On September 30, 2014, California Governor Jerry Brown
signed SB 785, clarifying and consolidating various Design-Build laws for public
construction contracts throughout the state.
Use by state and
local agencies: Specifically, the
new law provides for uniform Design-Build processes for certain state agencies,
cities, counties, and other local contracting districts for projects over $1
million. The law defines a number of common terms, and outlines a standard Design-Build
procurement process that includes either selection based on a low bid or a best
value approach. Click here for the legislative analysis of the bill that provides insight into the rationale for
SB 785.
Who supported and opposed the bill? The bill was supported by the AGC of California, some public
owners, and the Western Pacific Region of the Design-Build Institute of America.
It was opposed by some non-union contractor and subcontractor trade
associations.
What is Design-Build?
Design-Build is a project delivery method that places design and
construction services under one contract with a single point of responsibility.
Its advantages include reduced project costs, expedited project completion, and
better quality due to the integration of design and construction through one
firm. The Design-Build Institute of
America (DBIA) has written a Design-Build Done Right Primer that explains key concepts of this project delivery method.
Design-Build
nationwide: Rules for use of Design-Build vary from state to state. The Design-Build Institute of America has published a 2013 State Statute Report outlining Design-Build laws in various states.
Managing Design-Build
contracts: Design-Build can be an
effective tool for some projects, but it is very important that a public
agency selects the right Design-Build partner for the project. Here are some key guidelines related to the
selection process:
- Think through the selection process carefully up
front, including evaluating likely proposers and how the process and point
allocation may impact the end result.
- Based on the particular project, evaluate the
appropriate allocation of points between qualifications/technical merit
and price.
- Don’t
change the selection process mid-stream through the procurement. This can
lead to protests and delays for the project.
- If the
agency does not have personnel with specific Design-Build experience, obtain
the services of a qualified consultant to guide the agency though the
project.