Monday, October 21, 2013

What You Need to Know About Liquidated Damages

Most public works contracts include a provision giving the public agency the right to assess liquidated damages against the contractor, usually a fixed dollar amount for each day the contractor fails to complete the work by the agreed upon date for substantial completion.

Why include Liquidated Damages?  Liquidated damages is a tool that public agencies may use to help ensure that the contractor performs the work consistent with the schedule in the contract documents.  Liquidated damages are intended to fairly compensate a public agency for costs that may be incurred by the contractor's failure to complete the work in a timely manner.

Establishing the Liquidated Damage amount:  It is not normally possible to determine ahead of time what the actual costs may be for a public agency in the event of the contractor's delay in completing the project.  In establishing the amount of liquidated damages to include in the bidding documents and contract, public agencies should go through a process to estimate what their costs might be.  In other words, there should be some rational basis for the amount of liquidated damages.  Some common factors that often go into establishing the liquidated damage amount include the following:
  1. Temporary facility costs for the public agency if the project is not completed on time
  2. Administrative staff costs of managing the project for a longer period of time
  3. Additional fees paid to the designer (architect/engineer) or a third party construction manager required to provide services for a longer period of time
  4. Revenue loss for the public agency if the facility is not completed in a timely manner
  5. Temporary systems and security for the project (e.g. fire watch)
  6. Agency costs for additional storage time for furniture or equipment
  7. Regulatory financial sanctions against the public agency for failure to meet a deadline
Can Liquidated Damages be too high?   Yes, liquidated damages, even when calculated based on likely costs, may be too high.  In establishing the per day amount for liquidated damages based on potential costs, public agencies should evaluate the reasonableness of the amount, and the potential risks of an amount that is too high.  Factors to consider in establishing the liquidated damage amount include the following:
  • Don't discourage bidding:  Not so high that it either discourages bidders from bidding the project.
  • Don't risk higher bids:  Not so high that it encourages bidders to submit higher bid prices to mitigate their perceived risk in being potentially assessed the liquidated damage amount.
  • Incentive for timely performance:  Should be a sufficient amount so that it serves as an incentive for the contractor to complete the work on time.
When does "substantial completion" occur?  Liquidated damages may be assessed up to the required substantial completion date.  Substantial completion occurs when the public agency has beneficial use and occupancy of the facility for its intended purpose.  Not all of the punch list work must be completed, but the owner must be able to actually use the facility.

Assessing liquidated damages:  Many public agencies are hesitant to actually assess liquidated damages against a contractor even if the contractor is late in completing the work.  The reasons for a delay in completion must be documented in order to make a case to assess liquidated damages.  To the extent that any of the delays are not the fault of the contractor, the public agency should grant an extension of time.  All completion past the required date of substantial completion should be accounted for either through the use of liquidated damages, and/or granting an extension of time.

Practical tips:
  • Worksheet:  Develop a worksheet to help you calculate liquidated damages to include on each project.
  • Fair Liquidated Damage amount:  Conduct a risk analysis for each project to make sure the liquidated damage amount is neither too high nor too low.
  • Keep records:  Maintain careful records during construction to document contractor delays.
  • Assess damages and/or grant days:  Account for all of the late completion days after the required substantial completion date by either assessing liquidated damages, and/or granting an extension of time for some or all of the days.
Note:  This blog posting is a repeat of one from February 25, 2013. 
Mike Purdy's Public Contracting Blog 
© 2013 by Michael E. Purdy Associates, LLC 
http://PublicContracting.blogspot.com

Wednesday, October 16, 2013

Detecting Counterfeit Payment and Performance Bonds

Changes in technology have given rise to a number of cases where contractors have forged Payment and Performance Bonds, leaving the public unprotected.

What do bonds do?  Most public agencies require Payment and Performance Bonds for public works construction projects.  These bonds are important tools to protect the public in the event the contractor either fails to pay subcontractors, suppliers, and workers, or the contractor fails to perform the work.

Check the bonds:  Here's a quick list of things to do to help ensure that the Payment and Performance Bonds you receive from contractors are not counterfeit.
  • Evaluate the contractor's reputation:  Have you done business with the contractor in the past?  What is their reputation?  Are they are new and unknown contractor?   If you aren't familiar with the contractor, you may want to investigate the legitimacy of the bonds. 
  • Review the bonds:  Are there irregularities or inconsistencies in the bonds?  Is the bond form current?  Are all of the dates, including those on the Power-of-Attorney document current?  The last date on the Power-of-Attorney should be within the last six months to year.
  • Verify the bonds independently:   Contact the actual bonding company backing the bond, not the attorney-in-fact who signed the bond on behalf of the bonding company.  Research the contact information for the bonding company independently and don't rely on a phone number provided on the bond.  One California contractor set up a separate cell phone number they included on a forged bond in the event a public agency called to verify the bond.  Contact the surety to verify that the bond was appropriately issued by the attorney-in-fact.
Examples of bond forgeries:  Here are a couple of stories of forged bonds by contractors:
  • New Jersey contractor jailed for forgery.  Click here to read the entry from my blog on June 12, 2011.  
  • California contractor pleads guilty to forging payment and performance bonds.  Click here to read the entry from my blog on September 25, 2011.     
  • New York City contractor submits phony bonds to Housing Authority. Click here for details. 
  • Washington state contractor forges bonds. Click here for details.  
Note:  This blog posting is a repeat of one from October 29, 2012.
Mike Purdy's Public Contracting Blog 
© 2012-2013 by Michael E. Purdy Associates, LLC 
http://PublicContracting.blogspot.com

Tuesday, October 15, 2013

Training: Best Practices for Construction and Services Contracting

I will be providing two days of training in Anchorage, Alaska on Best Practices for Construction and Services Contracting, applicable to both the public and private sectors.

When:  November 7-8, 2013 (8:00 a.m. to 4:30 p.m.)

Where:  Anchorage, Alaska (Westmark Hotel)

Instructor:  Mike Purdy

Sponsored by:   NAPM Alaska

Contact me if you would like a copy of the outline of the training.

Mike Purdy's Public Contracting Blog 
© 2013 by Michael E. Purdy Associates, LLC 
http://PublicContracting.blogspot.com

Monday, October 14, 2013

Have You Changed Your Indemnification Clause in Your Contracts?


It's been more than a year since the Washington State Legislature amended the provisions for what is permitted in contracts regarding indemnification.  Has your agency updated the indemnification clause in your contracts?  This blog posting is a repeat of one from April 24, 2012 with only minor changes.

With strong backing and support from the professional design community, the Washington State Legislature approved in 2012 (with only one dissenting vote) Substitute House Bill 1559 related to indemnification provisions in public contracts. Then Governor Christine Gregoire signed the bill. 

Previous Law:  The purpose of the previous law in RCW 4.24.115 was to establish a standard of concurrent negligence in indemnification clauses.  In other words, a public agency may not require a contractor to indemnify the public agency against liability for damages "caused by or resulting from the sole negligence" of the public agency.  Instead, the previous law established that indemnification is valid and enforceable only to the extent of the concurrent negligence of the contractor and public agency. 

3 Changes in Law in 2012:  SHB 1559 amended RCW 4.24.115 in the following three areas:
  • Clarification of covered parties:  The previous law stated that it applied to a contract "relative to the construction, alteration, repair, addition to, subtraction from, improvement to, or maintenance of, any building, highway, road, railroad, excavation, or other structure, project, development, or improvement attached to real estate, including moving and demolition in connection..."  [emphasis added]  Many agencies interpreted the phrase "relative to" to include contracts for architectural, engineering, landscape architectural, and land surveying services, even though the language was not explicit.  SHB 1559 specifically added contracts for these four disciplines to the protections provided for in the law.
  • No duty to defend:  One of the regular sticking points in negotiating contracts with designers relates to whether the indemnification provided by the designer covers their duty to defend the public agency in the event of a claim.  SHB 1559 explicitly prohibits language in public contracts that includes the duty to defend and the cost of such defense.
  • Extent of indemnification:  The previous concurrent negligence standard was only applicable to liability for damages related to bodily injury and property damage.  Thus, for any other type of liability, a public agency could apply a sole negligence standard.  SHB 1559 changed this.  The concurrent negligence framework expanded to cover any liability arising out of any services performed on the contract.
Have you changed your contracts?  SHB 1559, approved in 2012, became effective on June 7, 2012.  Has your agency reviewed and changed indemnification language included in both construction contracts and contracts for architectural, engineering, landscape architectural, and land surveying services?

Talk with your attorney:  Indemnification is a complicated area and attorneys are best suited to sort through and develop appropriate contract language.  If you have not already done so, public agencies should consult with their attorneys for what language may need to change in their contracts. 

More Information:  Two Seattle area law firms have written helpful articles about SHB 1559 that may help in understanding this 2012 legislation:
Mike Purdy's Public Contracting Blog 
© 2013 by Michael E. Purdy Associates, LLC 
http://PublicContracting.blogspot.com

Sunday, October 13, 2013

Training: Bid Responsiveness and Bidder Responsibility

Bid Responsiveness and Bidder Responsibility:  Responsiveness and Responsibility.  They sound very similar but are very different concepts.  This training will provide key background information and examples on how public agencies should evaluate whether bids are responsive or non-responsive, and how to help ensure that the low bidder is a responsible bidder. 

Where and When:  Four training sessions in Washington state, all from 10:00 a.m. to 2:30 p.m.
  • Renton (October 31, 2013)
  • Yakima (November 5, 2013)
  • Camas (November 13, 2013)
  • Everett (November 21, 2013)
Cost:  Free 

Instructors:
  • Mike Purdy
  • John Carpita, MRSC
Sponsored by:
  • APWA Washington Chapter, Contract Administration Subcommittee
  • MRSC (Municipal Research and Services Center)
Information and registration:  Click here.

Mike Purdy's Public Contracting Blog
© 2013 by Michael E. Purdy Associates, LLC
http://PublicContracting.blogspot.com

Free Prevailing Wage Training in Spokane, Washington

Prevailing Wage Workshop for Awarding Agencies

Sponsored by:  Department of Labor and Industries and State Auditor's Office
 

Where:  Spokane Community College, Lair Student Center, 1810 N. Green Street, Spokane, WA 99217)
 
Cost:  Free

Date:  October 25, 2013 (9:30 a.m. to Noon)


Information and registration:  Contact Laura Herman at L&I at herq235@LNI.WA.GOV or at (360) 902-5311. 
Mike Purdy's Public Contracting Blog
© 2013 by Michael E. Purdy Associates, LLC
http://PublicContracting.blogspot.com

Thursday, October 10, 2013

Training: Construction Project Scheduling & Delay Claims

Construction Project Scheduling & Delay Claims

When:  October 25, 2013 (9:00 a.m. to 4:45 p.m.)

Where:  Seattle, Washington (City University, 521 Wall Street)

Instructors:

Agenda:
  • 30 Minutes to CPM Proficiency
  • Basic Scheduling Concepts for Delay, Acceleration and Mitigation
  • Primary Legal Concepts for Delay Claims
  • Cost Analysis for Schedule and Delay Claims
  • The Evolving Claims Landscape for Projects in Washington & Oregon
  • Contracting Strategies for Schedule Issues
  • Managing Schedule Delays and Claims on Complex Construction Projects
  • Dispute Resolution and Arbitration of Schedule & Delay Claims
Cost:
  • $425 - government employees
  • $525 - single registration
  • $500 - two or more registrations
  • See website for other prices
Information and registration: Click here.

Live Webcast:  This training is available via live webcast.  Click here for more information.