans, specifications, and estimate filed in the office of the individual or body authorized to require the work
  • Have the plans, specifications, and estimate approved by the authorized individual or body
The law doesn't address the issue of modifying the estimate after bids have been submitted. Such a practice does appear to circumvent the public's interest, and in the case of the Port, appears to be at variance with the Port's internal policies that requires Commission approval of contract awards where the low bid is 10% or more of the estimate.

What practices does your public agency use with respect to development of estimates?

Wednesday, December 10, 2008

Port of Seattle Disciplines Employees over Contracting Fraud

On Tuesday, December 9, 2008, two Port of Seattle employees resigned and CEO Tay Yoshitani disciplined seven additional Port employees for their role in fraudulent contracting activity.

The actions come after a critical audit of the Port's construction contracting management practices and a recent report that identified ten instances of fraud committed by Port employees.

Resigned:
  • John Rothnie, project manager for the third runway project
  • Larry McFadden, general manager of Port Construction Services
Suspended without pay:
  • Ray Rawe, chief engineer (3 week suspension)
  • David Soike, deputy director of aviation (1 week suspension)
  • Paul Powell, contract services manager (1 week suspension)
  • Robert Riley, director of airport capital improvement (1 week suspension)
Reprimanded:
  • Linda Stout, deputy CEO
  • Craig Watson, general counsel
  • Mark Reis, airport director
The summary of the Port's actions may be found by clicking here.

More information may be found in the Seattle Times story, or by visiting the Port of Seattle's website.

Monday, December 8, 2008

Port of Seattle to Announce Disciplinary Measures

Port of Seattle CEO Tay Yoshitani is expected to announce on Tuesday, December 9, 2008, disciplinary measures against Port employees involved in instances of fraud.

An independent investigation recently released reported ten instances of fraud by Port employees, most related to the Port's construction contracting management practices. The investigation was ordered by the Port after the Washington State Auditor's Office performance audit in December 2007 disclosed that the Port wasted almost $100 million due to poor contracting practices.


A
Seattle Times article on December 7, 2008 discusses the difficulties of pinpointing which employees were involved in doctoring a critical memo that is at the heart of one of the fraud allegations.

Thursday, December 4, 2008

Port of Seattle Fraud Report Issued

After ten months and $1.39 million, former U.S. Attorney Mike McKay issued his report on ten instances of fraud that he discovered at the Port of Seattle.

The report follows a scathing performance audit of the Port of Seattle's contracting practices issued almost a year ago.


McKay found that one Port employee leaked the Port's internal cost estimate to a contractor who later bid on the third runway project and ended up making a 30% profit on the project. Other findings of fraud included:
  • Negotiating price with a contractor prior to award
  • Breaking projects into smaller projects to avoid competitive bidding thresholds
  • Not notifying certain contractors of bidding opportunities
  • Steering contracts to favorite contractors
  • Issuing an emergency contract for $25,000 that was later amended to more than $1 million for non-emergency work
The complete 76 page fraud report, issued on December 3, 2008, may be found by clicking here. An executive summary of the report may be found by clicking here.

You can also read the December 4, 2008
Seattle Times article on the subject.

Friday, July 25, 2008

Performance Audit Update from the State Auditor


In their Summer 2008 newsletter, Audit Connection, the Washington State Auditor’s Office has an article entitled Performance Audit Update.

There are construction management audits in various stages of planning for a dozen agencies. In addition, the article notes other performance audits underway now for a number of different programs at various agencies.