A 5 inch surveying error has resulted in a misalignment of a concrete ramp being built in Seattle by PCL Construction.
After assessing its options, PCL decided to tear down 160 feet of concrete and start over, a mistake that will cost the company between $20,000 and $25,000. The ramp is part of work being performed on the South Spokane Street Viaduct.
Click here for an article from the Seattle Times with more details.
Mike Purdy's Public Contracting Blog© 2011 by Michael E. Purdy Associates, LLChttp://PublicContracting.blogspot.com
No comments:
Post a Comment