Just a reminder that RCW 39.04.105, which applies to municipalities (cities, counties, towns, districts, other public agencies - See RCW 39.04.010 for definition), establishes a procedure for how to deal with bid protests on public works projects.
Protest must be submitted in writing no later than two full business days following bid opening.
Municipality can't execute contract with any other bidder than the protesting bidder without providing at least two full business days' written notice of the intent to execute a contract for the project.
It's a good idea to make sure you have protest procedures in your bidding documents that are consistent with the State law.