- All bids exceed the available funds,
- The apparent low responsive bid does not exceed the available funds by a) 5% on projects under $1 million, b) the greater of $50,000 or 2.5% for projects between $1 million and $5 million, or c) the greater of $125,000 or 1% for projects over $5 million, AND
- The negotiated adjustment will bring the bid price within the available funds.
Thursday, January 22, 2009
Legislation Would Expand Bid Negotiations to Municipalities
For a number of years, state agencies in Washington State have had the ability, under RCW 39.04.015 to negotiate with the low bidder on a public works project based on agreed changes to the plans and specifications under the following conditions: