Wednesday, January 28, 2015

How Not to Implement Bidder Responsibilty Criteria on a Project

Establishing bidder responsibility criteria on public works construction projects can be a good idea.  It helps ensure that the low bidder is, in fact, capable and qualified to successfully perform the work.  Some public agencies, however, go about implementing responsibility in ways that are counterproductive and lack transparency. 

City of Des Moines, Iowa:  In September 2014, the City of Des Moines adopted what they grandiosely call the "City of Des Moines Taxpayer Quality Assurance Policy."  It only applies for building or facility projects estimated to cost more than $1 million.  In essence, it is intended to be a bidder responsibility law, but it is flawed in a number of ways:
  • More Prequalification than Responsibility:  The law requires that all contractors interested in bidding on a project must complete and submit "no later than two weeks prior to the deadline for accepting bids" a "General Contractor Quality Assurance Questionnaire" and respond to 26 questions.  Establishing bidder responsibility is generally determined after bids have been opened to assess whether the low bidder is responsible.  The City of Des Moines' questionnaire begins to look more like a prequalification process.
  • All bidders must complete questionnaire:  Unlike bidder responsibility practices, the City is requiring all bidders to complete and submit the questionnaire.  Because of the length and complexity of some of the questions, this may cause some bidders to decide not to bid on city work, thus reducing competition and increasing prices, or to bid on the project but increase their prices to recoup their costs in completing the questionnaire and to deal with the hassle of bidding with the City.
  • Responsiveness vs. Responsibility:  The City's practice of requiring the questionnaire prior to bidding makes submission of the form a matter of responsiveness initially before an analysis is even made of whether the bidder is responsible. In other words, if a bidder fails to submit the questionnaire by the deadline, presumably their bid is non-responsive. Documentation of bidder responsibility should never be made part of the bid process, but requested of the low bidder after bid opening.
  • Questionnaire is subjective:  The questions asked by the City are not actual bidder responsibility criteria, but collects information about which the City does not disclose what the basis will be of their evaluation of the questionnaire.  In other words, to properly implement bidder responsibility, there must be actual criteria and standards, so that anyone looking at the documentation submitted should be able to come to the same conclusion about whether the bidder met the criteria or not.  
Misguided effort:  The City of Des Moines' attempt to ensure responsible bidders is ultimately misguided.  It creates a subjective process that will discourage competition and increase costs. The policy also attempts to fix a non-existent problem.  According to the City's engineers, "in general, the City of Des Moines has not experienced major issues in its public bid construction program." Click here to read an excellent and more detailed analysis of the City's law from the law firm of Fabyanske Westra Hart & Thomson. 

Use bidder responsibility criteria:  The preferred method for implementing bidder responsibility is to publish actual criteria in the bid documents, and to then request documentation from the low bidder a certain number of days after bid opening demonstrating that they meet the criteria.  Criteria should be crafted in such a manner to not unduly restrict competition, but to establish a baseline threshold of the ability of the bidder to successfully perform the work.  Click here to read "Suggested Guidelines for Bidder Responsibility" published by the State of Washington's Capital Projects Advisory Review Board.


Presidential History:
  • Presidential History Blog:   While I will discontinue writing this Public Contracting Blog on March 5, 2015, you can sign up for a free email subscription to my Presidential History Blog at www.PresidentialHistory.com.  On a case-by-case basis, I will only be accepting limited consulting and training opportunities after March 5, 2015.
Mike Purdy's Public Contracting Blog
© 2015 by Michael E. Purdy Associates, LLC
http://PublicContracting.blogspot.com

Wednesday, October 8, 2014

Training on Construction Bidding and Contracting

I am teaching three courses for NIGP at various locations across the country.  If you're interested in having me teach any of these classes for your NIGP chapter or public agency, please contact Faye Jackson at NIGP directly at FJackson@nigp.org.  If you're within Washington state, contact me directly. Here's a description of the courses.

Maryland State Capitol
in Annapolis
When Bad Things Happen to Bids: Strategies for Ensuring Successful Public Construction Projects:   I was in Annapolis, Maryland on September 12, 2014 teaching this course.  Here's an outline of this one day course: 

Why Aren’t Bidders More Careful?
  • Why Do Bidders Make Mistakes?
  • Missing Bid Prices
  • Conflict Between Numbers and Words
  • Bid Calculation Errors
  • Claims of Error
Is Your Bidder Playing Games?
  • Bid is Too Low
  • Incentive Payments
  • Unbalanced Bids
  • Conditioned or Qualified Bids
Will the Real Low Bidder Please Stand Up?
  • Additive and Alternate Bids
  • Tie Bids
  • Responsive Bids
  • Responsible Bidders
  • Local Bid Preferences
  • Bid Protests and Appeals
  • Conflicts of Interest
What Can You Do to Manage Bidding?
  • What Should Be on the Bid Form?
  • Why Should You Limit Submissions with the Bid?
  • On What Days Should You Not Receive Bids?
  • When is a Bid Late?
  • When Should You Take a Bid Guaranty?
Best Practices in Developing Public Construction Bid Documents:  I'll be teaching this course on October 27 in Savannah, Georgia.  Here's an outline of this one day course:

Principles of Preparation

Formats and Structures
  • Organizational Structures
  • Content Based Systems
  • What Are the Pros and Cons of Using Industry Approved Documents?
Components of Bid Documents
  • Advertisement for Bids
  • Instructions to Bidders
  • Bid Form
  • Payment and Performance Bonds
  • Bidding and Contract Reporting Forms
  • Contract
  • General Conditions / Specifications
  • Technical Specifications
  • Prevailing Wages
  • Specialty Reports and Studies
  • Addenda
Project Review of Bid Documents
  • Do the Bid Documents Reflect Your Objectives?
  • What Provisions Should You Tailor to a Project?
  • Who Should Review the Documents Before Advertisement?
Long Term Review of Bid Documents
  • Baseline Review
  • Annual Review
  • Internal and External Consistency
  • Training
Document Management and Control
  • How Can You Protect Your Standard Documents?
  • Where Should the Standard Documents be Electronically Stored?
  • Who Should Make Changes to Your Standard Documents?
  • How Can You Keep Track of Changes?
Procurement Tools for Ensuring Contractor Performance on Public Construction Projects:  I'll be teaching this class on November 3 in Phoenix, Arizona and then again on November 17 in Hagerstown, Maryland.  Here's an outline of this one day course: 

Is the Contractor Qualified?
  • Pre-qualify Bidders
  • Establish Bidder Responsibility Criteria
  • Specification Qualification Requirements
  • Subcontractor Approval Process
How Can You Manage the Bidding Process?
  • Develop Clear Bidding Documents
  • Optional vs. Mandatory Pre-Bid Meetings
  • Craft Clear Addenda
  • Accept Bidder’s Claim of Error
How Can Bonding Companies Help?
  • Bid Bonds and Other Bid Guaranties
  • Performance Bonds
  • Payment Bonds
  • Warranty Bonds
What Financial Tools Are at Your Disposal?
  • Withhold Retainage
  • Determine and Assess Liquidated Damages
  • Assess Actual Damages
  • Obtain Release of Claims Prior to Payments
What Are Effective Construction Management Practices?
  • Avoid Front-Loaded Schedule of Values
  • Inspect Work Performed
  • Review Pay Applications for Work Completed
  • Manage Claims Process
  • Control Change Orders Approved
Can You Evaluate Contractor Performance?
  • Features of Effective Contractor Performance Evaluation Programs
  • Using Results from Contractor Evaluations
When Can You Award Based on Price and Qualifications?
  • Best Value Procurement
  • Design-Build
  • Construction Manager at Risk
  • Job Order Contracting
Mike Purdy's Public Contracting Blog
© 2014 by Michael E. Purdy Associates, LLC
http://PublicContracting.blogspot.com

Monday, December 9, 2013

A Public Construction Project to Remember - The Reconstruction of the White House During Truman's Presidency

The complete reconstruction of the White House during Harry Truman's presidency was perhaps the most historically significant public construction project of the 20th century.

Project challenges described in new book:  I've just finished reading a newly published book that tells the story of this project, and its challenges including the following:
  • Project design indecision
  • Political feuding about funding
  • Bidder pre-qualification
  • The low bid that was shockingly low
  • Delays in producing drawings for the contractor
  • Change orders
  • Over-budget - requiring additional funding requests to Congress
  • Schedule delays and late completion
  • A key subcontractor with a low bid who was missing-in-action and didn't staff the project adequately
  • Labor strike
  • Waiving competitive bidding for the interior decorator
  • And more... 
In The Hidden White House -  Harry Truman and the Reconstruction of America's Most Famous Residence, Robert Klara has written the definitive, not to be surpassed, work on this sometimes overlooked major saving and reconstruction of the White House. 

A riveting story told well:  Robert Klara is a superb story-teller and historian who brings to life the untold stories surrounding this mid-twentieth century reconstruction of the White House.  Klara's narrative is filled with incredible detail, all supported by meticulous research and facts.  What is incredible is that the details do not get in the way, but instead enhance this rich and riveting story.  Klara's book is a delight to read and I found it hard to put it down.  As one presidential historian noted in her book review, "Klara has taken what is basically a construction plan and has made it read like an adventure story."

I'm giving away 3 free copies of the book:  I thoroughly enjoyed reading every page of this engaging book, and think you will too.  On New Years Day (January 1, 2014), I will draw three names from a list and give away (and send) three free copies of The Hidden White House to a lucky trio.  In addition to writing this Public Contracting Blog, I enjoy presidential history and write a Presidential History Blog (and am researching and writing on a book about presidential history).  To be eligible for the book giveaway drawing, all you need to do is sign up for a free email subscription to my Presidential History Blog at http://PurdysPresidentialHistory.blogspot.com.

Burned in 1814:  During the War of 1812, British forces swept into Washington, DC on August 24, 1814 and torched The President's House shortly after President James Madison left town in haste.  The house was re-built but many of the charred timbers that supported the interior of the building were kept in place in the repaired White House, leaving for a future president to address the less than sturdy structure.

Digging the sub-basement in the
demolished White House in 1950
In danger of collapse in 1948:  What is less well known than the 1814 attack on the White House are the unintentional assaults (renovations) of the mansion that occurred with every president.  "Each new 'improvement' meant more holes to be drilled in the wood, more walls to be moved or knocked down, and more weight heaped upon the house," Klara writes.  The abuses heaped upon The President's House over the decades culminated in the almost complete collapse of the building during Harry Truman's presidency.  

Gut and Rebuild:  From November 21, 1948 when the Truman family fled for a safer habitat, to March 27, 1952 when they returned, the interior of the historic home was completely gutted and rebuilt with a steel structure, leaving only the original outside walls remaining from the day in 1792 when  the cornerstone for the building had been laid.  As John Hersey, a writer for The New Yorker, noted about the new White House, "It was as if someone had decided to set up a modern office inside a deserted castle."

Politics:  Klara tells the story of sagging ceilings, stretching and tinkling chandeliers over social events in the White House, and inspections that revealed a sinking and collapsing mansion.  White House officials chose the moment of a state dinner in 1947 to inform the President that the chandelier chain in the East Room was "stretching."  Truman sarcastically noted later that "It was a nice time to tell me."  Concerns grew about the safety of the President and his family and they were eventually moved out to the Blair House across the street.  But Congress still needed to appropriate money for the expensive reconstruction, leaving some financially conservative members of Congress to consider tearing down the entire mansion and building something cheaper.  Ultimately, the outside walls were saved, but the interior was totally re-built.  Congress appointed a commission to oversee the work, but Truman himself played a decisive role in directing the work.

Process:  Klara takes the reader from the discovery of the failing structure through the decision making process about what to about it, to the actual gutting of the interior and saving of historical items (many of which would be cut up and sold as souvenirs), through the delayed and over budget construction process that included the building of an underground bomb-proof shelter. Along the way is the story of the attempted assassination of President Truman who was temporarily residing in the security-challenged Blair House across the street from the White House.

People:  Klara does a masterful job of painting portraits of the key people involved in the decision and actual implementation of the rebuilding of the White House, from members of Congress, to members of the commission in charge of the renovation, to White House staff to the contractors.  These men, and the Truman family, come alive under Klara's steady hand and insightful heart.  


Selecting a contractor:  To give you a sense of how The Hidden White House is amazingly relevant to public construction contracting issues today, and to give you a taste of Klara's writing style, here's an excerpt (headings are mine) from the book on the contractor selection process for the White House renovation project: 
Scope of Work:  On September 26, 1949, the commission [appointed by Congress to manage the project] released its terms for the White House renovation contract.  The document enumerated a job of dizzying proportions: interior demolition; removal and storage of historic decorative elements; shoring, bracing, and underpinning; excavation, ironwork and concrete; plumbing, electrical, and on it went.  The contractor was to stock all raw materials, furnish all equipment, and supply the skilled labor - and do it all within the confines of an 85-by-165-foot shell of fragile historic sandstone.  Here was a long, complicated, nerve-racking job.  Few construction companies in the nation were fit to even try for it.
Pre-Qualified Bidders Only:  [Public] Buildings commissioner [W.E.] Reynolds made clear that inexperienced or undercapitalized contractors need not apply: "The national and historical importance of this project demands that all materials and workmanship be of the highest grade and that the work be executed by individuals, firms or corporations...[with the] most skillful talents in the field of their work."  As a filter, Reynolds required all interested firms to complete a questionnaire.  Only the contractors that met his definition of having "special qualifications and experience" would be invited to submit a bid, and even they would have to do it in person.  At 1:00 P.M. on October 28, 1949, Reynolds opened the doors of the General Services Administration Building's auditorium, where he waited.
Cost-Plus-Fixed-Fee Contract:  Because of the risks and uncertainties of the White House renovation, the commission invited bids on a cost-plus-fixed-fee basis.  This structure provided that the government would reimburse the contractor for all materials and labor necessary to get the job done (the cost), while establishing a set profit (the fixed fee.)  The arrangement afforded a measure of protection to the contractor on a dicey job by guaranteeing his margin.  Even so, on a job this complex and dangerous, bidding was high-stakes poker.
A VERY Low Bid:  In the end, only fifteen contractors had the nerve to play.  The George A. Fuller Company, builders of New York's Flatiron Building, dropped off a bid for $242,500.  From Chicago, Bates & Rogers came in at $950,000.  Most of the contractors had tossed their hats in around the quarter-million-dollar range, and it looked like of of them would snag the job.  At least, it did until PBA administrator Fay Slater rose at day's end and read the lowest bid aloud to the room.  A "murmur of surprise," as the New York Times termed it, rose from the audience.
Contractor Comfortable With Low Bid:  The winner was John McShain, Inc., of Philadelphia, which agreed to take the job for $100,000.  It was madness.  No firm could make a profit on a fee that low.  But once the reporters finally located John McShain, he was entirely composed.  "I figured nobody would go as low as than," remarked the builder, "so I bid it."
Contract Awarded:  Eight days later, a letter from the Public Buildings Administration arrived at McShain's office at Seventeenth and Spring Garden streets.  "Your proposal dated October 28, 1949, for the renovation and modernization of the Executive Mansion, Washington, D.C., is hereby accepted," it said.  The White House renovation now belonged to him.
About Robert Klara:  Robert Klara is also the author of the critically acclaimed book FDR's Funeral Train, another favorite book of mine.  Klara, who lives in New York City, has been a staff editor for several magazines and his freelance work has appeared in The New York Times, American Heritage, and The Christian Science Monitor, among other publications.

Get your free copy of the book:  Don't forget about the drawing for three free copies of The Hidden White House that I will hold on January 1, 2014.  To be eligible, all you need to do is sign up for a free email subscription to my Presidential History Blog at http://PurdysPresidentialHistory.blogspot.com. 

Resources:
 
Mike Purdy's Public Contracting Blog
© 2013 by Michael E. Purdy Associates, LLC
http://PublicContracting.blogspot.com

Tuesday, August 20, 2013

Obtaining Qualified Contractors on Public Construction Projects

Traditionally, public agencies have awarded public construction projects to the low bidder.  In theory, this ensures that the public pays the lowest possible cost for such work.  However, the low bid doesn't always result in the lowest price at the end of the project, nor does it ensure that the low bidder is capable of performing quality work.

Agencies seek more flexibility in award:  In response to concerns about low bidders not performing well and arguing for change orders that will increase the contract cost, public agencies have increasingly been developing alternative methods for awarding public construction projects.  These alternative methods come with their own set of challenges and may actually cost more money, depending on how the selection process is implemented.

Design-Bid-Build:  The following three approaches, based on contractors bidding a fully designed scope of work, are sometimes used by public agencies for ensuring that the contractor selected is qualified to perform the work:

Prequalification:  Under this scenario, contractors must be prequalified and meet certain criteria before being permitted to bid on a project.  Some public agencies are not authorized to prequalify contractors.  For those that are authorized to prequalify contractors, it is important that the criteria used to evaluate qualifications be clear, objective, and not overly restrictive of the bidding pool of contractors.

Bidder Responsibility:   In many cases, bidder responsibility criteria are the same as the prequalification criteria.  The only difference is that all contractors may bid a project rather than just prequalified contractors.  The low bidder must then demonstrate they meet the bidder responsibility criteria.  Prequalification analysis occurs prior to bidding, while bidder responsibility evaluation occurs after bidding, but prior to award.  Like prequalification, bidder responsibility inserts an element of subjectivity into the award process.

Best Value:  A best value selection process moves away from price as the only basis for identifying the successful contractor and instead begins to looks more like a Request for Proposals process, where various evaluation criteria are identified, including price.  Not all public agencies are authorized to conduct a best value selection process, and the process is often criticized for its subjectivity with the result that the public agency may contract with the firm who does not have the lowest bid.

Alternative Project Delivery Methods:  The following two alternative project delivery methods are gaining in popularity with public agencies.  Unlike the models used under a Design-Bid-Build approach, the design is not complete when the contractor is selected under the following two alternative methods:

Construction Manager at Risk:  This process is known by many different names (CM at Risk, CMAR, GC/CM (General Contractor/Construction Manager), and CM/GC (Construction Manager/General Contractor)).  Not all public agencies are authorized to use this process which involves selection of a contractor early in the design process, through a Request for Proposals process, partially based on qualifications and partially based on limited pricing (fee and general conditions work).  The selected contractor then works with the designer in providing various preconstruction services (cost estimating, scheduling, constructability reviews, value engineering, etc.) before the construction cost is negotiated between the parties when the design is sufficiently completed. 

Design-Build:  Under this project delivery method, the public agency uses a Request for Proposals process to select one firm to both design and build the project, eliminating or reducing conflicts between the designer and contractor.  The price is either part of the selection process (which brings with it many of the problems of the traditional low bid award), or the price is negotiated between the partieis when the design is sufficiently complete.  

Indefinite Delivery/Indefinite Quantity:  Also known as IDIQ, this method of public construction is basically an on-call process, in which undefined work is bid ahead of time and one contractor is selected, sometimes based on price alone and sometimes based on price and qualifications.  There are two major forms that IDIQ public construction contracts take:

Job Order Contracting:  Under Job Order Contracting, a contractor is selected partially based on qualifications and partially based on their markup percentage for serving as the general contractor for undefined work that will be assigned as the needs arise.  Establishing the cost of a specific project is typically based on an agreed upon unit price book.  Nevertheless, the contractor and agency must still negotiate the specific cost of work to ensure that units and quantities used in the estimate are appropriate.  Job Order Contracting is sometimes criticized for being more expensive than the traditional low bid process, but it is a more efficient process for ensuring that work is performed in a timely manner.

On-Call Contracting:  On-call construction contracting differs from Job Order Contracting in the selection process in that specific units of work are bid as part of the selection process (rather than relying upon a unit price book).  While the contractor in Job Order Contracting may be required to subcontract out major portions of the work, under on-call contracting, the contractor often performs all or most of the work themselves.  On-Call contracting is an effective tool for minimizing multiple invitations to bid for what are typically smaller dollar amount projects.  

General comments:
  • How much are bidder qualifications worth?  In most of the methods described above, there is some level of subjectivity involved in the selection process as a public agency evaluates and scores bidders based on qualifications and experience.  The result is that the low bidder may not end up being the selected bidder, or the price may be negotiated.  
  • Maintaining fairness and transparency:  In selecting contractors based on factors other than the low price, it is important that the process established be fair and transparent, and that the qualifications and proposals of contractors be rated as objectively as possible.  The low bid process was originally established to avoid public agencies showing favoritism to certain contractors.  Public agencies are now recognizing that the low bidder isn't always the best option for the public.  But in expanding the scope of selection methodologies, there is the risk of shifting back into an environment of favoritism to certain contractors.  These alternative tools must be managed carefully and thoughtfully.
  • Not all agencies authorized to use all methods:  Not all public agencies are authorized to use some of the selection methods outlined here.  State laws differ.  In addition, if there are federal funds involved with a project, public agencies need to work closely with the federal department granting the money to ensure that the selection process complies with federal regulations.
Mike Purdy's Public Contracting Blog 
© 2013 by Michael E. Purdy Associates, LLC 
http://PublicContracting.blogspot.com

Wednesday, October 3, 2012

May Public Agencies Prequalify Contractors?

A Washington state board recently asked for an interpretation of whether public agencies in the State of Washington are authorized to prequalify contractors.  

Contractor concerns:  The prequalification question came up in response to concerns expressed by contractors about one city that routinely prequalifies contractors for public works projects.

No clear answer:  At its September 13, 2012 meeting, the Capital Projects Advisory Review Board (CPARB) was informed by a representative from the State Attorney General's Office that the question posed was an "unsettled area of law in Washington," that there are good arguments on both sides, and that it was an issue for the courts to interpret in the event of a lawsuit.  CPARB was advised that there is no law that authorizes or prohibits prequalification of contractors for all public agencies. 


What agencies may prequalify?  Some have interpreted the fact that there are only three types of public agencies specifically authorized in Washington state law to prequalify contractors as evidence that the Legislature intended to grant this exemption to typical competitive bidding requirements to only the following:
  • WSDOT (State Department of Transportation) for highway work - RCW 47.28.070
  • Public Utility Districts (PUDs) for electrical work - RCW 54.04.085
  • Cities or towns owning an electrical utility for electrical work - RCW 35.92.350
Further contractor action?  It is unclear at this point what action contractors and contractor associations may take to formally challenge the prequalification practices of the city in question.

How to get qualified contractors:  The Legislature has provided public agencies with the ability to help ensure that qualified contractors work on public works projects through the use of Supplemental Bidder Responsibility Criteria, as authorized in RCW 39.04.350 (2).
Mike Purdy's Public Contracting Blog 
© 2012 by Michael E. Purdy Associates, LLC 
http://PublicContracting.blogspot.com

Sunday, June 3, 2012

May Public Agencies in Washington Prequalify Contractors?

Are public agencies in the State of Washington authorized to prequalify contractors on public works projects?  

CPARB discussion:  This was a question that was recently the subject of a discussion at the May 10, 2012 meeting of the Capital Projects Advisory Review Board (CPARB).   At issue were complaints filed by contractors against a city with a prequalification process.

What is prequalification?  Under prequalification, a public agency conducts a separate evaluation process to determine which contractors meet specific criteria and are thus able to submit bids.  

What agencies are authorized to prequalify?  In Washington State, only three types of public agencies are specifically authorized in state law to use prequalification:
  • WSDOT (State Department of Transportation) for highway work - RCW 47.28.070
  • Public Utility Districts (PUDs) for electrical work - RCW 54.04.085
  • Cities or towns owning an electrical utility for electrical work - RCW 35.92.350
Are agencies prohibited from prequalifying contractors?  The general interpretation has been that since the Washington State Legislature has specifically authorized only certain types of agencies to use prequalification, that the authority does not exist for other public agencies to prequalify contractors. 

Attorney General opinion:  The issue of prequalification authority was addressed in an Attorney General opinion from 1993 to the University of Washington.  That opinion concluded that the University did not have authority to require that contractors have an apprenticeship program as a prequalification requirement.

How can agencies get qualified contractors?  While the prequalification process prior to bidding is not authorized, public agencies are authorized to utilize supplemental bidder responsibility criteria.  After bid opening, the agency requests the low bidder to submit specified documentation demonstrating that they meet the published criteria. In order to be determined to be a responsible bidder and awarded the project, the low bidder must meet the supplemental bidder responsibility criteria. 

Resources for responsibility criteria: 
  • RCW 39.04.350 addresses supplemental bidder responsibility criteria
Mike Purdy's Public Contracting Blog 
© 2012 by Michael E. Purdy Associates, LLC 
http://PublicContracting.blogspot.com

Wednesday, May 23, 2012

State Charged with Public Works Procurement Process Reform

Under the terms of legislation approved this year, the Washington State Department of Enterprise Services (DES) will be conducting an ambitious review of the state's current public works procurement processes and will make reform recommendations.  

The state's capital budget bill (ESB 6074 - Section 1022) outlined the charge to DES but allocated only $75,000 to complete the quick turn-around study.

Focus of report:  Because of the limited funding for the study, DES may concentrate some of its focus on state agencies, although the legislation broadly applies to the state's "current public works procurement processes."  The report is required to include historical data on:
  • Use of change orders
  • Use of Job Order Contracting
  • How competitive public works contracts are advertised
  • Contract closeout procedures
In addition, DES told the Capital Projects Advisory Review Board (CPARB) on May 10, 2012 that the study may address a number of other topics, including the following:
  • Best value procurement
  • Use of electronic signatures
  • Standardizing bidding thresholds for all agencies
  • Prequalification of contractors on Design-Bid-Build projects
Labor union concerns:  The impetus for the study came from the state employees labor union (Washington Federation of State Employees) and the impact that some public works processes are having upon their work.  For example, union representatives expressed concern in testimony to the Legislature that some public works change orders are outside the original scope of work of the project and represent work that state employees, and not contractors, should be performing.

Stakeholder input:  In developing its report and recommendations, DES may consult with the Capital Projects Advisory Review Board (CPARB) for advice and assistance, and will also solicit input from various stakeholders. 

Other concurrent studies:  In addition to the study being conducted by DES, two other organizations are conducting reviews of public works contracting, specifically the alternative public works contracting processes authorized by RCW 39.10:
Public works legislation in 2013:  It is anticipated that next year the Legislature will be reviewing significant legislation addressing public works procurement and contracting procedures:
  • CPARB:  CPARB's intent is to recommend legislation to the Legislature in January 2013.  That legislation will take into account recommendations from JLARC as well as CPARB's Reauthorization Subcommittee.  It is anticipated that the legislation will make recommendations for certain changes to the GC/CM, Design-Build, and Job Order Contracting laws, and will authorize continuation of these alternative methods beyond June 2013, which is when the current law expires. 
  • DES:  DES is required to submit its report to the Legislature and Governor by December 15, 2012, and to include draft legislation to implement the recommendations in its report.  This legislation will also presumably be considered by the Legislature in 2013.
Overlap between studies:  All three reviews (DES, CPARB, JLARC) will be examining Job Order Contracting processes and practices.

Mike Purdy's Public Contracting Blog 
© 2012 by Michael E. Purdy Associates, LLC 
http://PublicContracting.blogspot.com

Sunday, March 25, 2012

Obtaining Qualified Subcontractors on GC/CM Projects

On GC/CM (General Contractor/Construction Manager) projects in Washington State, there are a number of tools available to both the contractor and the public agency to ensure that subcontractors working on the project are qualified.

Award to Low Bid Required:  The issue of qualifications of subcontractors is particularly important since RCW 39.10.380 requires that "all subcontract work and equipment and material purchases" must be competitively bid by the GC/CM and awarded to the low responsible bidder with a responsive bid.

4 Subcontractor Selection Tools:  There are four primary tools available to ensure qualified subcontractors on GC/CM public works projects:

  1. Prequalification: When the GC/CM and public agency determine that, for specific subcontract bid packages, it is "in the best interest of the project and critical to the successful completion" of the work, the GC/CM and public body may go through a process to prequalify which subcontractors are eligible to bid on specific subcontract bid packages.  This process, which is outlined in RCW 39.10.400, ensures that only subcontractors with the necessary experience are permitted to bid on specific bid packages.  There is a process outlined for determining that prequalification (technically referred to as “bidder eligibility”) is necessary and an appeals process.
  1. Bidder Responsibility:  On all subcontract bid packages in which prequalification is not used, the GC/CM and public agency must “include the specific objective criteria that will be used…to evaluate bidder responsibility.” (RCW 39.10.380 (2))  Whereas prequalification occurs prior to bidding, bidder responsibility evaluation occurs after subcontract bids have been submitted and prior to award.  The GC/CM is required to award to the lowest responsible bidder with a responsive bid.  The bidder responsibility criteria are in addition to the mandatory bidder responsibility criteria outlined in RCW 39.06.020 for subcontractors.  The bidder responsibility criteria help ensures that the low subcontract bidder has the requisite experience, qualifications, and personnel to perform the subcontract work.
  1. Bonding:  On subcontract bid packages of more than $300,000, subcontract bidders must submit a bid bond. RCW 39.10.380 (3) doesn’t appear to include the option for the GC/CM to receive alternate forms of a bid guaranty.  Any subcontractor awarded a subcontract by the GC/CM for more than $300,000 must also provide a performance and payment bond for the contract amount to the GC/CM.  The bid, performance, and payment bond requirements provide an added level of review into the qualifications and financial capability of subcontractors awarded work under a GC/CM project.
  1. Qualifications Based Selection of Certain Subcontractors:  In 2010, the Washington State Legislature adopted an alternative method for a GC/CM to select mechanical and electrical subcontractors. Rather than bidding this work, RCW 39.10.385 provides that the GC/CM may select these subcontractors before the design of the project is complete based on their qualifications, fee, and general conditions costs – a process very similar to how public agencies are required to select the GC/CM.  By having these key subcontractors on board during pre-construction, they are able to provide valuable services in helping to develop the design.
Project Delivery Methods:  In addition to the traditional Design-Bid-Build project delivery method (also known as the traditional low bid model), there are three alternative public work delivery methods authorized in Washington state:
  • GC/CM
  • Design-Build
  • Job Order Contracting
Other Names and Practices for GC/CM:  GC/CM (General Contractor/Construction Manager), as a project delivery method, is also known by a variety of other terms in other parts of the country: Construction Manager at Risk, CM at Risk, CMAR, and CM/GC (Construction Manager/General Contractor).  Different states have different requirements governing subcontractor selection and other facets of the GC/CM process.

Mike Purdy's Public Contracting Blog 
© 2012 by Michael E. Purdy Associates, 
LLC http://PublicContracting.blogspot.com

Tuesday, July 19, 2011

When Are Contractor Qualification Requirements too Restrictive?

It's important for public agencies to obtain qualified contractors on public works projects.  It's also important to have a wide pool of competitive contractors eligible to bid on construction projects.  

Striking a Balance:  When public agencies pre-qualify contractors, or establish responsibility criteria that impact what contractor may be awarded a project, it's important that the requirements be relevant for the project and not overly restrictive of the bidding pool.

Wyoming's Controversy:  A number of Wyoming contractors are upset at the overly restrictive pre-qualification requirements placed on a $7 million pipeline project that effectively cuts them out of bidding the project on August 9, 2011.  Only five contractors have pre-qualified and they're all from outside of Wyoming (Colorado, Montana, and Florida).  

Are the Requirements Reasonable?  The contractors have taken their concerns to the governor's office, the legislature, and the agency bidding the project (Shoshone Municipal Pipeline Joint Powers Board), contending that the requirement for having constructed projects with two miles of 24-inch pipeline in the past five years is an unreasonable requirement.  "There hasn't been that much 24-inch pipe laid in the state in the past five years," Bruce Hicks of Excel Construction Co. complained.  In addition, contractors are questioning the relevance of the 24-inch requirement, since "it all goes together the same way" regardless of the diameter of pipe.  

Bid Preference Law Not Applicable:  Wyoming recently passed a bid preference law giving in-state contractors a preference if they are within 5 percent of the low bid from an out of state firm.  However, with the project requiring pre-qualification, the Wyoming firms won't even get the chance to bid to see if the bid preference might be applicable.

More About the Wyoming Issues:  Click here to read a Casper Star-Tribune article on the controversy, or click here to read an article from codyenterprises.com.

Washington State's Experience:  In Washington State, only a few types of public agencies are authorized to pre-qualify contractors.  However, under RCW 39.04.350, all public agencies may establish supplemental bidder responsibility criteria to evaluate whether the low bidder is a responsible bidder capable of performing the work.  In the four years that the bidder responsibility law has been in effect, contractors have voiced concerns about how some agencies have inappropriately implemented the law. 

Solving the Problem in Washington State:  The state's Capital Projects Advisory Review Board (CPARB) has appointed a task force to address the issues and come up with recommendations.  In March 2011, CPARB joined with a number of industry associations to sponsor a training session on the bidder responsibility law.  Efforts are underway to conduct additional training this fall.  The task force will also be recommending changes to CPARB's Suggested Guidelines for Bidder Responsibility to address some of the concerns raised.

Checklist:  I've done a lot of training on Washington's bidder responsibility requirements and have developed a checklist to help public agencies work through the issues when they utilize the criteria.  You can find the checklist on my website by clicking here.
Mike Purdy's Public Contracting Blog 
© 2011 by Michael E. Purdy Associates, LLC 
http://PublicContracting.blogspot.com

Tuesday, May 10, 2011

4 Key Tools to Obtain Qualified Subcontractors on GC/CM Projects

In Washington State, GC/CM (General Contractor/ Construction Manager) is one of three alternative public works contracting procedures that may be used for certain public works construction projects in lieu of the traditional low bid, or Design-Bid-Build, process.

Under GC/CM, all construction work must be publicly bid to subcontractors by the selected contractor (the GC/CM) and awarded to the low bidder.  In order to help ensure that the subcontractors are qualified, there are four key tools that RCW 39.10 describes that may (or must) be used:
  • Prequalification:  Officially known in state law as "subcontractor eligibility to bid," a GC/CM and public agency may essentially prequalify which subcontractors may submit a bid on specific subcontract bid packages.  To use this process, a public hearing addressing the intent to prequalify subcontractors must be held along with the proposed criteria, which may be modified based on feedback received at the hearing.  To utilize this process, the GC/CM and public agency must make a determination that doing so would be in the best interest of the project and critical to the successful completion of the subcontract bid package work.  A Request for Qualifications is then advertised and qualifications are received and evaluated based on the established criteria.  Only those subcontractors meeting the criteria and/or threshold number of points established in the RFQ are eligible to submit a subcontract bid.
  • Responsibility Criteria:  If the prequalification process is not used, the GC/CM is required to include "specific objective criteria" that the GC/CM and public agency will use to evaluate whether the low subcontract bidder is a responsible bidder.  The primary difference between the prequalification and responsibility criteria processes is one of timing.  In prequalification, a determination of responsibility is made prior to bidding, while under the responsibility criteria section of state law (RCW 39.10.380 (2)), the determination is made after submittal of bids and prior to award of a subcontract by the GC/CM.  The responsibility criteria in GC/CM subcontract bidding is very similar to the Supplemental Bidder Responsibility Criteria permitted on Design-Bid-Build projects (RCW 39.04.350).
  • Early Selection of Mechanical and/or Electrical Subcontractors:  Under a 2010 law approved by the Legislature, a GC/CM may select the mechanical and/or electrical subcontractors early in the process, during the preconstruction phase before the construction documents have been finalized.  The purpose of this early selection process is to bring the experiences and expertise of these key subcontractors to the preconstruction phase.  Under this process, these subcontractors are selected through a very similar process by which the GC/CM is selected by the owner based on qualifications and bids for fee and general conditions work.  The actual construction cost is negotiated between the GC/CM and subcontractor and that price is then folded into the negotiated Maximum Allowable Construction Cost (MACC) between the GC/CM and owner.  This process has been used just a couple of time so far and is outlined in detail in RCW 39.10.385.
  • Payment and Performance Bonds:  For subcontract bid packages over $300,000, the subcontractors are required to submit a payment and performance bond to the GC/CM.  The owner bears the cost for these bonds as part of the MACC.  In this difficult construction economy, bonding companies are more carefully evaluating the financial viability of subcontractors.  Thus, bonding becomes an important tool to help ensure that only financially healthy subcontractors participate on these public GC/CM projects.  A GC/CM may also require a payment and performance bond for subcontract bid packages less than $300,000.
Applying the Tools:  Each GC/CM project is different: 
  • Prequalification may not be appropriate for some subcontract bid packages, and the time it takes to go through the process may limit its use.  
  • Bidder responsibility must be used for all subcontract bid packages where prequalification is not used
  • The early selection of the mechanical and/or electrical subcontractors is a time-consuming process that a project schedule may not allow for.  Some owners and GC/CM see value in this process while for others and for specific projects, it may not be as appropriate.
  • Bonding is required on all subcontract bid packages over $300,000.
Mike Purdy's Public Contracting Blog 
© 2011 by Michael E. Purdy Associates, LLC 
http://PublicContracting.blogspot.com

Tuesday, November 2, 2010

Florida County to Prequalify Contractors

Concerned about the track record of a particular contractor, county officials in Florida have taken steps to establish a prequalification process for public works contractors, rather than relying on evaluating the qualifications of the low bidder after bids have been received.

Current County Practice:  Prequalification would allow Lee County to determine what contractors are permitted to bid County road projects.  Currently, any contractor can bid on the County's projects.  The County then evaluates the low bidder's responsibility based on the firm's past job history, its financial strength, its payment record to subcontractors, environmental compliance, and history of litigation. 

On November 1, 2010, the County commissioners voted to move ahead with establishing a prequalification process.  

County Concerns with Contractor:  Although the County maintained that the move toward prequalification was not targeting any contractor, the County has had a number of problems with Michigan-based Posen Construction.  The County's concerns with Posen include the following:
  • Asbestos was identified on Posen's projects.
  • Posen has a history of not paying subcontractors.
  • Additional County time to oversee Posen's projects.  County commissioner Tammy Hall complained that "if we have to spend twice as much staff time, it's not really a low bid."
Additional Information:  From News-Press.com, click here.

When Should Contractor Qualifications Be Determined?  Prequalification and bidder responsibility essentially rely on the same criteria for determining whether a contractor should be awarded a public works project. The difference is in the timing.  Under prequalification, the decision about a contractor's qualifications is made prior to bidding and limits what contractors can submit a bid.  Under bidder responsibility, the decision about a contractor's qualifications is made after bids have been submitted, and the low bidder is evaluated to determine if they are qualified and meet pre-established criteria.

Bidder Responsibility in Washington State:  In Washington State, RCW 39.04.350 allows public agencies to develop bidder responsibility criteria to be used in evaluating whether the low bidder is qualified to perform a project.  The 2007 law has been the source of significant controversy in the state, with some contractors complaining about overly restrictive criteria that limits their ability to be responsible.  A task force with public agencies, contractors, and subcontractors is currently meeting to develop common ground in understanding how bidder responsibility should be implemented.

Prequalification in Washington State: Only a few types of public agencies in Washington State are specifically authorized to prequalify contractors, including the following:

Mike Purdy's Public Contracting Blog (© 2010 by Michael E. Purdy Associates) 
http://PublicContracting.blogspot.com

Thursday, August 12, 2010

The Dilemma of Low Bids and Contractor Performance

The Question:  Are public agencies required to award public works construction projects to the low bidder, even if the low bidder has a history of poor performance or a pattern of filing unjustified change order requests and claims?

While there are some tools available to public agencies to help manage the low bid process, those tools must be managed carefully, and even then it may be difficult to disqualify the low bidder.

Not all agencies are authorized to use all of the following tools.  Check your local and state laws to determine if you can use these tools.  The following is a very quick summary introduction to some of the issues involved.

Pre-Qualification:  Under this process, a public agency only accepts bids from contractors who have already gone through a qualifications-based short listing process.  It is often authorized for agencies with specialized work, such as for electrical work.  In theory, it limits the bidding pool only to qualified contractors.

Bidder Responsibility Criteria:  This process is similar to Pre-Qualification except that the review of the contractor's qualifications occurs after the bid submittal deadline instead of before it.  Criteria must be relevant, fair, defensible, and not overly restrictive of the bidding pool.  In Washington State, supplemental bidder responsibility criteria may be used and are outlined in RCW 39.04.350.

References:  Reference checks with previous owners is often a part of a bidder responsibility analysis.  Owners desiring to use references as a means to disqualify a bidder should proceed with caution.  There are often personality conflicts that may have occurred on a previous project that may impact the comments of a reference.  Public agencies should provide bidders who may be disqualified based on reference checks with the opportunity to provide feedback on the comments received.

Performance Evaluation Program:  If implemented correctly, this can be one of the most effective tools for not awarding contracts to contractors with a consistently poor record of performance.  A performance evaluation program should be included in the bidding and contract documents, with clear and relevant evaluation criteria, an appeal process, and how poor performance evaluation scores will be used in making future award decisions.

Think Strategically:  If your agency is facing specific issues about unqualified contractors being awarded projects, it is best to think strategically about the particulars of your situation as well as what is authorized by your state and local laws.  If you would like assistance in thinking through these issues, or in developing a contractor performance evaluation program, please contact me.

Tuesday, June 15, 2010

New Medical Construction Rosters Approved for University of Washington

The Washington State Legislature approved legislation that permits the University of Washington to pre-qualify contractors for construction rosters related to critical patient care or specialized medical research facilities (Medical Rosters).  

Pre-Qualification vs. Bidder Responsibility Criteria:  The intent of the new law is to permit the University of Washington to establish pre-qualification requirements for this highly specialized and sensitive work that contractors must meet to be placed on the roster.  The UW operates both the UW Medical Center and Harborview Medical Center. 

Prior to passage of the new law, the only tool available for ensuring that the low bidder was a responsible bidder was for the University to add supplemental bidder responsibility criteria, as authorized by RCW 39.04.350.  This can often be a time-consuming process with responsibility evaluated after bid opening. 

By essentially pre-qualifying contractors for the Medical Roster, the University of Washington will not have to establish separate supplemental bidder responsibility criteria on each separate project relating to medical facilities, thus saving time.

Modeled After Existing Laws:  Substitute Senate Bill 6355, which became effective on June 10, 2010, is modeled heavily after both the current Small Works Roster law authorized in RCW 39.04.155 and portions of the GC/CM law in RCW 39.10.360.  There are significant portions of each of these laws that are included in the new law, some word for word.

Key Features:   The new Medical Roster law, which adds a new section to chapter 28B.20 RCW, includes the following key features:
  • Dollar Threshold:  The roster may be used for projects equal to or less than $5 million.
  • Applicability:  The Medical Roster applies to "construction, renovation, remodeling, or alteration of improvements within a building that is used directly for critical patient care or highly specialized medical research."
  • Relationship with Small Works Roster:  The Medical Roster may be used in lieu of the provisions of the Small Works Roster program (RCW 39.04.155).
  • Single or Multiple Rosters:  A single Medical Roster may be created, or multiple rosters may be used based on different trade specialties or categories.
  • Advertisement:  The University of Washington must advertise annually announcing the Medical Roster to contractors.  The law specifies a number of subjects that must be addressed in the public solicitation, including the reasons for using the roster, a description of the contractor qualifications required to be placed on the roster, the form of contract to be used, the evaluation and appeal process, etc.  Contractors may be added at any time during the year.
  • Evaluation Criteria:  The University must establish an evaluation committee to evaluate the qualifications of contractors desiring to be placed on the roster.  Evaluation criteria must include at least the following:  a) Ability of a contractor's professional personnel; b) Contractor's past performance on similar projects, c) Contractor's ability to meet time and budget requirements, d) Contractor's ability to provide preconstruction services, e) Contractor's capacity to successfully complete the project; f) Contractor's approach to executing projects, g) Contractor's approach to safety and their safety history, h) Contractor's record of performance, integrity, judgment, and skills.
  • Quotation Procedure:  The University of Washington must establish a procedure to obtaining quotations from all contractors on the Medical Roster to ensure competitive process.
  • MWBE:  The University of Washington must make an effort to solicit proposals from certified minority and woman owned contractors.
  • Reporting:  Annually, beginning in September 2010, a university using the Medical Roster must provide a report to the Capital Projects Advisory Review Board on the usage of the roster.
  • Sunset:  The Medical Roster process for awarding such contracts terminates as of June 30, 2015.
Pre-Qualification:  The new law follows in the footsteps of existing statutes that permits certain types of government jurisdictions to pre-qualify contractors for specific work.  For example, Public Utility Districts must pre-qualify contractors for electrical work (RCW 54.04.085).

Subjective Process:  The Medical Roster law provides the University of Washington with significant latitude in selecting only qualified contractors for the roster, and requires that the evaluation criteria include highly subjective criteria relating to the integrity and judgment of the contractors.  These subjective criteria have caused significant concerns by contractors when used in supplemental bidder responsibility criteria.


Wednesday, May 19, 2010

Tools for Selecting the Best Contractor

It's important that the contractor selected for a public works project be qualified and capable of successfully performing the project.  

Generally, there are three points in time when a public agency can review contractor qualifications:
  1. Prior to Advertising - Prequalification
  2. Prior to Award - Bidder Responsibility
  3. Prior to Performance - Specification Qualifications
Prequalification:  Under Prequalification, the public agency conducts a separate evaluation process to determine which contractors meet specific criteria and are thus able to submit bids.  Contractors may protest the Prequalification process which may lead to delays in the project.  In addition, of course, there may be protests and delays at the point of award. 

In Washington State, only three types of public agencies are specifically authorized to use Prequalification:
  1. WSDOT (State Department of Transportation) for highway work - RCW 47.28.070
  2. Public Utility Districts (PUDs) for electrical work - RCW 54.04.085
  3. Cities or towns owning an electrical utility for electrical work - RCW 35.92.350
The general interpretation has been that since the Washington State Legislature has specifically authorized certain types of agencies to use prequalification, that the authority does not exist for other public agencies to prequalify contractors.

Under the GC/CM (General Contractor/Construction Manager) project delivery method, the GC/CM may prequalify subcontractors prior to competitively bidding subcontract bid packages (RCW 39.10.400).

Bidder Responsibility:  Bids should be awarded to the responsible bidder submitting the low responsive bid.  Responsiveness deals with the bid and whether the bid complies in all material respects to what was required in the bidding documents.  Responsibility, on the other hand, relates to the bidder and whether they are capable and qualified to perform the project.  

RCW 39.04.350 authorizes public agencies in the State of Washington to establish relevant supplemental bidder responsibility criteria for public works projects, and to evaluate whether the low bidder meets these criteria.  

There has been a lot of controversy since this law was adopted in 2007 about how some public agencies are implementing the law.  Contractors have raised concerns about overly restrictive and anti-competitive criteria that have been used.  A Task Force to address these concerns has been created by the Capital Projects Advisory Review Board (CPARB).  The next meeting of the Task Force is on May 20, 2010.

Specification Qualifications:  Technical specifications frequently require that the contractor performing the work of certain sections in the specifications must meet specific qualification requirements related to years of experience or certifications.  Prior to the work being performed, it is the responsibility of the public agency to ensure that the contractor performing the work meets any qualification requirements outlined in the specifications.

What's the Difference?  Functionally, each of these tools accomplishes the same objective of ensuring the use of qualified contractors on public works projects.  The primary difference relates to when the review occurs of the contractor's qualifications.  

The Challenge:  Each of these tools has a level of subjectivity that requires public agencies to carefully define their objectives.  The challenge for public agencies is to protect the public's interests and get the best contractor at the lowest price (primary purpose of public bidding), while at the same time ensuring a fair and transparent selection process for the contracting community (secondary purpose of public bidding).

Training:  In mid-April 2010, I taught a five and a half hour class for the City of Bellingham on how to develop and implement Supplemental Bidder Responsibility Criteria on public works projects.  I am thinking of offering a similar class sometime in the fall.  If you're interested in such a class, please contact me.