Monday, June 30, 2008

Calculating Retainage on Public Works Contracts

On public works contracts in Washington State, public agencies are required to withhold 5% of each progress payment as Retainage. The Retainage is a trust fund for the protection of the Washington State Department of Revenue for unpaid taxes and for workers, subcontractors, and suppliers who have not been paid. See chapter 60.28 RCW.

When calculating the amount of Retainage, a question frequently comes up: Is the Retainage calculated on the amount earned by the contractor before or after the application of the sales tax amount?

Answer: Retainage should be calculated before the sales tax amount, and just on the amount actually earned by the contractor.

In other words, take the amount earned by the contractor for the month (without sales tax), take 5% of that amount to calculate Retainage, and then add sales tax to the amount earned by the contractor for the month. The following chart illustrates how to calculate the Retainage:

$100,000.00

Total amount earned by the contractor

$5,000.00

Minus 5% Retainage

$95,000.00

Equals total amount earned and due to Contractor

$9,000.00

Plus sales tax at 9% (King County rate) calculated on the total amount earned by the contractor

$104,000.00

Total payment to contractor (total amount earned and due to contractor plus sales tax amount)

Insurance in the Construction Industry - Training Seminar


Insurance in the Construction Industry – Seminar

When: October 16-17, 2008
Where: Bellevue Courtyard Marriott -- Bellevue, WA
Cost: $422.50 for one day and $695 for both days
Sponsored by: The Seminar Group

For more information about the agenda and faculty, or to register, call 800-574-4852 or visit The Seminar Group



Saturday, June 28, 2008

WSDOT Public Hearing on FY 2009 DBE Goals

The Washington State Department of Transportation (WSDOT) will hold a public hearing on July 8, 2008 from 3:00 p.m. to 5:00 p.m. at the NewHolly Neighborhood Campus Gathering Hall, 7054 32nd Avenue South, Seattle, WA.

The purpose of the hearing is to receive public comments on WSDOT’s proposed goal for Disadvantaged Business Enterprise (DBE) participation on Federal Highway Administration (FHWA) assisted projects. The proposed goal for federal fiscal year 2009 is 15.85%. The federal fiscal year starts on October 1, 2008 and ends on September 30, 2009.

More detailed information about the hearing and contact and comment information is available by clicking here for the flyer on the public hearing.

AIA Amends A312 Payment Bond

The American Institute of Architects (AIA) recently announced interim amendments to their popular A312 Payment Bond form that has been required by many owners from construction contractors since 1984.

Due to a series of court cases about certain provisions of the bond, some sureties have been hesitant to use the A312 Payment Bond without amendments to it in order to protect their interests. At issue are decisions by courts in Maryland, Virginia, and Florida that have strictly held the sureties to the time requirements of the bond for the bonding company to respond to claims.

Paragraph 6 of the A312 Payment Bond imposes certain requirements on the surety to respond to a claimant within 45 days after the surety receives the claim. The surety is further required to state the amounts of the claim that are undisputed and their basis for challenging any amounts of the claim that are disputed.

The courts essentially ruled that when a surety fails to provide the appropriate response within the 45 day period, they waive their defense against the claim and become liable for the full amount of the claim.

In response to the court cases, the AIA has developed interim amendment language to the A312 Payment Bond until they are able to meet with all of the major stakeholders and make appropriate permanent changes in the bond form. The revised language adds the following paragraph:

“The Surety’s failure to discharge its obligations under this Section 6 shall not be deemed to constitute a waiver of defenses the Surety or Contractor may have or acquire as to the claim. However, if the Surety fails to discharges its obligations under this Section 6, the Surety shall indemnify the Claimant for the reasonable attorney’s fees the Claimant incurs to recover any sums found to be due and owing to the Claimant.”

Owners should not be surprised when they receive an A312 Payment Bond with amendments to Paragraph 6, limiting the surety’s liability in the event they fail to provide the notice within the time period specified.

For reference, the following are the three court cases that have triggered this recent activity of changing the Payment Bond:

  • National Union Fire Insurance Co. of Pittsburg v. David A. Bramble, Inc., 879 A. 2d 101 (Md. 2005)
  • Casey Industrial, Inc. v. Seaboard Surety Co., 2006 WL 2850652 (E.D. Va. Oct. 2, 2006)
  • J.C. Gibson Plastering Co., Inc. v. XL Specialty Insurance Co., 2007 WL 2916399 (M.D. Fla. Oct. 8, 2007)

The National Association of Surety Bond Producers (NASBP) has a useful PowerPoint presentation with additional background on the court cases and the problems with the A312 Payment Bond. Obviously, this is written from the perspective of sureties, but it seems fairly balanced.

In addition Construction WebLinks also has a good article about the issue.

Thursday, June 26, 2008

Public Hearing on Prevailing Wage Rules


The Washington State Department of Labor and Industries will be conducting a public hearing to amend the Washington Administrative Code (WAC) in order to address legislative increases in the amounts charged by Labor and Industries for approval of prevailing wage forms required on public works construction projects (“Statement of Intent to Pay Prevailing Wages” and “Affidavit of Wages Paid”).

The hearing will be held on July 25, 2008 at 9:00 a.m. at the Department’s office at 7273 Linderson Way SW, Tumwater Washington.

The current regulations, WAC 296-127-040 and 296-127-045, include the actual dollar amount of the fee charged by Labor and Industries.

When the Washington Legislature approved EHB 3381, effective July 1, 2008, it formally increased the approval amount for each form from $25 to $40.

Rather than amend the WAC to increase the fee amount, the Department of Labor and Industries is proposing to amend the WAC so that the WAC simply references RCW 39.12.070, the section of the law where the dollar amount charged for the forms is codified. This change will make maintenance of the WAC easier for the Department and they will not have to amend the WAC every time the Legislature increases the fees.

This is a housekeeping amendment to the WAC and has no significant impact on the construction industry. The impact of raising the fees occurred when the Legislature approved the increase.

Written comments on the proposed change in the WAC may be made as follows:

By mail to:
Sally Elliott
Specialty Compliance Services Division
Post Office Box 44400
Olympia, WA 98504-4400

By electronic mail to: yous235@lni.wa.gov

By fax: 360-902-5292 (Comments submitted by fax must be 10 pages or less.)

Comments must be received by the Department of Labor and Industries no later than July 25, 2008.

Wednesday, June 25, 2008

Responsiveness vs. Responsibility

The words “responsiveness” and “responsibility” sound very similar, but in public works contracting, they means two entirely different things.

“Responsiveness” refers to whether a bid is responsive. In other words, did the bidder submit a bid that responded to and was in compliance with what was requested in the bidding documents?

Typical issues of responsiveness include the following:

  • Was the bid submitted by the bid submittal deadline?
  • Did the bidder sign the bid?
  • Was a bid guaranty in the appropriate amount submitted with the bid?
  • Did the bidder submit a bid on all required items?
  • Did the bidder acknowledge all addenda issued?
  • Was a list of subcontractors submitted with the bid, if required? For example, in Washington State, RCW 39.30.060 requires that the bidder submit a list of subcontractors with the bid who will be performing HVAC, electrical, and mechanical work if the project is estimated to cost $1 million or more.

A public agency should reject a bid as non-responsive that is materially different from the requirements of the bidding documents. A public agency may waive an irregularity in the bid as an informality if the irregularity is immaterial.

The test as to the materiality of a variance in a bid is whether it gives a bidder a substantial advantage or benefit not enjoyed by other bidders (Gostovich v City of West Richland, March 1969).

“Responsibility” on the other hand refers not to the bid, but to the bidder. The question asked regarding responsibility is whether the bidder is capable and qualified to perform the project.

In Washington State bidder responsibility on public works projects is governed by a law that became effective on July 22, 2008. RCW 39.04.350 defines certain mandatory bidder responsibility criteria and permits public agencies to also establish supplemental bidder responsibility criteria that are relevant to a specific project. Developing supplemental bidder responsibility criteria takes great care to ensure that the criteria are relevant to the project. The Capital Projects Advisory Review Board (CPARB) has developed Suggested Guidelines for Bidder Responsibility that many public agencies will find useful in understanding the State's bidder responsibility law.

Both responsiveness and responsibility have certain levels of subjectivity in making a determination and both are based on the particular facts of a situation. There are a number of court decisions that help shape how these issues are interpreted.

I have developed a training class addressing responsiveness and responsibility issues in public works contracting. Please contact me if you are interested in more information about the training.

Monday, June 23, 2008

Bidder Responsibility Training on June 25th

There’s still time to sign up for the web conference on the new Bidder Responsibility law which is applicable to all public agencies in Washington State. The web conference (from your own computer and telephone) will be held on Wednesday, June 25, 2008, from 11:30 a.m. to 1:00 p.m.

I am one of the presenters along with local attorney, Arne Hedeen. The training is sponsored by Contract Solutions Group and costs $129 for a single connection at which you may have multiple attendees.

For more information and to register, click here.

If you can't make this web conference and are interested in me providing this training to your agency or a group of agencies, please contact me.